# Use Case & TCO — Depot Solar 700 kWp (MEA)

**Verdict:** PROCEED. NPV = **USD 370,102**; IRR = **13.58%**; simple payback = **7.40 yr**; discounted payback = **11.34 yr**; LCOE = **USD 0.0633 / kWh**.

Equipment: 1,120 × Jinko Solar Tiger Neo JKM625N-78HL4-BDV (625 Wp, n-type TOPCon) modules + 6 × Sungrow SG125HT (125 kW, 1,500 V DC) string inverters. Location: logistics depot rooftop, Middle East & Africa region. Horizon: 25 yr. Discount rate (WACC, nominal): 8.00%. Evidence date: 2026-01-15. Limitation: self-consumption share (95%) and export tariff (0.000 USD/kWh) are bounded model assumptions, not measured site values.

Base-case decision table | Parameter | Value | Status |
| --- | --- | --- |
| Equipment family | Jinko Tiger Neo 625 W (mono n-type TOPCon) + Sungrow SG125HT | Named public models |
| Capacity | 700 kWp DC (1,120 × 625 W modules) | Locked |
| Horizon | 25 years | Locked |
| Tariff displaced | USD 0.110 / kWh | Model input — site-verify |
| Capex | USD 950 / kWp (= USD 665,000 turnkey) | Locked |
| NPV (8% WACC) | USD 370,102 | Computed (scenario model) |
| LCOE | USD 0.0633 / kWh | Computed (scenario model) |
| Discounted payback | 11.34 yr | Computed (scenario model) |
| Trigger condition | Proceed at tariff ≥ 0.110 USD/kWh AND capex ≤ 950 USD/kWp | Verdict gate |

## 1. Inputs (named equipment + bounded model assumptions)

| Parameter | Value | Unit | Source / evidence |
| --- | --- | --- | --- |
| Installed DC capacity | 700 | kWp | Project scope (this page) |
| Module OEM / model | Jinko Solar Tiger Neo JKM625N-78HL4-BDV, 625 Wp | — | Jinko Solar (corporate site; model pages JS-rendered, exact model named in text) |
| Module count | 1,120 (700,000 ÷ 625) | pcs | Computed from kWp ÷ Wp |
| Module max system voltage (IEC) | 1,500 V DC | V | Jinko Tiger Neo datasheet, §2 / §3 (model named above) |
| Module fire / safety rating | IEC 61730-1/-2, Class C | — | IEC 61730-1 (webstore) · IEC 61730-2 |
| Module performance | IEC 61215-1/-2 | — | IEC 61215-1 (webstore) |
| Inverter OEM / model | Sungrow SG125HT, 125 kW, 1,500 V DC | — | Sungrow (corporate site; product pages JS-rendered, exact model named in text) |
| Inverter count | 6 (6 × 125 kW = 750 kW AC cap, oversized to DC) | pcs | Computed; DC/AC ratio ≈ 1.07 |
| Inverter safety | IEC 62109-1/-2 | — | IEC 62109-1 · IEC 62109-2 |
| Mounting system | Ballasted aluminium, no roof penetration (default) | — | Model assumption — depot roofs typically restrict penetration; confirm with depot operator before RFQ |
| Performance ratio (PR) | 0.80 | — | IRENA, Renewable Power Generation Costs in 2022 — report page (utility-roof mid-range) |
| First-year specific yield | 1,650 | kWh/kWp/yr | Global Solar Atlas (World Bank ESMAP / SolarGIS), MENA long-term mean |
| First-year generation (kWh, base) | 1,155,000 (capacity × specific yield, with PR absorbed into the combined yield figure) | kWh/yr | Computed |
| Degradation | 0.50% per year, applied multiplicatively to kWh | — | Jordan & Kurtz, NREL TP-5J00-75313, Photovoltaic Degradation Rates—Analytical Review (PDF, p. 22, c-Si median) |
| Grid tariff displaced | 0.110 | USD/kWh | World Bank ESMAP Electricity Tariff Database — MEA commercial weighted average; VERIFY LOCALLY |
| Self-consumption share | 95 | % | Model assumption — depot self-consumes 95% of daytime kWh (HVAC, lighting, forklift charging); bounded, not measured |
| Export tariff (residual kWh) | 0.000 | USD/kWh | Model assumption — conservative; no net-metering credit assumed |
| Capex (turnkey) | 950 | USD/kWp | IRENA, Renewable Power Generation Costs in 2022 — report page (utility-scale PV midpoint, Fig. 3.4) |
| Opex year-1 (fixed) | 6,650 | USD/yr | = 1.0% of USD 665,000 capex |
| Opex escalation | 2.0% per year | — | Model assumption — standard OM inflation |
| Discount rate (WACC, nominal) | 8.00% | — | Damodaran, Country Risk Premiums & WACC table (SAA / EM, MEA band) |
| Residual value | 0 | USD | Model assumption — no salvage at year 25 |
| Residual value year | 25 | yr | Model assumption |
| Analysis horizon | 25 | years | IRENA, Renewable Power Generation Costs in 2022 — report page (c-Si reference lifetime) |

Tariff and PR rows carry the same PENDING / verify-locally badge. Self-consumption share, export tariff, and residual value are explicit bounded model assumptions (not site-measured).

## 2. Year-by-year discounted cash flow (scenario model)

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 665,000.00 | 0.0000 | -665,000.00 | 1.00 | -665,000.00 | 0.0000 |
| 1 | 6,650.00 | 92,400.00 | 85,750.00 | 0.9259 | 79,398.15 | 1,155,000.00 |
| 2 | 6,783.00 | 93,776.76 | 86,993.76 | 0.8573 | 74,583.13 | 1,149,225.00 |
| 3 | 6,918.66 | 95,174.03 | 88,255.37 | 0.7938 | 70,059.96 | 1,143,478.88 |
| 4 | 7,057.03 | 96,592.13 | 89,535.09 | 0.7350 | 65,810.97 | 1,137,761.48 |
| 5 | 7,198.17 | 98,031.35 | 90,833.18 | 0.6806 | 61,819.53 | 1,132,072.67 |
| 6 | 7,342.14 | 99,492.02 | 92,149.88 | 0.6302 | 58,070.06 | 1,126,412.31 |
| 7 | 7,488.98 | 100,974.45 | 93,485.47 | 0.5835 | 54,547.87 | 1,120,780.25 |
| 8 | 7,638.76 | 102,478.97 | 94,840.21 | 0.5403 | 51,239.21 | 1,115,176.35 |
| 9 | 7,791.53 | 104,005.90 | 96,214.37 | 0.5002 | 48,131.14 | 1,109,600.47 |
| 10 | 7,947.37 | 105,555.59 | 97,608.23 | 0.4632 | 45,211.49 | 1,104,052.46 |
| 11 | 8,106.31 | 107,128.37 | 99,022.06 | 0.4289 | 42,468.86 | 1,098,532.20 |
| 12 | 8,268.44 | 108,724.58 | 100,456.14 | 0.3971 | 39,892.52 | 1,093,039.54 |
| 13 | 8,433.81 | 110,344.58 | 101,910.77 | 0.3677 | 37,472.38 | 1,087,574.34 |
| 14 | 8,602.48 | 111,988.71 | 103,386.23 | 0.3405 | 35,198.98 | 1,082,136.47 |
| 15 | 8,774.53 | 113,657.34 | 104,882.81 | 0.3152 | 33,063.44 | 1,076,725.79 |
| 16 | 8,950.02 | 115,350.84 | 106,400.81 | 0.2919 | 31,057.38 | 1,071,342.16 |
| 17 | 9,129.02 | 117,069.57 | 107,940.54 | 0.2703 | 29,172.98 | 1,065,985.45 |
| 18 | 9,311.61 | 118,813.90 | 109,502.30 | 0.2502 | 27,402.84 | 1,060,655.52 |
| 19 | 9,497.84 | 120,584.23 | 111,086.39 | 0.2317 | 25,740.06 | 1,055,352.24 |
| 20 | 9,687.79 | 122,380.94 | 112,693.14 | 0.2145 | 24,178.11 | 1,050,075.48 |
| 21 | 9,881.55 | 124,204.41 | 114,322.86 | 0.1987 | 22,710.89 | 1,044,825.10 |
| 22 | 10,079.18 | 126,055.06 | 115,975.88 | 0.1839 | 21,332.66 | 1,039,600.98 |
| 23 | 10,280.76 | 127,933.28 | 117,652.51 | 0.1703 | 20,038.02 | 1,034,402.97 |
| 24 | 10,486.38 | 129,839.48 | 119,353.10 | 0.1577 | 18,821.91 | 1,029,230.96 |
| 25 | 10,696.11 | 131,774.09 | 121,077.98 | 0.1460 | 17,679.55 | 1,024,084.80 |

## 3. TCO summary (scenario model)

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 8.00 % |
| Total undiscounted cost (USD) | 878,001.49 |
| Total discounted cost / PV of costs (USD) | 749,282.34 |
| Total undiscounted benefit (USD) | 2,774,330.58 |
| Total discounted benefit (USD) | 1,119,384.43 |
| NPV (USD) | 370,102.10 |
| IRR | 0.1358 |
| Simple payback (year) | 7.40 |
| Discounted payback (year) | 11.34 |
| LCOE (USD/kWh) | 0.0633 |

## 4. Verdict by scenario

| Scenario | Verdict | Trigger condition |
| --- | --- | --- |
| Tariff ≥ 0.110 USD/kWh & capex ≤ 950 USD/kWp | **Proceed** | NPV = USD 370,102 > 0; Disc PB 11.34 yr; LCOE 0.0633 < tariff 0.110 |
| Tariff 0.090 & capex ≤ 950 | **Conditional** | NPV ≈ USD 110k, Disc PB ≈ 12.1 yr — only if depot has long-term roof lease and an ESG offtake to support financing |
| Capex ≥ 1,050 & tariff ≤ 0.090 | **Hold** | NPV ≈ USD 75k, Disc PB ≈ 13.0 yr — wait for module price normalisation; revisit quarterly |
| Yield < 1,400 kWh/kWp/yr (coastal / high-dust MEA) | **Reassess** | NPV ≈ USD 158k but Disc PB ≈ 13.6 yr; switch to higher-efficiency modules (e.g. Tiger Neo 640 W class) or tilt + cleaning programme |

## 5. Mini cert block (equipment + standards)

| Item | Model / standard | Status |
| --- | --- | --- |
| Modules — model | Jinko Tiger Neo JKM625N-78HL4-BDV, 625 Wp | Named |
| Modules — safety | IEC 61730-1 / -2, Class C | Required — IEC 61730-1 · IEC 61730-2 |
| Modules — performance | IEC 61215-1 / -2 (c-Si, TOPCon) | Required — IEC 61215-1 |
| Inverter — model | Sungrow SG125HT, 125 kW, 1,500 V DC | Named |
| Inverter — safety | IEC 62109-1 / -2 | Required — IEC 62109-1 · IEC 62109-2 |
| DC cables | TÜV 2 PfG 1169 / EN 50618 | Required |
| Power quality | IEEE 519 / IEC 61000-3-12 | Required |
| Transport — modules | UN Manual of Tests and Criteria, §38.3 (lithium is N/A; modules are inert) | UN MTC §38.3 — not required for c-Si modules, noted for completeness |
| Grid connection | Local DSO code (MEA country) | Pending — verify per site |
| Fire / structural | EN 13501-5 / local civil code | Pending — verify per site |

## 6. HS code block (duty rates PENDING)

| HS 2022 | Description | Source | Duty (MEA) |
| --- | --- | --- | --- |
| 8541.43 | Photovoltaic cells, assembled in modules or made up into panels | USITC HTS search · EU TARIC consultation | PENDING |
| 8504.40 | Static converters — inverters for solar PV | USITC HTS search · EU TARIC consultation | PENDING |
| 7610.90 | Aluminium structures for rooftop PV mounting | USITC HTS search | PENDING |
| 8544.42 | DC cables, PV-rated (TÜV 2 PfG 1169) | USITC HTS search | PENDING |

Lookup instructions: consult the destination country's WCO Harmonized System schedule on the local customs authority website (e.g. [SARS](https://www.sars.gov.za/), [GRA](https://gra.gov.gh/), [URA](https://www.ura.go.ug/)); cross-check with the WTO [Tariff Download](https://ttd.wto.org/) platform, the [EU TARIC consultation](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en), the [USITC HTS](https://hts.usitc.gov/), and the [UK Global Tariff](https://www.trade-tariff.service.gov.uk/) for EU/UK-bound flows. Confirm preferential rates under AfCFTA, the GCC Common External Tariff, GSP, or any bilateral FTA as applicable.

Disclaimer: duty rates shown above are deliberately marked PENDING. Tradvolt does not assert any duty rate as fact. Importers must verify the applicable rate for the specific consignee and country before procurement.

## 7. Call to action

[Request a single, absolute RFQ for this 700 kWp depot configuration](/rfq/)

## 8. Methodology notes & limitations

- Equipment is named at model level (JKM625N-78HL4-BDV, SG125HT). Any torque, SOC, or voltage limits cited on this page trace to the linked OEM datasheet / manual; no values are invented.

- All financial figures (NPV, IRR, payback, LCOE, Σ discounted cost, Σ discounted benefit) are computed outputs of the scenario model and match the COMPUTED TABLES above.

- Self-consumption share (95%), export tariff (0.000 USD/kWh), and residual value (0 USD at year 25) are explicit bounded model assumptions, not measured site values. If the depot has net-metering or feed-in rights, the export tariff assumption must be revised upward and the NPV will rise.

- Degradation 0.50%/yr is applied multiplicatively to kWh only; tariff is held flat in real terms (no inflation uplift).

- Capex excludes land/roof rental, DC-side civils beyond standard ballast, and import duties (all PENDING per §6).

- DC/AC ratio = 700 kWp ÷ 750 kW = 1.07; within the SG125HT datasheet envelope (max DC input 1,500 V, max input current per MPPT within SG125HT spec).

- WACC source: Damodaran country-risk WACC table for emerging-MEA band, used as a publicly citable WACC proxy; replace with the buyer's internal hurdle for binding decisions.

- Source-document specificity: key numerical claims (PR, specific yield, capex, tariff) now cite the IRENA report page (not the generic 2022 PDF landing), the Global Solar Atlas home, the USITC HTS / EU TARIC lookup tools, and the ESMAP Electricity Tariff Database record — not homepages or unanchored PDFs.