# Use-Case / TCO — Airport GSE Solar 300 kWp (AU)

**Verdict: NPV = AUD 1,233,185 (positive) over a 25-year horizon at a 7.00% discount rate; simple payback 3.28 yr, discounted payback 3.84 yr; LCOE AUD 0.0886/kWh.** Equipment: 518 × LONGi Hi-MO 7 LR7-72HGD bifacial modules on Schletter Fix Z-Prof mounting, 2 × Sungrow SG125HT three-phase string inverters (250 kW AC total). Location: Australian regional airport (Ausgrid distribution area, NSW). Horizon: 25 years. Discount rate: 7.00% nominal. Evidence date: 2024-11-15. Limitation: site-specific specific-yield (1,580 kWh/kWp/yr) is a bounded model assumption; replace with a Solcast / PVsyst site simulation before financial close.

Decision summary (computed) | Metric | Value |
| --- | --- |
| Currency | AUD (nominal) |
| Horizon (years) | 25 |
| Discount rate | 7.00 % |
| Total undiscounted cost (AUD) | 591,170.44 |
| Total discounted cost / PV of costs (AUD) | 469,477.90 |
| Total undiscounted benefit (AUD) | 3,972,941.68 |
| Total discounted benefit (AUD) | 1,702,662.73 |
| NPV (AUD) | 1,233,184.83 |
| IRR | 0.3193 |
| Simple payback (year) | 3.28 |
| Discounted payback (year) | 3.84 |
| LCOE (AUD/kWh) | 0.0886 |

## 1. Inputs Table

| Input | Value | Unit | Source |
| --- | --- | --- | --- |
| System size (DC nameplate) | 300.44 (518 × 580 W) | kWp | LONGi Hi-MO 7 module family |
| Module family / model | LONGi Hi-MO 7 (HPBC 2.0 back-contact; LR7-72HGD) | — | LONGi Hi-MO 7 product page (610 W, up to 24.8% efficiency) |
| Inverter family / model | Sungrow SG125HT (×2, 250 kW AC total) | — | Sungrow string inverter range (incl. SG125HT C&I 3-phase) |
| Mounting system | Schletter Fix Z-Prof (AS/NZS 5033:2021 compliant clamp; install manual Rev. 04-2023) | — | Schletter Group fixed-tilt systems category — exact manual revision confirmed at RFQ |
| Module datasheet warranty (linear) | 12-yr product / 30-yr linear power; bifaciality up to 80% | — | LONGi Hi-MO 7 datasheet |
| Performance ratio (PR) | 0.85 | — | CEC Products Program (PR band 0.80–0.90 typical for AU commercial rooftop) — bounded assumption |
| Specific yield, AU airport site | 1,580 | kWh/kWp/yr | Bounded model assumption — replace with site Solcast TMY before financial close |
| CapEx (turnkey rooftop) | 1,250 | AUD/kWp | CEC commercial rooftop cost guidance 2024 — bounded assumption within ±10% |
| Fixed OpEx (O&M + insurance) | 1.5 | % of CapEx/yr | Bounded model assumption |
| Inverter replacement (year 12) | 120 | AUD/kWp | Sungrow SG-HT service manual (capacitor-replace interval) + bounded assumption |
| Blended commercial tariff (Ausgrid EA029) | 0.28 | AUD/kWh | Ausgrid business & commercial tariffs (EA029 BLNT2AU, incl. GST) |
| Tariff escalation | 3.0 | %/yr | Bounded assumption — RBA target-band midpoint |
| Module degradation | 0.5 | %/yr | Bounded assumption consistent with LONGi linear-power warranty |
| Discount rate (WACC, nominal) | 7.0 | %/yr | Bounded assumption within AER nominal WACC band |
| Analysis horizon | 25 | years | Bounded assumption consistent with PV module linear-warranty term |
| Self-consumption share (model default) | 85 | % of generation | Bounded model assumption (GSE chargers operate daytime — to be confirmed by site load profile) |
| Export tariff (model default) | 0.05 | AUD/kWh | Bounded model assumption — small-export FiT band NSW 2024 |
| Residual value (model default) | 0.00 | AUD | Bounded model assumption (conservative, set to zero at year 25) |
| Residual value year (model default) | 25 | year | Bounded model assumption (end-of-horizon) |

## 2. TCO Summary (verbatim from scenario model)

TCO summary | Metric | Value |
| --- | --- |
| Currency | AUD |
| Horizon (years) | 25 |
| Discount rate | 7.00 % |
| Total undiscounted cost (AUD) | 591,170.44 |
| Total discounted cost / PV of costs (AUD) | 469,477.90 |
| Total undiscounted benefit (AUD) | 3,972,941.68 |
| Total discounted benefit (AUD) | 1,702,662.73 |
| NPV (AUD) | 1,233,184.83 |
| IRR | 0.3193 |
| Simple payback (year) | 3.28 |
| Discounted payback (year) | 3.84 |
| LCOE (AUD/kWh) | 0.0886 |

## 3. Computed Cash-Flow Table (verbatim from scenario model)

Year-by-year cash flow | Year | Cost (AUD) | Benefit (AUD) | Net (AUD) | Discount factor | Discounted net (AUD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 375,000.00 | 0.0000 | -375,000.00 | 1.00 | -375,000.00 | 0.0000 |
| 1 | 5,625.00 | 116,537.67 | 110,912.67 | 0.9346 | 103,656.70 | 474,695.20 |
| 2 | 5,737.50 | 119,433.63 | 113,696.13 | 0.8734 | 99,306.61 | 472,321.72 |
| 3 | 5,852.25 | 122,401.56 | 116,549.31 | 0.8163 | 95,138.95 | 469,960.12 |
| 4 | 5,969.30 | 125,443.24 | 119,473.94 | 0.7629 | 91,146.10 | 467,610.31 |
| 5 | 6,088.68 | 128,560.50 | 122,471.82 | 0.7130 | 87,320.72 | 465,272.26 |
| 6 | 6,210.45 | 131,755.23 | 125,544.78 | 0.6663 | 83,655.78 | 462,945.90 |
| 7 | 6,334.66 | 135,029.35 | 128,694.68 | 0.6227 | 80,144.58 | 460,631.17 |
| 8 | 6,461.36 | 138,384.83 | 131,923.47 | 0.5820 | 76,780.66 | 458,328.02 |
| 9 | 6,590.58 | 141,823.69 | 135,233.11 | 0.5439 | 73,557.85 | 456,036.38 |
| 10 | 6,722.40 | 145,348.01 | 138,625.61 | 0.5083 | 70,470.23 | 453,756.19 |
| 11 | 6,856.84 | 148,959.91 | 142,103.06 | 0.4751 | 67,512.14 | 451,487.41 |
| 12 | 42,993.98 | 152,661.56 | 109,667.58 | 0.4440 | 48,693.72 | 449,229.98 |
| 13 | 7,133.86 | 156,455.20 | 149,321.34 | 0.4150 | 61,963.05 | 446,983.83 |
| 14 | 7,276.54 | 160,343.11 | 153,066.57 | 0.3878 | 59,361.86 | 444,748.91 |
| 15 | 7,422.07 | 164,327.64 | 156,905.57 | 0.3624 | 56,869.80 | 442,525.16 |
| 16 | 7,570.51 | 168,411.18 | 160,840.67 | 0.3387 | 54,482.30 | 440,312.54 |
| 17 | 7,721.92 | 172,596.20 | 164,874.28 | 0.3166 | 52,194.97 | 438,110.97 |
| 18 | 7,876.36 | 176,885.21 | 169,008.86 | 0.2959 | 50,003.62 | 435,920.42 |
| 19 | 8,033.89 | 181,280.81 | 173,246.93 | 0.2765 | 47,904.22 | 433,740.82 |
| 20 | 8,194.56 | 185,785.64 | 177,591.08 | 0.2584 | 45,892.91 | 431,572.11 |
| 21 | 8,358.45 | 190,402.41 | 182,043.96 | 0.2415 | 43,966.00 | 429,414.25 |
| 22 | 8,525.62 | 195,133.91 | 186,608.29 | 0.2257 | 42,119.95 | 427,267.18 |
| 23 | 8,696.14 | 199,982.99 | 191,286.85 | 0.2109 | 40,351.37 | 425,130.85 |
| 24 | 8,870.06 | 204,952.57 | 196,082.51 | 0.1971 | 38,657.00 | 423,005.19 |
| 25 | 9,047.46 | 210,045.64 | 200,998.18 | 0.1842 | 37,033.75 | 420,890.17 |

## 4. Scenario Verdict

- **Baseline (e = 3.0%, WACC = 7.0%):** NPV AUD 1,233,185; simple payback 3.28 yr; discounted payback 3.84 yr; LCOE 0.0886 AUD/kWh. Strongly positive business case across all 25 yr; payback within the inverter-replacement cycle leaves a clear safety margin.

- Site-specific specific yield (1,580 kWh/kWp/yr), self-consumption share (85%), and inverter-replacement cost (AUD 120/kWp in year 12) are bounded model assumptions and must be re-confirmed by a site-specific yield simulation (Solcast TMY / PVsyst) and a fixed-price O&M contract before financial close.

## 5. Cert & Compliance Block

- Module qualification: IEC 61215-1:2021 ed2 (Terrestrial PV modules — Design qualification and type approval — Part 1: Test requirements) and IEC 61730-1/-2 (PV module safety) per the [IEC 61215-1:2021 ed2 webstore listing](https://webstore.iec.ch/en/publication/61345).

- Power-converter safety: IEC 62109-1:2010 (Safety of power converters for PV — General requirements) per the [IEC 62109-1:2010 webstore listing](https://webstore.iec.ch/en/publication/6470).

- UL PV-module safety (US-bound shipments): UL 61730-1 per the [UL 61730-1 product page](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1).

- Installation: AS/NZS 5033:2021 (PV array installation). Install per the Schletter Fix Z-Prof manual; clamp torque values per Section 4.2 (manual revision confirmed at RFQ).

- Inverter connection: AS/NZS 4777.2:2020. Verify that the Sungrow SG125HT is on the [CEC approved inverters list](https://cleanenergycouncil.org.au/industry/products/inverters) at commissioning.

- STC eligibility: both module and inverter must appear on the [CEC Products Program approved lists](https://cleanenergycouncil.org.au/industry-programs/products-program) current at commissioning.

- Battery / transport of lithium: UN Manual of Tests and Criteria, Section 38.3 (UN 38.3), per the [UN Manual of Tests and Criteria canonical page](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria) — applicable to GSE battery chargers, not to the PV array itself.

## 6. HS Code & Tariff Block (lookup instructions)

| Component | HS subheading | Tariff lookup tool | Duty rate (AU MFN) |
| --- | --- | --- | --- |
| Crystalline-Si PV modules | 8541.43 | ABF current tariff lookup | 0% (free, MFN) — confirm subheading & any FTA preference |
| String inverters (> 1 kW) | 8504.40 | ABF current tariff lookup | 0% (free, MFN) |
| PV-rated DC cable | 8544.60 | ABF current tariff lookup | 0% (free, MFN) |
| Aluminium mounting structure | 7610.90 | ABF current tariff lookup | 5% (verify FTA preference) |
| Steel mounting structure | 7308.20 | ABF current tariff lookup | 5% (verify FTA preference) |
| DC combiners / isolators | 8536.90 | ABF current tariff lookup | 0% (free, MFN) |

**Lookup instructions:** confirm the exact subheading and any FTA preferential rate (e.g. KAFTA, AANZFTA, CPTPP, RCEP, ChAFTA) on the ABF tariff-lookup tool before quoting a landed cost. PV modules under HS 8541.43 are free of MFN duty in Australia; aluminium mounting under 7610.90 attracts 5% MFN unless an FTA preference applies. For non-AU destinations use the corresponding national lookup tool: [USITC HTS (US)](https://hts.usitc.gov/), [UK Global Tariff](https://www.trade-tariff.service.gov.uk/), [EU TARIC](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en), [Japan Customs](https://www.customs.go.jp/english/), [NZ Customs Working Tariff](https://www.customs.govt.nz/business/tariffs/working-tariff-document/), [SARS (ZA)](https://www.sars.gov.za/), [GRA (GH)](https://gra.gov.gh/), [URA (UG)](https://www.ura.go.ug/).

**Disclaimer:** TradVolt does not provide legal or customs advice. HS classifications and duty rates are the importer's responsibility and must be confirmed with a licensed customs broker or the Australian Border Force. Numbers in this article are engineering estimates for an indicative TCO and are not a financial recommendation.