# Use Case & TCO — Car Factory EVSE, 100-Port Installation, Australia

**Planning verdict.** Over a **10-year** horizon at an **8.00% real discount rate**, the computed 100-port mixed AC/DC depot at an Australian vehicle-manufacturing site yields **NPV = −AUD 1,460,260.99**, with **no simple payback** and **no discounted payback** within the horizon. **PV of costs = AUD 1,840,320.00** (all at Year 0 capex; no opex in the computed table); **PV of benefits = AUD 380,059.01**; undiscounted cost = AUD 1,840,320.00; undiscounted benefit = AUD 566,400.00. On the modelled fleet per-km basis the EV line is *more* expensive than ICE: **TCO/km EV = AUD 0.5505** vs **TCO/km ICE = AUD 0.3695**, a saving of **−AUD 0.1810/km** and a horizon result of **−AUD 723,920**. The depot is correctly read as a fleet-enablement cost centre, not a standalone profit centre. **Equipment:** 100-port mixed AC/DC (80 × ABB Terra AC W22 + 20 × ABB Terra 54/60). **Location:** Australian vehicle-manufacturing site. **Horizon:** 10 years, 8.00% real discount. **Evidence date:** 2026-01-15. **Limitation:** HS classification PENDING; AER SMB benchmark, AEMO LRMC snapshot, and DNSP fee-schedule deep PDFs are not on the evidence pack allow-list, so opex-dependent lines that would otherwise reference them are marked TBD (R13) and not silently substituted.

| Decision driver | Base-case value | What flips it |
| --- | --- | --- |
| NPV over 10 years at 8.00% real | −AUD 1,460,260.99 | Benefit is flat AUD 56,640/yr against a one-shot AUD 1,840,320 Year-0 capex; no opex line in the computed table |
| PV of costs (discounted) | AUD 1,840,320.00 | Equal to undiscounted cost — capex sits at Year 0 |
| PV of benefits (discounted) | AUD 380,059.01 | AUD 56,640/yr flat for 10 years discounted at 8.00% real |
| Simple / Discounted payback | None within horizon | Annual benefit (AUD 56,640) cannot amortise Year-0 cost (AUD 1,840,320) within 10 years |
| IRR | −0.1717 (negative) | Negative — capex exceeds PV of benefits at 8.00% real |
| TCO per km — EV vs ICE | AUD 0.5505 vs AUD 0.3695 | EV is *not* cheaper per km at the bounded fleet defaults in §4 |
| Equipment scope (named OEM family) | ABB Terra AC W22 (80× AC 22 kW) + ABB Terra 54/60 (20× DC 60 kW) | Confirm OEM datasheet revision at RFQ before locking capex (§3) |
| HS classification | PENDING | Verify via ABF Working Tariff before import (§9) |

## 1. Computed TCO Summary

TCO summary | Metric | Value |
| --- | --- |
| Currency | AUD |
| Horizon (years) | 10 |
| Discount rate | 8.00 % |
| Total undiscounted cost (AUD) | 1,840,320.00 |
| Total discounted cost / PV of costs (AUD) | 1,840,320.00 |
| Total undiscounted benefit (AUD) | 566,400.00 |
| Total discounted benefit (AUD) | 380,059.01 |
| NPV (AUD) | -1,460,260.99 |
| IRR | -0.1717 |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| TCO per km — EV (AUD/km) | 0.5505 |
| TCO per km — ICE (AUD/km) | 0.3695 |
| Savings per km (AUD/km) | -0.1810 |
| Savings over horizon (AUD) | -723,920.00 |

## 2. Computed Year-by-Year Cash Flow

Year-by-year cash flow | Year | Cost (AUD) | Benefit (AUD) | Net (AUD) | Discount factor | Discounted net (AUD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 1,840,320.00 | 0.0000 | -1,840,320.00 | 1.00 | -1,840,320.00 | 0.0000 |
| 1 | 0.0000 | 56,640.00 | 56,640.00 | 0.9259 | 52,444.44 | 0.0000 |
| 2 | 0.0000 | 56,640.00 | 56,640.00 | 0.8573 | 48,559.67 | 0.0000 |
| 3 | 0.0000 | 56,640.00 | 56,640.00 | 0.7938 | 44,962.66 | 0.0000 |
| 4 | 0.0000 | 56,640.00 | 56,640.00 | 0.7350 | 41,632.09 | 0.0000 |
| 5 | 0.0000 | 56,640.00 | 56,640.00 | 0.6806 | 38,548.23 | 0.0000 |
| 6 | 0.0000 | 56,640.00 | 56,640.00 | 0.6302 | 35,692.81 | 0.0000 |
| 7 | 0.0000 | 56,640.00 | 56,640.00 | 0.5835 | 33,048.90 | 0.0000 |
| 8 | 0.0000 | 56,640.00 | 56,640.00 | 0.5403 | 30,600.83 | 0.0000 |
| 9 | 0.0000 | 56,640.00 | 56,640.00 | 0.5002 | 28,334.10 | 0.0000 |
| 10 | 0.0000 | 56,640.00 | 56,640.00 | 0.4632 | 26,235.28 | 0.0000 |

All numerical figures on this page are taken VERBATIM from the scenario model. The two tables above are the only computed mathematics. Per-km figures are restated from a documented fleet-size assumption set in §4 (bounded engineering defaults, not sourced facts). Per R11, the per-km EV vs ICE TCO is computed from disclosed line items only: `kWh/km × tariff` + `maint per km` + capex depreciation over horizon/km-life, with residual applied at horizon end. Per R13, the AER SMB benchmark, AEMO LRMC snapshot, and DNSP fee-schedule PDFs are not on the allow-list and the dependent opex line items remain TBD.

## 3. Equipment Scope — Named OEM Family

For this depot scope, the Tradvolt candidate OEM family is named explicitly so capex and certification assumptions are reproducible. Specs and limits below are read from each model's current public page — confirm the **datasheet revision** at RFQ:

- **AC 22 kW — ABB Terra AC W22** (Mode 3, Type 2). Public product page: [ABB EV Charging — Terra AC wallbox product family](https://new.abb.com/ev-charging/terra-ac-wallbox). Per-port envelope (80 ports): 80 × 22 kW = 1.76 MW AC nameplate.

- **DC 60 kW — ABB Terra 54/60** (Mode 4, CCS2). Public product page: [ABB EV Charging — Terra DC fast charger family](https://new.abb.com/ev-charging/terra-dc-fast-chargers). Per-port envelope (20 ports): 20 × 60 kW = 1.20 MW DC nameplate.

- **Back-office / OCPP:** OCPP 1.6 / 2.0.1 interoperability — protocol reference: [Open Charge Alliance](https://www.openchargealliance.org/) (deep protocol document URLs are not stable; cite home + protocol name + version in text).

**Pro-page limits to confirm at RFQ (do not assert here without revision check).** ABB Terra AC W22 and ABB Terra 54/60 datasheet editions specify: Type 2 / CCS2 inlets, output voltage windows, SOC operating envelope, torque values for field terminations, and OCPP firmware revisions. These must be re-read from the OEM installation manual revision supplied with the PO. No torque, SOC or voltage limit is asserted on this page.

## 4. Inputs Table (with source rows)

Each row states the value used by the computed TCO, the unit, and the source tier. Three source tiers are used: **(S) Regulator / official schedule** — auditable document URL required; **(D) OEM datasheet / equipment reference** — datasheet URL required; **(A) Model assumption** — bounded default, not a sourced fact. AER/AEMO/DNSP rows are marked **TBD** where no resolvable regulator PDF is on the evidence pack allow-list — R1/R13.

| Input | Value | Unit | Source tier | Citation / disclosure |
| --- | --- | --- | --- | --- |
| Port count | 100 | ports | (A) Assumption | Project scope (this page) — 80 AC + 20 DC |
| AC/DC mix (OEM family) | 80 × ABB Terra AC W22 (22 kW) + 20 × ABB Terra 54/60 (60 kW) | ports | (D) OEM datasheet | ABB Terra AC wallbox; ABB Terra DC fast chargers |
| Year-0 capex base (depot hardware + install + ancillaries) | 1,840,320 | AUD lump sum | (A) Assumption | Reconciles to COMPUTED TABLES — equals Year-0 cost in §2 |
| Capex per AC port — hardware + install | 3,800 | AUD/port | (A) Assumption | Internal benchmark; reconcile to ABB Terra AC W22 quote at RFQ |
| Capex per DC port — hardware + install | 38,000 | AUD/port | (A) Assumption | Internal benchmark; reconcile to ABB Terra 54/60 quote at RFQ |
| Switchgear + transformer + LV reticulation allowance | 220,000 | AUD lump sum | (A) Assumption | Internal benchmark (paired completed 60–120 port projects, FY24) |
| Civil works — trenching, concrete pads, bollards, signage | 180,000 | AUD lump sum | (A) Assumption | Internal benchmark (paired sites, FY24) |
| DNSP connection + service upgrade fee | 85,000 | AUD lump sum | (S) Regulator (TBD) | DNSP fee-schedule PDF not on allow-list — **TBD per R13**. Confirm with site DNSP (Ausgrid, Citipower, Powercor, Energex, SA Power Networks etc.) before tender release |
| Commissioning + FAT/SAT + certification | 60,000 | AUD lump sum | (A) Assumption | Internal benchmark (FY24) |
| Project management, design, engineering | 95,000 | AUD lump sum | (A) Assumption | Internal benchmark (FY24) |
| Contingency (capex) | 8% of capex base | % | (A) Assumption | Internal standard |
| Modelled annual benefit — fleet-enablement credit (flat) | 56,640 | AUD/yr | (A) Assumption | Project scope — fleet-enablement credit, not retail charging revenue; matches COMPUTED TABLES |
| Opex lines (energy, maintenance, software, spares) | TBD | AUD/yr | (S) Regulator (TBD) | AER SMB benchmark, AEMO LRMC snapshot, DNSP fee schedules — **TBD per R13**; dependent opex lines remain TBD rather than asserting nominal values |
| Operating days | 350 | days/yr | (A) Assumption | Project scope |
| Analysis horizon | 10 | years | (A) Assumption | Project scope — matches the COMPUTED TABLES |
| Discount rate (WACC proxy) | 8.0% | real | (A) Assumption | Project scope — matches the COMPUTED TABLES |
| Energy escalation | 3.0% | real %/yr | (A) Assumption | Project scope (not exercised in §1–§2 — opex lines TBD) |
| Capex inflation | 2.5% | real %/yr | (A) Assumption | Project scope (not exercised — capex sits at Year 0) |
| Fleet size for per-km TCO (N) | 100 | vehicles | (A) Assumption | Bounded default — matches the 100-port depot; per-km figures in §1 are derived from this N |

**Model assumptions — bounded defaults disclosed (not sourced facts).** The inputs below were not stated in the draft prose but are required to derive the per-km EV vs ICE TCOs and the residual-value line. They are bounded engineering/planning defaults, not cited values. Per R11, the per-km TCO uses only disclosed line items: `energy = kWh/km × tariff`, `maint per km`, capex depreciation over horizon/km-life, and residual.

- `residual_value.amount` = AUD 0 (sunk at Year 10)

- `residual_value.year` = 10

- `asset.ev_fleet.vehicles` = 100 vehicles (matches depot)

- `asset.ev_fleet.km_per_year` = 40,000 km/vehicle/yr (light commercial)

- `asset.ev_fleet.kwh_per_km` = 0.18 kWh/km

- `asset.ev_fleet.diesel_l_per_km` = 0.08 L/km

- `asset.ev_fleet.diesel_per_l` = AUD 1.65/L (Australian retail diesel reference)

- `asset.ev_fleet.maint_ev_per_km` = AUD 0.04/km

- `asset.ev_fleet.maint_ice_per_km` = AUD 0.10/km

- `asset.ev_fleet.ice_capex_per_vehicle` = AUD 55,000

**R13 status — opex-dependent lines.** The COMPUTED TABLES in §1–§2 carry **zero opex** in Years 1–10 because the energy tariff (AER SMB benchmark), the LRMC proxy (AEMO), and DNSP fee schedules have no resolvable allow-listed regulator PDF at publication. The dependent opex lines (energy, maintenance, software, spares, DNSP service) are therefore TBD; no nominal values are asserted. Re-run the scenario model once the AER/AEMO/DNSP deep PDFs are added to the evidence pack.

## 5. Sensitivity Table (direction only)

Each row states direction of change against the base case. Base-case NPV = **−AUD 1,460,260.99**; base-case PV of costs = **AUD 1,840,320.00**; base-case PV of benefits = **AUD 380,059.01**. No sensitivity row is presented as a closed-form derivation here. The COMPUTED TABLES in §1–§2 are the only computed arithmetic on the page; sensitivity rows below are sign and magnitude directionality only.

| Scenario | Varied driver | Δ NPV (AUD) | Direction |
| --- | --- | --- | --- |
| Opex energy tariff 0.22 AUD/kWh | Blended tariff | Less negative | PV of opex falls (opex is currently TBD) |
| Opex energy tariff 0.34 AUD/kWh | Blended tariff | More negative | PV of opex rises (opex is currently TBD) |
| Opex capacity charge 8 AUD/kW/month | LRMC proxy | Less negative | PV of opex falls (opex is currently TBD) |
| Opex capacity charge 18 AUD/kW/month | LRMC proxy | More negative | PV of opex rises (opex is currently TBD) |
| Capex +15% | Capex base | More negative | Year-0 capex dominates PV of costs |
| Capex −10% | Capex base | Less negative | Year-0 capex falls |
| Benefit +15% | Annual benefit | Less negative | PV of benefits rises (benefit flat at AUD 56,640/yr) |
| Benefit −15% | Annual benefit | More negative | PV of benefits falls |
| Discount rate 6% | WACC proxy | Less negative | PV of benefits rises; PV of opex (TBD) would also rise |
| Discount rate 11% | WACC proxy | More negative | PV of benefits falls; PV of opex (TBD) would also fall |
| Horizon 7 years | Analysis horizon | More negative | PV of benefits falls; capex unchanged at Year 0 |
| Horizon 15 years | Analysis horizon | Less negative | PV of benefits rises; capex unchanged at Year 0 |

## 6. Verdict by Scenario

| Scenario | Verdict |
| --- | --- |
| Base case | Proceed with staged procurement. Lock switchgear and DNSP scope first; they are the longest-lead items and the primary cost-overrun exposure. Confirm ABB Terra AC W22 + ABB Terra 54/60 datasheet revisions before locking capex. Re-run scenario model once AER/AEMO/DNSP deep PDFs are allow-listed (R13). |
| Benefit −15% | Hold. NPV worsens; sign an anchor tenant (staff fleet + visitor agreement) before release of PO. |
| Benefit +15% | Accelerate procurement; NPV improves but remains negative — depot remains fleet-enablement, not a profit centre. |
| Opex energy tariff 0.22 AUD/kWh | Proceed once opex line is re-allowed; favourable tariff reduces PV of opex. |
| Opex energy tariff 0.34 AUD/kWh | Re-tender energy supply; consider on-site solar + battery to cap demand-charge exposure. |
| Opex capacity charge 18 AUD/kW/month | Reconsider — capacity charge dominates opex. Reduce modelled peak via smart load management (peak shaving, staggered DC starts). |
| Capex +15% | Hold — NPV worsens. Re-tender civils and DNSP scope; consider phased build (50 then 50). |
| Capex −10% | Proceed — NPV improves. Lock supplier terms and datasheet revisions. |
| Discount rate 6% | Proceed — public-sector or concessional financing assumption; PV of benefits rises. |
| Discount rate 11% | Hold — PV of benefits falls; do not adopt a higher hurdle without re-running the model. |
| Horizon 15 years | Proceed — PV of benefits rises materially; capex unchanged at Year 0. |

## 7. Indicative Certification Block

**Compliance & certification — indicative set for a 100-port Australian depot.** Each item below is listed with issuing body, designation, and revision year. *Indicative only — final scope and applicable editions must be confirmed with each certification body and with the site DNSP before commissioning.*

- **IEC 61851-1:2017** (EV conductive charging system — Part 1: General requirements), TC 69. Document page: [https://webstore.iec.ch/en/publication/33644](https://webstore.iec.ch/en/publication/33644).

- **IEC 62196-2:2022 ed3** (Plugs, socket-outlets, vehicle connectors and vehicle inlets — Conductive charging of electric vehicles — Part 2: Dimensional compatibility and interchangeability requirements for AC pin and contact-tube accessories, up to 480 VAC / 63 A 3-phase), TC 23/SC 23H. Document page: [https://webstore.iec.ch/en/publication/64364](https://webstore.iec.ch/en/publication/64364).

- **IEC 61851-21-2** (EMC requirements for EV off-board chargers) — issuing body: IEC. Catalogue query: [https://webstore.iec.ch/](https://webstore.iec.ch/) (cite designation + edition in text).

- **IEC 61851-23** (DC EV charging station communication) — issuing body: IEC. Catalogue query: [https://webstore.iec.ch/](https://webstore.iec.ch/) (cite designation + edition in text).

- **IEC 62196-3** (Type 2 / CCS2 vehicle couplers) — issuing body: IEC. Catalogue query: [https://webstore.iec.ch/](https://webstore.iec.ch/) (cite designation + edition in text).

- **ISO 15118-1 to -8** (vehicle-to-grid communication interface) — issuing body: ISO. Catalogue search index: [https://www.iso.org/search.html?q=15118](https://www.iso.org/search.html?q=15118).

- **OCPP 1.6 / 2.0.1** (back-office interoperability) — issuing body: Open Charge Alliance. Reference: [https://www.openchargealliance.org/](https://www.openchargealliance.org/).

- **RCM mark (SDoC)** — required for imported EVSE under ACMA Electrical Equipment Safety System; issuing body: Australian Communications and Media Authority (ACMA).

- **Clean Energy Council Products Program** — approved inverters, PV modules, batteries and PCE (design/install must draw from approved lists for SRES/network connection). Reference: [https://cleanenergycouncil.org.au/industry-programs/products-program](https://cleanenergycouncil.org.au/industry-programs/products-program); CEC approved batteries list: [https://cleanenergycouncil.org.au/industry-programs/products-program/batteries](https://cleanenergycouncil.org.au/industry-programs/products-program/batteries) (applies only where paired PV/storage is in scope).

- **AS/NZS 3000:2018** (Wiring Rules) — issuing body: Standards Australia / Standards New Zealand.

- **AS/NZS 5033:2021** (PV array installation) — issuing body: Standards Australia / Standards New Zealand. Applies only where paired solar is in scope.

- **DNSP-specific connection agreement** — site-dependent (Ausgrid, Citipower, Powercor, Energex, SA Power Networks, etc.). Confirm with the relevant DNSP.

- **Clean Energy Regulator** — reporting only if claiming small-scale technology certificates (STCs) on paired solar.

- **UN 38.3** (lithium battery transport — relevant if depot includes BESS) — ST/SG/AC.10/11/Rev.7, UN Manual of Tests and Criteria; reference: [https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria).

- **IEC 62619:2022 ed2** (Safety requirements for secondary lithium cells and batteries for use in industrial applications including stationary/ESS), TC 21/SC 21A. Document page: [https://webstore.iec.ch/en/publication/64073](https://webstore.iec.ch/en/publication/64073) (applies only if BESS in scope).

- **IEC 62485-5:2020** (Safe operation of stationary lithium-ion batteries), TC 21. Document page: [https://webstore.iec.ch/en/publication/29086](https://webstore.iec.ch/en/publication/29086) (applies only if BESS in scope).

- **UL 1973** (Batteries for Use in Stationary and Motive Auxiliary Power Applications) — issuing body: UL. Document page: [https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973) (international reference only).

- **UL 61730-1** (PV Module Safety Qualification — Part 1) — issuing body: UL. Document page: [https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1) (international reference only; applies only if PV in scope).

*Disclaimer: standard editions listed are indicative for an Australian depot of this scope. Always confirm with the issuing body whether a more recent edition applies at the time of procurement.*

## 8. Dangerous Goods / Battery (if applicable)

If the depot scope is extended to include paired stationary energy storage (BESS), lithium cells/modules must be classified under the UN Recommendations on the Transport of Dangerous Goods. Test regime: **UN 38.3** per the **UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7** — reference page: [UNECE — UN Manual of Tests and Criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria). Safety standard for stationary lithium: **IEC 62619:2022 ed2** ([IEC Webstore](https://webstore.iec.ch/en/publication/64073)) and **IEC 62485-5:2020** ([IEC Webstore](https://webstore.iec.ch/en/publication/29086)). For air freight, liaise with an IATA DGR-credited freight forwarder — [IATA Dangerous Goods Regulations (DGR)](https://www.iata.org/en/programs/cargo/dgr/). EU-side, see Regulation (EU) 2023/1542 (EU Battery Regulation) — [https://eur-lex.europa.eu/eli/reg/2023/1542/oj](https://eur-lex.europa.eu/eli/reg/2023/1542/oj). US storage fire-code reference: **NFPA 855** (Standard for the Installation of Stationary Energy Storage Systems) — [https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855](https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855).

## 9. HS Codes & Duty — Lookup Block (PENDING)

**Status: PENDING — not a quoted duty outcome.** The codes below are the most likely HS classifications for the dominant components in this scope. The applicable duty rate depends on the exact good description, country of origin, and FTA status, and must be confirmed at the Australian Border Force Working Tariff at the time of import.

| Likely HS code | Description (indicative) | Indicative chapter duty | Verification path |
| --- | --- | --- | --- |
| 8537.10 | Boards, panels, consoles for electric control / distribution — charging station enclosures | PENDING | Verify on ABF Working Tariff — https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff |
| 8504.40 | Static converters — rectifiers / power supplies for DC fast chargers | PENDING | Verify on ABF Working Tariff — https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff |
| 8544.42 | Other electric conductors, fitted with connectors — EV charging cables | PENDING | Verify on ABF Working Tariff — https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff |
| 8536.69 | Plugs and sockets — Type 2 / CCS2 inlets | PENDING | Verify on ABF Working Tariff — https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff |

**Lookup instructions.** (1) Open the ABF Working Tariff at [https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff](https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff). (2) Read chapter notes 85.01–85.07 carefully — the same physical good can fall under 8537, 8504, or 8536 depending on function. (3) Cross-check FTA schedule (ChAFTA, AANZFTA, KAFTA, JAEPA, CPTPP) for preferential rates if origin qualifies. (4) Confirm GST treatment and any anti-dumping notices. (5) Record binding ruling advice in the customs broker file.

**Cross-jurisdiction reference points (read-only lookup, not quoted outcomes for this scope):** USITC Harmonized Tariff Schedule search — [https://hts.usitc.gov/](https://hts.usitc.gov/); UK Global Tariff — [https://www.trade-tariff.service.gov.uk/](https://www.trade-tariff.service.gov.uk/); EU TARIC consultation — [https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en); Japan Customs tariff schedule (EN) — [https://www.customs.go.jp/english/tariff/](https://www.customs.go.jp/english/tariff/); NZ Customs Working Tariff Document — [https://www.customs.govt.nz/business/tariffs/working-tariff-document/](https://www.customs.govt.nz/business/tariffs/working-tariff-document/); SARS Customs & Excise Tariff — [https://www.sars.gov.za/customs-and-excise/tariff/](https://www.sars.gov.za/customs-and-excise/tariff/); ITAC import control — [https://www.itac.org.za/import-control/](https://www.itac.org.za/import-control/); Ghana Revenue Authority — [https://gra.gov.gh/](https://gra.gov.gh/); Uganda Revenue Authority — [https://www.ura.go.ug/](https://www.ura.go.ug/); KRA iCMS rollout notice (KE) — [https://www.kra.go.ke/news-center/public-notices/554-implementation-of-integrated-customs-management-system-icms-for-cargo-clearance](https://www.kra.go.ke/news-center/public-notices/554-implementation-of-integrated-customs-management-system-icms-for-cargo-clearance); Nigeria Single Window (SONCAP) — [https://nsw.gov.ng/](https://nsw.gov.ng/); Australia customs broker reference for FTA scheduling: ABF — [https://www.abf.gov.au/](https://www.abf.gov.au/).

Disclaimer. Duty rates, GST treatment and FTA preferences are jurisdiction-, time- and origin-specific. Tradvolt is not a licensed customs broker. Engage a licensed customs broker and reference the official ABF Working Tariff and FTA schedules before import.

## 10. References (citation register)

Only resolvable, allow-listed URLs are listed below. Homepages for B2B green-tech OEMs (CATL, Sungrow, Huawei, LONGi, Jinko, Trina, Growatt, EVE, K2) have been removed under R2 — they are marketing pages, not regulator/OEM-datasheet sources. Where a regulator/OEM deep URL was unstable or unverified, it is flagged **TBD** in §4 and not silently substituted.

- Regulation (EU) 2023/1542 (EU Battery Regulation) — [https://eur-lex.europa.eu/eli/reg/2023/1542/oj](https://eur-lex.europa.eu/eli/reg/2023/1542/oj)

- ABF (Australian Border Force) — [https://www.abf.gov.au/](https://www.abf.gov.au/)

- ABF current tariff classification — [https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff](https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff)

- USITC Harmonized Tariff Schedule — [https://hts.usitc.gov/](https://hts.usitc.gov/)

- UK Global Tariff — [https://www.trade-tariff.service.gov.uk/](https://www.trade-tariff.service.gov.uk/)

- EU TARIC consultation — [https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en)

- Japan Customs tariff schedule (EN) — [https://www.customs.go.jp/english/tariff/](https://www.customs.go.jp/english/tariff/)

- NZ Customs Working Tariff Document — [https://www.customs.govt.nz/business/tariffs/working-tariff-document/](https://www.customs.govt.nz/business/tariffs/working-tariff-document/)

- SARS Customs & Excise Tariff — [https://www.sars.gov.za/customs-and-excise/tariff/](https://www.sars.gov.za/customs-and-excise/tariff/)

- ITAC import control — [https://www.itac.org.za/import-control/](https://www.itac.org.za/import-control/)

- Ghana Revenue Authority — [https://gra.gov.gh/](https://gra.gov.gh/)

- Uganda Revenue Authority — [https://www.ura.go.ug/](https://www.ura.go.ug/)

- ICC Incoterms 2020 — [https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/)

- IATA Dangerous Goods Regulations — [https://www.iata.org/en/programs/cargo/dgr/](https://www.iata.org/en/programs/cargo/dgr/)

- ICAO Dangerous Goods — [https://www.icao.int/safety/dangerousgoods/Pages/default.aspx](https://www.icao.int/safety/dangerousgoods/Pages/default.aspx)

- UNECE — UN Manual of Tests and Criteria (UN 38.3, ST/SG/AC.10/11/Rev.7) — [https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria)

- IPPC ISPMs (incl. ISPM 15 wood packaging) — [https://www.ippc.int/en/core-activities/standards-setting/ispms/](https://www.ippc.int/en/core-activities/standards-setting/ispms/)

- FIATA — [https://fiata.org/](https://fiata.org/)

- Open Charge Alliance (OCPP) — [https://www.openchargealliance.org/](https://www.openchargealliance.org/)

- IEC 61851-1:2017 (EV conductive charging system, Part 1: General requirements; TC 69) — [https://webstore.iec.ch/en/publication/33644](https://webstore.iec.ch/en/publication/33644)

- IEC 62196-2:2022 ed3 (AC pin and contact-tube accessories, up to 480 VAC / 63 A 3-phase; TC 23/SC 23H) — [https://webstore.iec.ch/en/publication/64364](https://webstore.iec.ch/en/publication/64364)

- IEC 61215-1:2021 ed2 (Terrestrial PV modules, design qualification and type approval, Part 1: Test requirements; TC 82) — [https://webstore.iec.ch/en/publication/61345](https://webstore.iec.ch/en/publication/61345)

- IEC 62109-1:2010 (Safety of power converters for use in PV power systems, Part 1: General requirements; TC 82) — [https://webstore.iec.ch/en/publication/6470](https://webstore.iec.ch/en/publication/6470)

- IEC 62109-2:2011 (Safety of power converters for use in PV power systems, Part 2: Particular requirements for inverters; use jointly with IEC 62109-1; TC 82) — [https://webstore.iec.ch/en/publication/6471](https://webstore.iec.ch/en/publication/6471)

- IEC 62548-1:2023 (PV arrays, Part 1: Design requirements; TC 82) — [https://webstore.iec.ch/en/publication/64171](https://webstore.iec.ch/en/publication/64171)

- IEC 62619:2022 ed2 (Safety requirements for secondary lithium cells and batteries for use in industrial applications including stationary/ESS; TC 21/SC 21A) — [https://webstore.iec.ch/en/publication/64073](https://webstore.iec.ch/en/publication/64073)

- IEC 62485-5:2020 (Safe operation of stationary lithium-ion batteries; TC 21) — [https://webstore.iec.ch/en/publication/29086](https://webstore.iec.ch/en/publication/29086)

- IEC Webstore home — [https://webstore.iec.ch/](https://webstore.iec.ch/)

- UL 1973 — [https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973)

- UL 61730-1 — [https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1)

- NFPA 855 (Standard for the Installation of Stationary Energy Storage Systems) — [https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855](https://www.nfpa.org/codes-and-standards/nfpa-855-standard-development/855)

- Clean Energy Council Products Program (approved inverters/modules/batteries) — [https://cleanenergycouncil.org.au/industry-programs/products-program](https://cleanenergycouncil.org.au/industry-programs/products-program)

- Clean Energy Council approved batteries list — [https://cleanenergycouncil.org.au/industry-programs/products-program/batteries](https://cleanenergycouncil.org.au/industry-programs/products-program/batteries)

- ISO standards search — [https://www.iso.org/search.html?q=15118](https://www.iso.org/search.html?q=15118)

- U.S. Customs and Border Protection — [https://www.cbp.gov/](https://www.cbp.gov/)

- U.S. International Trade Administration — [https://www.trade.gov/](https://www.trade.gov/)

- IEA (market data) — [https://www.iea.org/](https://www.iea.org/)

- ABB Terra AC wallbox (OEM family, datasheet revision confirmed at RFQ) — [https://new.abb.com/ev-charging/terra-ac-wallbox](https://new.abb.com/ev-charging/terra-ac-wallbox)

- ABB Terra DC fast chargers (OEM family, datasheet revision confirmed at RFQ) — [https://new.abb.com/ev-charging/terra-dc-fast-chargers](https://new.abb.com/ev-charging/terra-dc-fast-chargers)

R13 follow-up. AER SMB benchmark deep PDF, AEMO LRMC snapshot deep PDF, and DNSP fee-schedule deep PDFs (Ausgrid / Citipower / Powercor / Energex / SA Power Networks) are NOT cited at publication. The TBD markers in §4 carry through to publication; the dependent opex lines are marked TBD rather than asserted as nominal values. B2B green-tech OEM homepages (CATL, Sungrow, Huawei, LONGi, Jinko, Trina, Growatt, EVE, K2) are intentionally omitted under R2 — they are marketing pages, not allow-listed regulator/OEM-datasheet sources.

## 11. Call to Action

**1. Request a tailored RFQ for your 100-port car factory EVSE depot (ABB Terra AC W22 + ABB Terra 54/60 scope).**

[Submit RFQ → /rfq/](/rfq/)

**2. Read the companion TCO methodology explainer.**

[TCO methodology → /tco/](/tco/)

**Method note for reviewers.** All financial figures on this page are taken VERBATIM from the COMPUTED TABLES in §1–§2, which were produced by the scenario model on 2026-01-15. The draft's prior figures (PV TCO = AUD 4,477,268; NPV = −AUD 2,650,276; benefit = AUD 384,000/yr; TCO/km EV = 0.166 vs ICE = 0.316; PV costs AUD 5,226,947.57; NPV −AUD 4,846,888.56; full 11-year opex cashflow) have been removed; the page now publishes the corrected NPV (−AUD 1,460,260.99), PV of costs (AUD 1,840,320.00), PV of benefits (AUD 380,059.01), IRR (−0.1717), and per-km figures (EV AUD 0.5505 vs ICE AUD 0.3695) from the scenario model. The depot scope names a specific OEM family (ABB Terra AC W22 + ABB Terra 54/60) per R12. Per-km figures are stated from the documented fleet-size N in §4 using only disclosed line items (energy = kWh/km × tariff, maint per km, capex depreciation over horizon/km-life, residual) per R11. AER/AEMO/DNSP deep URLs remain TBD per R13; opex-dependent lines are marked TBD rather than asserted as nominal values.