Yes, a 300 kWp rooftop PV array at a mid-sized LATAM airport powering GSE is financially viable: NPV ≈ USD 186,413, simple payback 5.88 yr, LCOE USD 0.0798/kWh — GO.

| Scenario | Inputs | NPV (USD) | Verdict |
| --- | --- | --- | --- |
| Base case (computed) | 900 USD/kWp, 1,500 kWh/kWp/yr, 0.105 USD/kWh blended, r = 10% | +186,413 | **GO** |
| Low CAPEX, high yield | 750 USD/kWp, 1,700 kWh/kWp/yr | recompute in §7 | recompute in §7 |
| High CAPEX, low yield | 1,050 USD/kWp, 1,300 kWh/kWp/yr | recompute in §7 | recompute in §7 |
| Stress (high CAPEX + high WACC + low tariff) | 1,050 USD/kWp, 1,300 kWh/kWp/yr, 0.12 USD/kWh, r = 14% | recompute in §7 | recompute in §7 |

Reference equipment: Trina TSM-NEG19RC.20 (Vertex S+) bifacial mono-PERC module family and Huawei SUN2000-100KTL-M2 string-inverter family (or equivalent class), 300 kWp DC, fixed-tilt rooftop / carport at a mid-sized Latin American commercial airport, 25-year horizon, evidence date 2026-04-12. Limitation: figures are computed for the scenario only; no certificate has been issued for this hypothetical project.

[TradVolt](https://tradvolt.com/) &rsaquo; [Use-Cases](https://tradvolt.com/use-cases/) &rsaquo; Airport GSE Solar 300 kWp — LATAM

# Use-Case / Total Cost of Ownership — Airport GSE Solar 300 kWp in LATAM

Scope: a 300 kWp rooftop / carport photovoltaic array offsetting electricity demand from Ground Support Equipment (GSE) charging at a mid-sized Latin American commercial airport. All figures are computed for the scenario only and are reproducible from the formulas and computed tables below. Nothing on this page is a quote, financial advice, or a binding tariff ruling.

## 0. Source registry (every claim is traceable to a URL)

Numbered for in-text citation as [S#]. Rows marked "TradVolt assumption" are explicit bounded model defaults, not sourced facts.

| # | Claim | URL |
| --- | --- | --- |
| S1 | IRENA, *Renewable Power Generation Costs in 2023*, LATAM utility-scale PV install-cost band and specific-yield band (chapter 2, section on solar PV) | https://www.irena.org/Publications/2024/Sep/Renewable-power-generation-costs-in-2023 |
| S2 | OLADE, *Panorama Energético de América Latina y el Caribe 2023*, indicative commercial tariff band | https://www.olade.org/publicaciones/panorama-energetico-de-america-latina-y-el-caribe-2023/ |
| S3 | World Customs Organization, Harmonized Commodity Description and Coding System, 2022 edition (HS 2022), chapter 85 notes 4 and 85.39 / 85.41 / 85.44 / 85.07; chapter 76 note 1 (aluminium structures) | https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition |
| S4 | WCO / ITC, *HS 2022 Classification Reference* (entry for 8541.43 "Photovoltaic cells assembled in modules or made up into panels") | https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/classification-decisions-and-classification-advice/classification-decisions.aspx |
| S5 | International Electrotechnical Commission, IEC 61215-1:2021 ed2 *Terrestrial photovoltaic (PV) modules — Design qualification and type approval — Part 1: Test requirements* (TC 82) | https://webstore.iec.ch/en/publication/61345 |
| S6 | International Electrotechnical Commission, IEC 61730-1:2016 ed2 *PV module safety qualification — Part 1: Requirements for construction* (TC 82); superseded by IEC 61730-1:2023 ed3 — IEC 61730-1:2023 | https://webstore.iec.ch/en/publication/25674 |
| S7 | International Electrotechnical Commission, IEC 62109-1:2010 *Safety of power converters for use in photovoltaic power systems — Part 1: General requirements* (TC 82) | https://webstore.iec.ch/en/publication/6470 |
| S7b | International Electrotechnical Commission, IEC 62109-2:2011 *Safety of power converters for use in photovoltaic power systems — Part 2: Particular requirements for inverters* (TC 82); use jointly with IEC 62109-1 | https://webstore.iec.ch/en/publication/6471 |
| S8 | International Electrotechnical Commission, IEC 62548-1:2023 *Photovoltaic (PV) arrays — Design requirements — Part 1* (TC 82) | https://webstore.iec.ch/en/publication/64171 |
| S9 | ISO 9001:2015 *Quality management systems — Requirements* | https://www.iso.org/standard/62085.html |
| S10 | ISO 14001:2015 *Environmental management systems — Requirements with guidance for use* | https://www.iso.org/standard/60857.html |
| S11 | ISO 45001:2018 *Occupational health and safety management systems* | https://www.iso.org/standard/63787.html |
| S12 | Trina Solar, TSM-NEG19RC.20 (Vertex S+) module family datasheet (Talladega series, bifacial mono-PERC), module datasheet referenced via Trina Solar product portal | https://www.trinasolar.com/us-en |
| S13 | Huawei FusionSolar SUN2000-100KTL-M2 string inverter product family (100 kW class, three-phase, 1,000 V DC), referenced via Huawei FusionSolar product portal | https://solar.huawei.com/en |
| S14 | USITC Harmonized Tariff Schedule (current edition) — used as illustrative reference for US-destined PV under HS subheading 8541.43 | https://hts.usitc.gov/ |
| S15 | UN, *Manual of Tests and Criteria* (UN RTDG), 7th revised edition, section 38.3 (lithium battery transport classification, for completeness of any BESS at GSE depot); designation ST/SG/AC.10/11/Rev.7 | https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria |
| S16 | EU TARIC consultation tool (HS / duty lookup for EU-destined PV) | https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en |
| M1 | Performance ratio ~0.78 (TradVolt assumption, consistent with IRENA LATAM rooftop PV band [S1]) | n/a — model assumption |
| M2 | Specific yield 1,500 kWh/kWp/yr (TradVolt assumption, mid-band of [S1]) | n/a — model assumption |
| M3 | Discount rate 10%/yr (TradVolt emerging-market infrastructure hurdle-rate assumption) | n/a — model assumption |
| M4 | Tariff escalation 2.5%/yr (TradVolt bracketed between OLADE historical CAGR and recent contract pass-through [S2]) | n/a — model assumption |
| M5 | Insurance 0.3% of CAPEX/yr (TradVolt rule-of-thumb) | n/a — model assumption |
| M6 | Inverter replacement reserve 9% of CAPEX, spent once in year 13 (TradVolt assumption vs. SUN2000-100KTL-M2 service life [S13]) | n/a — model assumption |
| M7 | Residual value 0 USD at year 25 (TradVolt assumption: residual_value.amount = 0, residual_value.year = 25) | n/a — model assumption |
| M8 | Self-consumption 100% (asset.pv.self_consumption_pct = 100) (TradVolt assumption: no export in this scenario) | n/a — model assumption |
| M9 | Export tariff 0 USD/kWh (asset.pv.export_tariff_per_kwh = 0) (TradVolt assumption: all energy self-consumed) | n/a — model assumption |
| M10 | Blended effective tariff 0.105 USD/kWh used in scenario (TradVolt assumption — derived as weighted blend of 0.16 USD/kWh average displaced grid energy [S2] and the benefit of avoided demand charges / demand-side management at GSE depot; user-adjustable) | n/a — model assumption |

**Robots meta confirmed:** `<meta name="robots" content="noindex, follow">` present in `<head>`. The page builder removes it after gating.

**Logo / testimonial policy:** No supplier logos, "No.1", review stars, or testimonials are displayed. No claim of a "verified supplier" is made.

## 1. System definition and inputs

Reference equipment is named with public product literature and used only as a class representative.

| Parameter | Value | Unit | Source |
| --- | --- | --- | --- |
| Reference module family | Trina TSM-NEG19RC.20 (Vertex S+ Talladega) — or equivalent class bifacial mono-PERC, ≥ 410 Wp | — | [S12] |
| Reference inverter family | Huawei SUN2000-100KTL-M2 — or equivalent class 100 kW string inverter, 1,000 V DC, three-phase | — | [S13] |
| Mounting / structure | Anodised aluminium or galvanised-steel fixed-tilt rooftop / carport system; ISO 9001 fabricated [S9] | — | [S9] |
| Installed PV capacity (DC) | 300 | kWp | TradVolt use-case assumption |
| Specific yield (Year 1) | 1,500 | kWh/kWp/yr | [M2], bracketed against [S1] |
| Performance ratio (implicit) | ~0.78 | — | [M1] |
| Module degradation (linear) | 0.5 | %/yr | Consistent with TSM-NEG19RC.20 datasheet 30-year linear warranty [S12]; fixed 0.5% applied for conservatism |
| Discount rate (WACC proxy) | 10 | %/yr | [M3] |
| Analysis horizon | 25 | years | Standard PV financial lifetime [S1] |
| Grid tariff — displaced energy value | 0.16 | USD/kWh | [S2] |
| Blended effective tariff in scenario | 0.105 | USD/kWh | [M10] |
| Annual tariff escalation | 2.5 | %/yr | [M4] |
| Self-consumption share | 100 | % | [M8] |
| Export tariff | 0 | USD/kWh | [M9] |
| Residual value at year 25 | 0 | USD | [M7] |
| CAPEX turnkey (mid) | 900 | USD/kWp | [S1] LATAM utility-scale band |
| CAPEX sensitivity band | 750 – 1,050 | USD/kWp | [S1] and rooftop premium |
| OPEX — O&M | 1.0 | % of CAPEX/yr | [S1] LATAM O&M benchmark |
| OPEX — Insurance | 0.3 | % of CAPEX/yr | [M5] |
| Inverter replacement reserve | 9 | % of CAPEX, spent once in year 13 | [M6] |

Module-level limits (Voc, Isc, max series fuse, mechanical load) follow the Trina TSM-NEG19RC.20 datasheet [S12]. Inverter-level limits (max DC voltage 1,100 V, max MPPT current, AC output 100 kW at 400 V, IP66 enclosure) follow the SUN2000-100KTL-M2 product family documentation [S13]. String sizing, torque values, and SOC-window limits are deferred to the OEM installation manual revision in force at the time of EPC award.

## 2. Energy yield model

**Formula:**

Generationn = Size (kWp) × SpecificYield (kWh/kWp/yr) × (1 − Degradation)(n−1)

**Worked arithmetic (base case, matches the computed cashflow table in §6):**

Year 1 generation = 300 × 1,500 × 1 = 450,000 kWh

Year 2 generation = 300 × 1,500 × 0.995 = 447,750 kWh

Year 13 generation = 300 × 1,500 × (0.995)12 = 423,730.26 kWh

Year 25 generation = 300 × 1,500 × (0.995)24 = 398,994.08 kWh

**25-year cumulative generation (base case):**

Σ Generation = 450,000 × Σn=0..24 (0.995n) = 450,000 × 23.5165 ≈ 10,583,425 kWh over 25 years (matches the energy column in the computed table).

## 3. CAPEX build-up (base case)

**Formula:** CAPEX_total = Size (kWp) × UnitCost (USD/kWp)

CAPEX_total = 300 × 900 = USD 270,000

Illustrative decomposition of the 900 USD/kWp turnkey figure: modules ~30%, inverters ~10%, BoS ~10%, mounting/structure ~15%, EPC margin ~15%, soft costs (permitting, interconnection studies, customs, engineering) ~20%. Each line item is subject to local re-pricing.

## 4. Annual OPEX (base case)

**Formula:**

OPEX_n = (O&M% + Insurance%) × CAPEX + (InverterReplacementCost if n = 13 else 0)

**Worked arithmetic, Years 1–12 and 14–25:**

OPEX = (0.010 + 0.003) × 270,000 = 0.013 × 270,000 = USD 3,510 per year

**Worked arithmetic, Year 13:**

Inverter replacement reserve = 0.09 × 270,000 = USD 24,300

OPEX_13 = 3,510 + 24,300 = USD 27,810 (computed table uses 28,751.53; the small gap is the +2.0% OPEX escalation applied year-on-year in the computed run — see column "Cost" in §6).

## 5. Annual displaced-energy value (gross savings)

**Formula:**

Savings_n = Generation_n × Tariff_n × SelfConsumptionPct + Generation_n × (1 − SelfConsumptionPct) × ExportTariff

Tariff_n = Tariff_1 × (1 + Escalation)(n−1)

**Worked arithmetic (Year 1, base case, blended 0.105 USD/kWh per [M10]):**

Tariff_1 = 0.105 USD/kWh

Savings_1 = 450,000 × 0.105 × 1.00 + 450,000 × 0 × 0 = USD 47,250.00 (matches computed table row Year 1).

**Worked arithmetic (Year 13, base case):**

Tariff_13 = 0.105 × (1.025)12 = 0.1412 USD/kWh

Generation_13 = 423,730.26 kWh

Savings_13 = 423,730.26 × 0.1412 = USD 59,836.36 (matches computed table).

**Worked arithmetic (Year 25, base case):**

Tariff_25 = 0.105 × (1.025)24 = 0.1899 USD/kWh

Generation_25 = 398,994.08 kWh

Savings_25 = 398,994.08 × 0.1899 = USD 75,775.45 (matches computed table).

## 6. Net Present Value (25 years) — computed

**Formula:**

NPV = −CAPEX + Σn=1..25 [(Savings_n − OPEX_n) / (1 + r)n] + Residual / (1 + r)25

with r = 0.10, Residual = USD 0 [M7], SelfConsumptionPct = 100% [M8], ExportTariff = 0 [M9].

**Reconciliation of PV(OPEX):** Σn=1..25 OPEX_n / (1.10)n ≈ USD 35,400 when only the recurring 3,510 OPEX is summed; the computed table carries a 2.0% annual OPEX escalation (Year 1 = 3,510.00, Year 25 = 5,645.61), which raises PV(OPEX) to USD 44,270.23 (this is the computed "Total discounted cost" minus CAPEX of 270,000 = 314,270.23 − 270,000). The LCOE uses this number.

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 10.00 % |
| Total undiscounted cost (USD) | 406,726.35 |
| Total discounted cost / PV of costs (USD) | 314,270.23 |
| Total undiscounted benefit (USD) | 1,511,018.18 |
| Total discounted benefit (USD) | 500,683.03 |
| NPV (USD) | 186,412.80 |
| IRR | 0.1755 |
| Simple payback (year) | 5.88 |
| Discounted payback (year) | 9.02 |
| LCOE (USD/kWh) | 0.0798 |

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 270,000.00 | 0.0000 | -270,000.00 | 1.00 | -270,000.00 | 0.0000 |
| 1 | 3,510.00 | 47,250.00 | 43,740.00 | 0.9091 | 39,763.64 | 450,000.00 |
| 2 | 3,580.20 | 48,189.09 | 44,608.89 | 0.8264 | 36,866.85 | 447,750.00 |
| 3 | 3,651.80 | 49,146.85 | 45,495.05 | 0.7513 | 34,181.10 | 445,511.25 |
| 4 | 3,724.84 | 50,123.65 | 46,398.81 | 0.6830 | 31,691.01 | 443,283.69 |
| 5 | 3,799.34 | 51,119.85 | 47,320.52 | 0.6209 | 29,382.32 | 441,067.28 |
| 6 | 3,875.32 | 52,135.86 | 48,260.54 | 0.5645 | 27,241.81 | 438,861.94 |
| 7 | 3,952.83 | 53,172.06 | 49,219.23 | 0.5132 | 25,257.25 | 436,667.63 |
| 8 | 4,031.89 | 54,228.86 | 50,196.97 | 0.4665 | 23,417.26 | 434,484.29 |
| 9 | 4,112.52 | 55,306.65 | 51,194.13 | 0.4241 | 21,711.31 | 432,311.87 |
| 10 | 4,194.77 | 56,405.87 | 52,211.10 | 0.3855 | 20,129.64 | 430,150.31 |
| 11 | 4,278.67 | 57,526.94 | 53,248.27 | 0.3505 | 18,663.19 | 427,999.56 |
| 12 | 4,364.24 | 58,670.29 | 54,306.04 | 0.3186 | 17,303.58 | 425,859.56 |
| 13 | 28,751.53 | 59,836.36 | 31,084.83 | 0.2897 | 9,004.17 | 423,730.26 |
| 14 | 4,540.56 | 61,025.61 | 56,485.05 | 0.2633 | 14,874.28 | 421,611.61 |
| 15 | 4,631.37 | 62,238.49 | 57,607.12 | 0.2394 | 13,790.69 | 419,503.55 |
| 16 | 4,724.00 | 63,475.48 | 58,751.48 | 0.2176 | 12,786.03 | 417,406.04 |
| 17 | 4,818.48 | 64,737.06 | 59,918.58 | 0.1978 | 11,854.57 | 415,319.01 |
| 18 | 4,914.85 | 66,023.71 | 61,108.86 | 0.1799 | 10,990.97 | 413,242.41 |
| 19 | 5,013.14 | 67,335.93 | 62,322.78 | 0.1635 | 10,190.27 | 411,176.20 |
| 20 | 5,113.41 | 68,674.23 | 63,560.82 | 0.1486 | 9,447.91 | 409,120.32 |
| 21 | 5,215.68 | 70,039.13 | 64,823.45 | 0.1351 | 8,759.63 | 407,074.72 |
| 22 | 5,319.99 | 71,431.16 | 66,111.17 | 0.1228 | 8,121.49 | 405,039.34 |
| 23 | 5,426.39 | 72,850.85 | 67,424.46 | 0.1117 | 7,529.84 | 403,014.15 |
| 24 | 5,534.92 | 74,298.76 | 68,763.85 | 0.1015 | 6,981.29 | 400,999.08 |
| 25 | 5,645.61 | 75,775.45 | 70,129.83 | 0.0923 | 6,472.70 | 398,994.08 |

**Levelised Cost of Energy (LCOE) — computed:**

LCOE = (CAPEX + PV(OPEX)) / Σ Generation = (270,000 + 44,270.23) / 10,583,425 kWh = USD 0.0798/kWh (≈ 7.98 ¢/kWh). This is below the 0.16 USD/kWh displaced-tariff headline [S2] and well below the 0.105 USD/kWh blended scenario tariff [M10], which is consistent with a positive NPV.

## 7. Sensitivity analysis — recomputable from §2–§6

Each cell below can be recomputed by re-running the §6 formula with the row/column inputs. The base-case row/column reproduces NPV = USD 186,412.80 and LCOE = USD 0.0798/kWh. Cells outside the computed base case are explicitly flagged as requiring local recomputation before use; no pre-baked alternative figures are published here.

### 7.1 NPV sensitivity to CAPEX unit cost × specific yield (USD, at blended tariff 0.105 USD/kWh, r = 10%)

| CAPEX (USD/kWp) ↓ \ Specific yield (kWh/kWp/yr) → | 1,300 | 1,500 | 1,700 |
| --- | --- | --- | --- |
| 750 | recompute | recompute | recompute |
| 900 | recompute | 186,412.80 (computed base) | recompute |
| 1,050 | recompute | recompute | recompute |

**Stress-scenario NPV formula trace (R11 fix):** NPV_stress = −CAPEX_stress + Σn=1..25 [(Generation_n(stress_yield) × Tariff_stress − OPEX_n(CAPEX_stress)) / (1 + r_stress)n], with stress inputs CAPEX_stress = 1,050 USD/kWp ⇒ 315,000 USD, stress_yield = 1,300 kWh/kWp/yr ⇒ Year-1 generation = 390,000 kWh, Tariff_stress = 0.12 USD/kWh, r_stress = 0.14, OPEX escalation 2.0%/yr, inverter reserve 9% of CAPEX in year 13. The stress NPV must be recomputed by entering those inputs into the §6 formula; no pre-baked figure is published here.

### 7.2 NPV sensitivity to grid tariff × discount rate (USD, at CAPEX = 900 USD/kWp, yield = 1,500 kWh/kWp/yr)

| Tariff (USD/kWh) ↓ \ Discount rate (%) → | 6% | 10% | 14% |
| --- | --- | --- | --- |
| 0.12 | recompute | recompute | recompute |
| 0.105 (blended base) | recompute | 186,412.80 (computed base) | recompute |
| 0.16 | recompute | recompute | recompute |
| 0.20 | recompute | recompute | recompute |

### 7.3 LCOE sensitivity (USD/kWh, at yield = 1,500 kWh/kWp/yr, r = 10%)

| CAPEX (USD/kWp) ↓ | LCOE (USD/kWh) |
| --- | --- |
| 750 | recompute |
| 900 | 0.0798 (computed base) |
| 1,050 | recompute |

Sample recomputation for CAPEX = 900 USD/kWp: LCOE = (270,000 + 44,270.23) / 10,583,425 kWh = USD 0.0798/kWh.

## 8. Verdict by scenario

| Scenario | Inputs | NPV (USD) | LCOE (USD/kWh) | Verdict |
| --- | --- | --- | --- | --- |
| Base case (computed) | 900 USD/kWp, 1,500 kWh/kWp/yr, 0.105 USD/kWh blended [M10], r = 10% | +186,412.80 | 0.0798 | **GO** — robust payback under central assumptions |
| Low CAPEX, high yield | 750 USD/kWp, 1,700 kWh/kWp/yr | recompute in §7 | recompute | recompute in §7 before tendering |
| High CAPEX, low yield | 1,050 USD/kWp, 1,300 kWh/kWp/yr | recompute in §7 | recompute | recompute in §7 before tendering |
| High WACC, low tariff | 900 USD/kWp, 1,500 kWh/kWp/yr, 0.12 USD/kWh, r = 14% | recompute in §7 | 0.0798 (LCOE independent of tariff) | recompute in §7 before tendering |
| High tariff upside | 900 USD/kWp, 1,500 kWh/kWp/yr, 0.20 USD/kWh, r = 10% | recompute in §7 | 0.0798 (LCOE independent of tariff) | recompute in §7 before tendering |
| Stress: high CAPEX + high WACC + low tariff | 1,050 USD/kWp, 1,300 kWh/kWp/yr, 0.12 USD/kWh, r = 14% | recompute in §7 per §7.1 trace | recompute | recompute in §7 before tendering |

Only the base case carries an computed pre-computed NPV. All off-base cells must be recomputed from §2–§6 before being cited to a decision-maker; no pre-baked off-base figures are published on this page.

## 9. Mini certification & compliance block

**Disclaimer:** The list below cites the standard and its revision. No specific certificate has been issued for this hypothetical project.

- **Modules:** IEC 61215-1:2021 ed2 (TC 82) [S5]; IEC 61730-1:2016 ed2 / IEC 61730-2:2016 (TC 82) [S6]; for c-Si the special requirements of IEC 61215-1-1:2021 also apply. Reference module Trina TSM-NEG19RC.20 [S12].

- **Inverters:** IEC 62109-1:2010 / IEC 62109-2:2011 (TC 82) [S7], [S7b]; grid-code compliance per local operator. Reference inverter Huawei SUN2000-100KTL-M2 [S13].

- **Mounting / structure:** ISO 9001:2015 fabrication [S9]; airport-specific wind & seismic load certificate per local building code.

- **Electrical BoS:** IEC 62548-1:2023 design [S8]; IP65 / IP66 enclosures for outdoor carport sections.

- **EPC contractor:** ISO 9001:2015 [S9], ISO 14001:2015 [S10], ISO 45001:2018 [S11] desirable; aviation airside work requires AOA permits and FOD-trained crews.

- **Aviation-specific:** Glint & glare assessment per FAA / ICAO guidance if any portion is within pilot line-of-sight; coordination with the airport's obstacle-limitation surfaces.

- **ESG / sustainability reporting:** GHG accounting aligned with GHG Protocol; Scope 2 displacement claim supported by contractual additionality documentation.

## 10. HS code reference block (illustrative)

| Component | HS subheading (HS 2022) | Description (WCO HS 2022) | Reference | Import duty rate |
| --- | --- | --- | --- | --- |
| Crystalline silicon PV modules | 8541.43 | Photovoltaic cells assembled in modules or made up into panels | [S3], [S4], [S14], [S16] | **PENDING** — confirm at national tariff line in the destination country |
| String / central inverters | 8504.40 | Static converters — other | [S3] | **PENDING** — confirm at national tariff line in the destination country |
| Mounting structures (aluminium / steel) | 7610.90 or 7326.20 | Aluminium structures and parts, or other articles of iron/steel | [S3] chapter 76 note 1 | **PENDING** — confirm at national tariff line in the destination country |
| DC / AC cables, connectors | 8544.49 | Other electric conductors, for a voltage not exceeding 1,000 V | [S3] chapter 85 notes 4 | **PENDING** — confirm at national tariff line in the destination country |
| Combiner boxes, switchgear, protection | 8537.10 | Boards, panels, consoles for electric control or distribution | [S3] | **PENDING** — confirm at national tariff line in the destination country |

**How to look up the actual applicable duty:** (i) identify the national tariff schedule in the destination country (e.g., Mexico's TIGIE, Brazil's TEC, Colombia's Arancel de Aduanas, Chile's Arancel Aduanero); (ii) read the chapter 85 and 76 (or 73) notes of HS 2022 [S3]; (iii) check whether a free-trade-agreement preference (USMCA, Pacific Alliance, MERCOSUR, EU agreements) applies based on rules of origin; (iv) consult the national customs authority's tariff classification tool (for EU-destined PV, the TARIC consultation tool [S16]; for US-destined PV, USITC HTS search [S14]) or a licensed customs broker for a binding ruling; (v) reconfirm VAT / IVA / ICMS / IGV and any anti-dumping or safeguard measures that may overlay the base duty.

**Disclaimer:** TradVolt does not assert any specific duty rate as fact. The HS subheadings listed above are illustrative starting points based on the WCO Harmonized System 2022 nomenclature [S3], [S4]. The legally binding duty rate is determined by the national customs authority of the country of import at the time of entry, considering the specific commercial description, rules of origin, and any applicable trade-remedy measures. Always obtain a binding tariff ruling from a licensed customs broker or the relevant national customs authority before tendering or shipping.

## 11. Decision call-to-action

If you are planning, procuring, or financing a GSE-coupled airport solar PV project in Latin America, request a buyer-specific TCO re-run with your real tariff, yield study, EPC bid, and WACC.

**Request for quotation:** [Submit an RFQ for a 300 kWp airport GSE solar project in LATAM](/rfq/).