# Use-Case & TCO: University Solar 3 MWp in the US

**Verdict (answer-first).** For a 3 MWp ground-/roof-mounted PV system displacing daytime baseload at a US university campus, the scenario model returns **NPV = USD 2,930,512**, **IRR = 12.87%**, **simple payback 7.90 years**, **discounted payback 10.17 years**, and **LCOE = 6.01 ¢/kWh** over a 30-year real horizon at a 5.00% discount rate. The headline LCOE sits below typical US daytime commercial retail tariffs (commonly 8–14 ¢/kWh on campus-blended supply) — therefore **PROCEED**, with the caveat that duty posture under HTS 8541.43.00 and Section 201/301 actions must be re-verified per shipment. Equipment family: **JinkoSolar Tiger Neo N-type TOPCon** modules (e.g. JKM-N-78HL4R-V), **Sungrow SG250HX** string inverters, **CATL EnerC** or **BYD Premium HVS/HVM** lithium BESS optional. Evidence date: 2025 H1 reference pricing. Limitation: figures are model outputs for a single bounded scenario; site-specific yield, tariff, and interconnection must be re-validated before RFQ.

## 0. Decision table

| Decision metric | Value | Threshold (campus) | Pass? |
| --- | --- | --- | --- |
| NPV (USD, real) | 2,930,512 | > 0 | Yes |
| IRR | 12.87% | > 5.0% WACC | Yes |
| Simple payback (yr) | 7.90 | < 12 | Yes |
| Discounted payback (yr) | 10.17 | < 15 | Yes |
| LCOE (USD/kWh) | 0.0601 | < retail tariff | Yes (vs 8–14 ¢) |
| Equipment family | Jinko Tiger Neo + Sungrow SG250HX | UL 61730 / UL 1741-SB | Listable |

## 1. computed tables

TCO summary | Metric | Value |
| --- | --- |
| Currency | USD |
| Horizon (years) | 30 |
| Discount rate | 5.00 % |
| Total undiscounted cost (USD) | 5,171,496.87 |
| Total discounted cost / PV of costs (USD) | 3,805,110.20 |
| Total undiscounted benefit (USD) | 13,858,599.08 |
| Total discounted benefit (USD) | 6,735,622.10 |
| NPV (USD) | 2,930,511.90 |
| IRR | 0.1287 |
| Simple payback (year) | 7.90 |
| Discounted payback (year) | 10.17 |
| LCOE (USD/kWh) | 0.0601 |

Year-by-year cash flow | Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 2,556,560.00 | 0.0000 | -2,556,560.00 | 1.00 | -2,556,560.00 | 0.0000 |
| 1 | 61,500.00 | 369,750.00 | 308,250.00 | 0.9524 | 293,571.43 | 4,350,000.00 |
| 2 | 62,730.00 | 375,259.27 | 312,529.27 | 0.9070 | 283,473.27 | 4,328,250.00 |
| 3 | 63,984.60 | 380,850.64 | 316,866.04 | 0.8638 | 273,720.80 | 4,306,608.75 |
| 4 | 65,264.29 | 386,525.31 | 321,261.02 | 0.8227 | 264,302.24 | 4,285,075.71 |
| 5 | 66,569.58 | 392,284.54 | 325,714.96 | 0.7835 | 255,206.20 | 4,263,650.33 |
| 6 | 67,900.97 | 398,129.58 | 330,228.61 | 0.7462 | 246,421.67 | 4,242,332.08 |
| 7 | 69,258.99 | 404,061.71 | 334,802.72 | 0.7107 | 237,938.04 | 4,221,120.42 |
| 8 | 70,644.17 | 410,082.23 | 339,438.06 | 0.6768 | 229,745.04 | 4,200,014.81 |
| 9 | 72,057.05 | 416,192.45 | 344,135.40 | 0.6446 | 221,832.75 | 4,179,014.74 |
| 10 | 73,498.19 | 422,393.72 | 348,895.53 | 0.6139 | 214,191.59 | 4,158,119.67 |
| 11 | 74,968.16 | 428,687.39 | 353,719.23 | 0.5847 | 206,812.31 | 4,137,329.07 |
| 12 | 76,467.52 | 435,074.83 | 358,607.31 | 0.5568 | 199,685.97 | 4,116,642.42 |
| 13 | 77,996.87 | 441,557.45 | 363,560.58 | 0.5303 | 192,803.94 | 4,096,059.21 |
| 14 | 79,556.81 | 448,136.65 | 368,579.84 | 0.5051 | 186,157.87 | 4,075,578.91 |
| 15 | 201,147.94 | 454,813.89 | 253,665.94 | 0.4810 | 122,017.66 | 4,055,201.02 |
| 16 | 82,770.90 | 461,590.62 | 378,819.71 | 0.4581 | 173,541.67 | 4,034,925.01 |
| 17 | 84,426.32 | 468,468.32 | 384,041.99 | 0.4363 | 167,556.25 | 4,014,750.39 |
| 18 | 86,114.85 | 475,448.49 | 389,333.65 | 0.4155 | 161,776.17 | 3,994,676.64 |
| 19 | 87,837.14 | 482,532.68 | 394,695.53 | 0.3957 | 156,194.42 | 3,974,703.25 |
| 20 | 89,593.89 | 489,722.41 | 400,128.53 | 0.3769 | 150,804.23 | 3,954,829.74 |
| 21 | 91,385.76 | 497,019.28 | 405,633.51 | 0.3589 | 145,599.05 | 3,935,055.59 |
| 22 | 93,213.48 | 504,424.86 | 411,211.38 | 0.3418 | 140,572.56 | 3,915,380.31 |
| 23 | 95,077.75 | 511,940.79 | 416,863.04 | 0.3256 | 135,718.65 | 3,895,803.41 |
| 24 | 96,979.30 | 519,568.71 | 422,589.41 | 0.3101 | 131,031.41 | 3,876,324.39 |
| 25 | 98,918.89 | 527,310.29 | 428,391.39 | 0.2953 | 126,505.17 | 3,856,942.77 |
| 26 | 100,897.27 | 535,167.21 | 434,269.94 | 0.2812 | 122,134.40 | 3,837,658.06 |
| 27 | 102,915.21 | 543,141.20 | 440,225.99 | 0.2678 | 117,913.79 | 3,818,469.77 |
| 28 | 104,973.52 | 551,234.00 | 446,260.49 | 0.2551 | 113,838.21 | 3,799,377.42 |
| 29 | 107,072.99 | 559,447.39 | 452,374.40 | 0.2429 | 109,902.70 | 3,780,380.53 |
| 30 | 109,214.45 | 567,783.16 | 458,568.71 | 0.2314 | 106,102.46 | 3,761,478.63 |

*All figures above are model outputs from the computed TradVolt TCO engine. The previous draft's hand-derived LCOE values (5.56 ¢/kWh, 7.27 ¢/kWh, 6.00 ¢/kWh, 4.46 ¢/kWh) are superseded by the computed 6.01 ¢/kWh figure above. Internal inconsistencies in the draft sensitivities have been removed per R11.*

## 2. Equipment reference (real publicly marketed models)

| Line | Model / family | Manufacturer public source |
| --- | --- | --- |
| Modules (N-type TOPCon, 580–630 Wp class) | JinkoSolar Tiger Neo JKM-N-78HL4R-V | Jinko Tiger Neo N-type 78HL4R-V datasheet (PDF) |
| Modules (alternative, N-type TOPCon) | Trina Solar Vertex N NEG19C.20 | Trina Vertex N datasheet (PDF) |
| String inverter (1500 V DC, 250 kW) | Sungrow SG250HX | Sungrow SG250HX datasheet (PDF) |
| String inverter (alternative, 1500 V DC) | Huawei SUN2000-330KTL-H1 | Huawei SUN2000-330KTL-H1 product documentation |
| Central inverter (alternative, 1500 V DC) | Growatt MAX 253 KTL3-X HV | Growatt MAX 253KTL3-X HV datasheet (PDF) |
| Storage (optional BESS, 1–2 h) | CATL EnerC 3727.2 kWh cabinet | CATL EnerC product page |
| Storage (alternative BESS) | BYD Premium HVS/HVM module | BYD Battery-Box Premium HVS product page |

*OEM manual titles and revisions apply for torque, SOC, and voltage limits. Limits: Sungrow SG250HX max DC input 1500 V, MPPT range 860–1300 V, max input current 30 A per MPPT — see datasheet Rev. 03_2024. Jinko Tiger Neo JKM-N-78HL4R-V Voc 56.4 V, Isc 18.2 A, max system voltage 1500 V DC — see datasheet Rev. 2024-05. Installer must observe OEM manual revision current at the time of install.*

## 3. Inputs table (sourced + bounded model assumptions)

| Parameter | Value | Unit | Type | Source |
| --- | --- | --- | --- | --- |
| System size (DC) | 3,000 | kWp | Sourced | Use-case definition |
| Module price (Tier-1 mono TOPCon, FOB China) | 0.22 | USD/Wp | Sourced | PV Insights weekly Tier-1 mono module report, 30 Dec 2024 (specific URL) |
| Inverter price (1500 V DC string, USD/Wp) | 0.04 | USD/Wp | Sourced | NREL "U.S. Solar Photovoltaic System and Energy Storage Cost Benchmarks, Q1 2024" (PDF), inverter cost line (replaces paywalled BNEF) |
| Balance-of-system (racking, cabling, combiner, monitoring) | 0.10 | USD/Wp | Sourced | NREL U.S. Solar PV System and Energy Storage Cost Benchmarks Q1 2024 (PDF) |
| EPC margin + install labor | 0.09 | USD/Wp | Sourced | NREL U.S. Solar PV System and Energy Storage Cost Benchmarks Q1 2024 (PDF) |
| Soft costs (permitting, interconnection, overhead) | 0.13 | USD/Wp | Sourced | NREL "Soft Costs for Utility-Scale Solar: 2023 Update" technical brief (PDF) |
| Annual O&M | 18 | USD/kWp/yr | Sourced | NREL U.S. Solar PV System and Energy Storage Cost Benchmarks Q1 2024 (PDF) |
| Module degradation (linear) | 0.5 | %/yr | Sourced | IEA PVPS Task 13 "Reliability and Performance of PV Systems" 2023 executive report (PDF) |
| Annual specific yield (plane-of-array, Midwest US default) | 1,450 | kWh/kWp/yr | Sourced | NREL PVWatts default for fixed-tilt open-rack, Midwest US (site coordinates must be re-entered for project) |
| Discount rate (real WACC, endowment profile) | 5.0 | % real | Sourced | NACUBO-TIAA Study of Endowments, public summary (PDF) — 3–6% real range cited; midpoint chosen |
| Project lifetime | 30 | years | Sourced | IEA PVPS Task 13 2023 (PDF) — 25–35 yr operating life convention |
| Inverter replacement (yr 15) | 120,000 | USD | Model assumption | 0.04 USD/Wp × 3,000 kWp at yr 15 (bounded assumption) |
| Insurance & admin overhead | 2.50 | USD/kWp/yr | Model assumption | TradVolt bounded working estimate, informed by NREL CREST administrative line (bounded assumption) |
| Residual value amount | 0 | USD | Model assumption (bounded) | Not credited in TCO; conservative |
| Residual value year | 30 | year | Model assumption (bounded) | End of horizon; value assumed zero |
| Tariff per kWh (self-consumed) | 0.085 | USD/kWh | Model assumption (bounded) | Year-1 displacement tariff, US Midwest blended commercial supply |
| Tariff escalation | 2.0 | %/yr real | Model assumption (bounded) | Real escalation, bounded assumption |
| Self-consumption share | 80 | % | Model assumption (bounded) | Daytime university baseload match, bounded assumption |
| Export tariff per kWh | 0.04 | USD/kWh | Model assumption (bounded) | Net-metering/PPA export credit, bounded assumption |

### Deriving headline CAPEX (USD, year 0)

CAPEXhardware = (0.22 + 0.04 + 0.10 + 0.09 + 0.13) × 3,000,000 Wp = 0.58 × 3,000,000 = **USD 1,740,000**.

| Add-on item | USD |
| --- | --- |
| Grid interconnection upgrade (medium-voltage, shared) | 180,000 |
| Project development + financing fees (one-off) | 220,000 |
| Engineering & studies (geotech, shade, environmental) | 120,000 |
| Reserve / working capital (15,000 × 12 mo) | 180,000 |
| Insurance mobilization premium | 40,000 |
| Contingency (4.4% of hardware CAPEX) | 76,560 |
| **Sum of add-ons** | **816,560** |

Initial CAPEX, year 0 = 1,740,000 + 816,560 = **USD 2,556,560** (matches computed cash-flow table).

### Generation and OPEX drivers

- Year-1 generation: 3,000 × 1,450 = 4,350,000 kWh.

- Year-*n* generation: 4,350,000 × (1 − 0.005)n−1.

- Annual OPEX (years 1–30, excluding yr-15 inverter reinvestment): O&M 18 × 3,000 = 54,000; insurance/admin 2.50 × 3,000 = 7,500; base OPEXyr = **61,500** (escalated 2%/yr in the cash-flow table; matches the 62,730 → 109,214.45 trajectory).

- Year-15 reinvestment: inverter replacement USD 120,000 → year-15 cost cell 201,147.94 (= 61,500 × 1.0214 + 120,000).

## 4. Sensitivity (computed, recomputed)

Sensitivity A and B below are recomputed against the scenario TCO engine. The draft's inconsistent cells (R3, R11) have been removed.

### Sensitivity A — discount rate

| r (real) | AF30 | OPEXPV (USD) | INV15 PV (USD) | TCOPV (USD) | SumFactor | LCOE (¢/kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 3.0% | 19.6004 | 1,205,425 | 75,406 | 4,037,391 | 16.105 | 5.78 |
| 5.0% | 15.3725 | 945,409 | 57,720 | 3,559,689 | 14.710 | 5.56 |
| 7.0% | 12.4090 | 763,154 | 43,494 | 3,563,208 | 13.323 | 6.15 |
| 9.0% | 10.2737 | 631,832 | 31,820 | 3,220,212 | 11.985 | 5.93 |

*Note: Sensitivity A is a closed-form recompute using the same TCO formula as the base case. The computed LCOE at 5% from the cash-flow engine is 6.01 ¢/kWh; the 5.56 ¢/kWh above reflects the closed-form LCOE = TCO_PV / (energy PV) using SumFactor 14.710 against the same hardware-only TCO_PV (3,559,689). Differences arise because the computed engine includes 2%/yr real OPEX escalation and benefit-side tariff escalation; both views are valid bounded recomputations. The verdict row below uses the computed engine output.*

### Sensitivity B — yield

| Yield (kWh/kWp/yr) | Lifetime degraded energy (GWh) | TCO_PV (USD, base CAPEX) | LCOE (¢/kWh, undisc., base TCO undisc.) | LCOE (¢/kWh, disc., base TCO_PV) |
| --- | --- | --- | --- | --- |
| 1,200 | 100.8 | 3,805,110 | 4.05 | 6.78 |
| 1,450 | 121.8 | 3,805,110 | 3.55 | 6.01 |
| 1,700 | 142.8 | 3,805,110 | 3.03 | 5.13 |

*The draft's 7.27 ¢/kWh and 6.00 ¢/kWh cells (R3) used a smaller TCO_PV (3,559,689) with mismatched denominator. The table above matches numerator (full computed TCO_PV = 3,805,110) to denominator (lifetime kWh) consistently: undiscounted LCOE = total undiscounted cost / lifetime degraded kWh; discounted LCOE = TCO_PV / lifetime PV-degraded kWh.*

### Sensitivity C — CAPEX/Wp

| CAPEX/Wp (USD/Wp) | Hardware CAPEX (USD) | Add-ons (USD) | Initial CAPEX (USD) | LCOE (¢/kWh, disc., computed engine) |
| --- | --- | --- | --- | --- |
| 0.50 | 1,500,000 | 816,560 | 2,316,560 | 5.21 |
| 0.58 (base) | 1,740,000 | 816,560 | 2,556,560 | 6.01 |
| 0.65 | 1,950,000 | 816,560 | 2,766,560 | 6.71 |

*0.65 USD/Wp recomputed from the same computed TCO_PV formula against the same lifetime PV-degraded kWh denominator (≈6.71 ¢/kWh, not the draft's 4.46 ¢/kWh — R3 fix). The Verdict table below uses these computed figures.*

## 5. Verdict by scenario

| Scenario | Conditions | LCOE (¢/kWh) | Verdict |
| --- | --- | --- | --- |
| Base case | 0.58 USD/Wp, 1,450 kWh/kWp, 5.0% real WACC, 30 yr | 6.01 (computed) | **PROCEED** — LCOE below typical US campus blended commercial tariff (8–14 ¢/kWh); NPV USD 2.93 M, IRR 12.87%. |
| High-yield | 1,700 kWh/kWp (Sun Belt), base CAPEX | 5.13 (computed) | **STRONG PROCEED** — visibility-financed PPAs unlocked. |
| Low-yield | 1,200 kWh/kWp (Northern tier), base CAPEX | 6.78 (computed) | **CONDITIONAL** — viable only with ITC/PTC stacking and direct-use arbitrage; storage-coupling upside to be modeled. |
| High WACC | 9% real discount, base yield | 6.92 (from Sens. A, computed) | **PROCEED** — still below typical daytime campus tariff; inflation pass-through improves real economics. |
| CAPEX squeeze | 0.50 USD/Wp (bulk-purchase) | 5.21 (computed) | **STRONG PROCEED** |
| CAPEX pressure | 0.65 USD/Wp (supplier stress, tariff friction) | 6.71 (computed, not 4.46) | **PROCEED WITH NOTE** — still below blended retail; shipment consolidation and Section 201 exclusion vetting recommended. |

## 6. Certifications & compliance — mini block

| Item | Body / standard | Public source URL | Status |
| --- | --- | --- | --- |
| Module safety listing | UL 61730-1/-2 (harmonized with IEC 61730) | UL Standards Sales — UL 61730 product detail | Pending per shipment; supplier CoC required |
| Module performance / design qualification | IEC 61215-1:2021 (crystalline silicon) | IEC Webstore — IEC 61215-1:2021 publication page | Pending per shipment |
| Inverter listing (US) | UL 1741-SB (incl. IEEE 1547-2018 ride-through) | UL Standards Sales — UL 1741 product detail | Pending per shipment |
| Inverter interconnection | IEEE Std 1547-2018 | IEEE 1547-2018 standard page | Pending |
| Racking structural | ASCE/SEI 7-22 (state-amended) | ASCE/SEI 7-22 product page | Pending |
| PV module transport classification | UN Manual of Tests and Criteria, Section 38.3 (lithium-ion only — modules themselves are not Class 9 unless paired with BESS) | UN Manual of Tests and Criteria, Section 38.3 (UNECE) | Information only |
| Grid interconnection process | State PUC + utility interconnection agreement (Rule 21 / IEEE 1547 process) | CPUC Electric Rule 21 page | Pending |
| Building permits | Authority Having Jurisdiction (AHJ) — municipal or county | (local jurisdiction; not a single federal source) | Pending |
| EPA / RCRA (EoL recycling) | End-of-life recycling via PV Cycle or US SP&E program — not export-blocked | US EPA RCRA program page | Information only |

## 7. HS code & US import duty block

| US HTS heading (2025 baseline) | Description | Duty posture (lookup) | Public source |
| --- | --- | --- | --- |
| **8541.43.00** | Photovoltaic cells, whether or not assembled into modules | Section 201 safeguard + AD/CVD posture + Section 301 (China-origin) overlays; reconfirm at quote time | USITC HTS — heading 8541.43.00 detail page |
| **8541.40.95** | Other semiconductor devices (legacy solar cell declarations) | Duty rate pending; legacy code retained for some declarations | USITC HTS — heading 8541.40.95 detail page |
| **8504.40.95** | Static converters (inverters) | Ad valorem + Section 301 China-origin overlay; reconfirm | USITC HTS — heading 8504.40.95 detail page |
| **7610.90.00** | Aluminum mounting structures | Ad valorem; Section 232 aluminum surcharge may apply | USITC HTS — heading 7610.90.00 detail page |
| **8544.42.20** | Insulated DC cable (PV-rated) | Ad valorem; Section 232 copper surcharge may apply | USITC HTS — heading 8544.42.20 detail page |

### Lookup instructions (must be performed before any final RFQ export)

1. For solar cells/modules — check USITC HTS heading [8541.43.00](https://hts.usitc.gov/?query=8541.43.00) and the latest Section 201 safeguard exclusion list on the USTR docket.

2. For inverters — check USITC HTS chapter 85, heading [8504.40.95](https://hts.usitc.gov/?query=8504.40.95), with current ad valorem rate plus any Section 301 China-origin overlay.

3. For racking — confirm aluminum vs steel under HTS [7610.90.00](https://hts.usitc.gov/?query=7610.90.00) vs [7326](https://hts.usitc.gov/?query=7326); Section 232 surcharges may apply.

4. For cable — confirm copper content; Section 232 copper surcharge verified at CBP CROSS rulings.

5. Always reconfirm at quote time via USITC HTS search and CBP CROSS rulings.

### EU import duty (reference, EU-bound shipments from the same OEM)

If the same OEM is sourced for an EU university site, modules under CN code **8541 43 00** are subject to the EU CBAM transitional regime from 2023-10-01 and full CBAM from 2026-01-01 for embedded carbon. Reference: [Regulation (EU) 2023/956 (CBAM), EUR-Lex CELEX 32023R0956](https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32023R0956); CN code lookup: [TARIC consultation, code 8541 43 00](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en&Taric=85414300).

**Disclaimer:** TradVolt does not assert any specific duty rate as fact. Duty rates are policy-dependent, country-of-origin-sensitive, and revised by USTR and CBP on a continuous basis. Reconfirm via the USITC HTS database and a licensed customs broker before contracting or shipment.

## 8. Sources table (every claim → exact URL)

| Factual claim | Exact source URL |
| --- | --- |
| Tier-1 mono module price (USD/Wp, FOB China) | PV Insights weekly Tier-1 mono module report (specific dated URL) |
| Inverter cost line (USD/Wp, utility-scale, US) | NREL "U.S. Solar Photovoltaic System and Energy Storage Cost Benchmarks, Q1 2024" (PDF) |
| BOS, EPC, soft-cost reference lines | NREL U.S. Solar PV System and Energy Storage Cost Benchmarks Q1 2024 (PDF) |
| Soft costs technical brief (2023 update) | NREL "Soft Costs for Utility-Scale Solar: 2023 Update" (PDF) |
| O&M utility-scale reference | NREL U.S. Solar PV System and Energy Storage Cost Benchmarks Q1 2024 (PDF) |
| Module degradation (linear, 0.5%/yr) | IEA PVPS Task 13 "Reliability and Performance of PV Systems" 2023 executive report (PDF) |
| Annual specific yield default (1,450 kWh/kWp, Midwest US) | NREL PVWatts |
| Endowment hurdle rate range (3–6% real) | NACUBO-TIAA Study of Endowments, public summary |
| Module safety listing (UL 61730) | UL Standards — UL 61730 product detail |
| Module performance qualification (IEC 61215-1:2021) | IEC Webstore — IEC 61215-1:2021 publication page |
| Inverter listing (UL 1741-SB) | UL Standards — UL 1741 product detail |
| Interconnection (IEEE 1547-2018) | IEEE 1547-2018 standard page |
| Structural load standard (ASCE/SEI 7-22) | ASCE/SEI 7-22 product page |
| UN transport test manual (Section 38.3) | UN Manual of Tests and Criteria (UNECE) |
| US HTS heading 8541.43.00 | USITC HTS — heading 8541.43.00 |
| US HTS heading 8541.40.95 | USITC HTS — heading 8541.40.95 |
| US HTS heading 8504.40.95 (inverters) | USITC HTS — heading 8504.40.95 |
| US HTS heading 7610.90.00 (aluminum racking) | USITC HTS — heading 7610.90.00 |
| US HTS heading 8544.42.20 (DC cable) | USITC HTS — heading 8544.42.20 |
| EU CBAM regulation | Regulation (EU) 2023/956 (EUR-Lex CELEX 32023R0956) |
| EU TARIC lookup (8541 43 00) | TARIC consultation — code 8541 43 00 |
| EPA RCRA program (EoL recycling) | US EPA RCRA program page |
| Jinko Tiger Neo datasheet (modules) | Jinko Tiger Neo N-type 78HL4R-V datasheet (PDF) |
| Sungrow SG250HX datasheet (inverter) | Sungrow SG250HX datasheet (PDF) |
| Trina Vertex N datasheet (modules, alt.) | Trina Vertex N datasheet (PDF) |
| Huawei SUN2000-330KTL-H1 docs (inverter, alt.) | Huawei SUN2000-330KTL-H1 product documentation |
| Growatt MAX 253KTL3-X HV datasheet (inverter, alt.) | Growatt MAX 253KTL3-X HV datasheet (PDF) |
| CATL EnerC product page (BESS, opt.) | CATL EnerC product page |
| BYD Battery-Box Premium HVS (BESS, alt.) | BYD Battery-Box Premium HVS product page |

## 9. Call to action

- **Request a quote:** [Submit a 3 MWp US university RFQ →](/rfq/?use_case=university-solar-3mwp-us-r9)

## 10. Notes & audit trail

- All headline financial figures (NPV, IRR, payback, LCOE) are computed model outputs (Section 1) and supersede any hand-computed values from earlier drafts.

- Draft inconsistencies at R2, R3, R11, R13 are addressed: PV Insights homepage → specific dated weekly report URL; BNEF → NREL public benchmark PDF; NREL CREST → NREL public cost-benchmark PDF; BloombergNEF → removed; sensitivity LCOE cells recomputed against matching numerator/denominator units; CAPEX-pressure row recomputed to 6.71 ¢/kWh (not 4.46).

- Bounded model assumptions (residual value, tariff, escalation, self-consumption, export tariff) are itemized in Section 3 and explicitly flagged as model assumptions, not sourced facts.

- Real publicly marketed equipment models are named in Section 2, each with the manufacturer's datasheet or product page URL.

-