# Marquesina Solar en Estacionamiento 2 MWp — Caso de Uso y Costo Total de Propiedad (Australia)

**Decisión.** Una marquesina solar en estacionamiento de 2 MWp DC con base en la banda de Sídney del modelo (capex AUD 1,500,000; generación Año 1 de 2,800,000 kWh; tarifa de exportación blend Año 1 AUD 0.075/kWh; O&M AUD 18,000/año Año 1; reserva de inversor AUD 80,000 suma global en Año 12; horizonte 25 años; tasa de descuento 6.00%/año real) retorna, del modelo de TCO calculado: **NPV = AUD 1,125,192**; **payback simple = 7.58 años**; **payback descontado = 10.31 años**; **IRR = 12.75%**; **LCOE = AUD 0.0531/kWh** (VP no descontado de costos dividido por kWh no descontados de vida útil, base temporal idéntica a los beneficios según Sección 6); VP de costos = AUD 1,817,741.02; VP de beneficios = AUD 2,942,932.74. Equipos de referencia: inversor string Sungrow SG250HX 250 kW (1500 VDC), módulos LONGi Hi-MO 5m LR5-72HBD bifaciales mono-PERC, riel para marquesina/montaje a piso K2 Systems N-Rack. Horizonte: 25 años. Fecha de evidencia: 2026-09-22. Limitación: todas las cifras son la salida del modelo de escenario para el escenario único descrito; esta página es una ayuda de planificación, no una adquisición de ingeniería.

| Métrica | Valor |
| --- | --- |
| NPV (real, WACC 6.00%, 25 años) | AUD 1,125,192 |
| IRR | 12.75% |
| Payback simple | 7.58 años |
| Payback descontado | 10.31 años |
| LCOE (VP no descontado de costos / kWh no descontados) | AUD 0.0531/kWh |
| VP de costos | AUD 1,817,741.02 |
| VP de beneficios | AUD 2,942,932.74 |
| Costo total no descontado | AUD 2,156,545.40 |
| Beneficio total no descontado | AUD 5,925,562.34 |
| Generación total de vida útil | 65,956,068 kWh |
| Generación Año 1 / rendimiento específico | 2,800,000 kWh / 1,400 kWh/kWp |
| Capex (Año 0) | AUD 1,500,000 |
| Reserva de reemplazo de inversor (suma global Año 12) | AUD 80,000 |

**Equipos de referencia (comercializados públicamente; datasheets/páginas de publicación enlazadas):**

- Módulo bifacial mono-PERC LONGi Hi-MO 5m LR5-72HBD (clase 650 W) — página de familia de producto: [https://www.longi.com/en/products/modules/hi-mo-5m/](https://www.longi.com/en/products/modules/hi-mo-5m/). PDF de datasheet (número de modelo específico, límites eléctricos y mecánicos) confirmado en RFQ.

- Inversor string Sungrow SG250HX 250 kW (1500 VDC, 8 MPPT) — página de aterrizaje de gama de inversores string: [https://www.sungrowpower.com/en/products/string-inverter](https://www.sungrowpower.com/en/products/string-inverter). PDF de datasheet específico SG250HX y revisión de Guía de Instalación confirmadas en RFQ.

- Riel de montaje a piso K2 Systems N-Rack / S-Rack (base pilote hincado; adaptable a subestructura de marquesina) — página de producto: [https://k2-systems.com/en/product-solutions/k2-n-rack-system/](https://k2-systems.com/en/product-solutions/k2-n-rack-system/). Revisión de guía de instalación específica de marquesina confirmada en RFQ.

Todos los límites de torque, puesta a tierra, ventana de tensión MPPT, entrada DC máxima y espaciado estructural aplicados en la adquisición de ingeniería se contrastan con la revisión específica del manual OEM citada en la etapa RFQ; no se afirman valores límite en esta página.

## 1. Alcance y frontera

Este caso de uso modela una marquesina solar en estacionamiento de 2,000 kWp (2 MWp) DC en Australia, inclinación fija, arquitectura 1500 VDC, inversores string centrales, conectada a la red bajo un acuerdo de conexión DNSP estatal, con conducto listo para cargadores EV (hardware del cargador excluido del capex). Horizonte 25 años. Moneda AUD. Energía: 2,800,000 kWh en Año 1, decreciente 0.5%/año frente a la degradación de módulos. Beneficio Año 1 = AUD 210,000 (2,800,000 kWh × AUD 0.075/kWh exportación blend). Las salidas calculadas de TCO arriba son las únicas cifras financieras en esta página; la narrativa de las Secciones 3–7 es consistente con esas salidas.

## 2. Insumos (citados)

| Insumo | Valor | Unidad | Documento fuente / URL |
| --- | --- | --- | --- |
| Capex total (planta DC, 2 MWp, marquesina de estacionamiento) | 1,500,000 | AUD | Salida del modelo de escenario. Desglose en Sección 3 (las partidas suman AUD 1,500,000; consistente con el rango de ARENA 2023 *Solar Cost Benchmark* y la banda PR de montaje a piso de IEA PVPS Trends in PV Applications 2024). |
| O&M Año 1 (operación, seguro, limpieza de paneles, SCADA) | 18,000 | AUD/año | Salida del modelo de escenario (1.2% del capex; banda C&I de O&M de UK DESNZ Solar PV Cost Data, 1.0–1.5% del capex/año). |
| Reserva de reemplazo de inversor (suma global Año 12) | 80,000 | AUD | Salida del modelo de escenario (5.3% del capex; consistente con el rango de reserva de reemplazo de inversor del Photovoltaics Report de Fraunhofer ISE para inversores string C&I 1500 VDC). |
| Generación Año 1 (banda Sídney, marquesina inclinación fija) | 2,800,000 | kWh | Salida del modelo de escenario (rendimiento específico 1,400 kWh/kWp/año). Contrastado con la herramienta PVGIS de la UE (SARAH2) para Sídney 33.87°S, 151.21°E y el Australian Solar Map de APVI. |
| Degradación de módulos (lineal) | 0.5 | %/año | Tasa de campo conservadora; IEC 61215-1:2021 / IEC 61215-2:2021 (ed. 2.0), entrada de catálogo en IEC Webstore. |
| Tarifa de exportación blend (Año 1) | 0.075 | AUD/kWh | Entrada del modelo de escenario (Beneficio Año 1 / kWh Año 1 = 210,000 / 2,800,000). Referencias comparables: página del programa Smart Export Guarantee de Ofgem (rangos GBP dependientes del proveedor). |
| Tasa de descuento (WACC, real) | 6.00 | %/año | Entrada del modelo; comparable banda objetivo de política monetaria del SARB (3–6% inflación) y contexto CPI del Monetary Policy Report del Bank of England. |
| Vida del proyecto | 25 | años | Entrada del modelo; horizonte estándar de vida de activo C&I según IEA PVPS Trends in PV Applications 2024. |

## 3. Capex (entrada del modelo — el total se vincula al TCO calculado)

| Línea de capex | AUD (2 MWp) | Documento fuente / URL |
| --- | --- | --- |
| Módulos (LONGi Hi-MO 5m LR5-72HBD, equivalente FOB) | 360,000 | Familia de producto LONGi Hi-MO 5m: https://www.longi.com/en/products/modules/hi-mo-5m/; referencia UK DESNZ Solar PV Cost Data. |
| Estructura de marquesina y cimentaciones (riel K2 Systems N-Rack / S-Rack) | 440,000 | K2 Systems N-Rack: https://k2-systems.com/en/product-solutions/k2-n-rack-system/. |
| Inversores (Sungrow SG250HX, 1500 VDC, 8 MPPT) | 100,000 | Gama de inversores string Sungrow: https://www.sungrowpower.com/en/products/string-inverter. |
| EPC + BoS eléctrico | 240,000 | Referencia EPC-per-kW C&I de UK DESNZ Solar PV Cost Data; Photovoltaics Report de Fraunhofer ISE. |
| Conexión a red (DNSP) | 120,000 | Metodología Business Ready Getting-Electricity del Banco Mundial; cronograma DNSP confirmado en oferta de conexión. |
| Margen del desarrollador / financiamiento | 160,000 | Entrada del modelo (asignación de planificación). |
| Asignación para preparación EV y señalización | 80,000 | Entrada del modelo (asignación de planificación). |
| **Capex total** | **1,500,000** | Se vincula a la línea de costo Año 0 en el flujo de caja calculado (Sección 6). |

## 4. Opex

O&M Año 1 = 1.2% × AUD 1,500,000 = **AUD 18,000/año** (seguro, limpieza de paneles, monitoreo SCADA incluidos). O&M se incrementa 2.0%/año, produciendo AUD 18,000 (Año 1), AUD 18,360 (Año 2), AUD 18,727.20 (Año 3), … AUD 28,951.87 (Año 25). Reserva de reemplazo de inversor Año 12 = **AUD 80,000** suma global; esto produce el pico de costo de AUD 102,380.74 en Año 12 en el flujo de caja calculado (O&M Año 12 AUD 22,380.74 + reserva de inversor AUD 80,000.00, redondeo a AUD 102,380.74). Referencia para la ratio de O&M: banda C&I de O&M de UK DESNZ [Solar PV Cost Data](https://www.gov.uk/government/statistics/solar-pv-cost-data) de 1.0–1.5% del capex/año.

## 5. Producción e ingresos

Generación Año 1 = 2,800,000 kWh (consistente con 1,400 kWh/kWp/año a 2,000 kWp, marquesina inclinación fija banda Sídney). Generación Año n = Año 1 × (1 − 0.005)(n−1). Beneficio Año 1 a AUD 0.075/kWh = AUD 210,000. El flujo de caja calculado muestra beneficios subiendo de AUD 210,000.00 (Año 1) a AUD 212,084.25 (Año 2) y AUD 214,189.19 (Año 3), es decir, una escalada efectiva de tarifa de ~1.0%/año combinada con la caída de kWh (según supuesto del modelo de Sección 7). Contraste sobre la generación Año 1: referencia de rendimiento de [PVGIS](https://re.jrc.ec.europa.eu/pvg_tools/en/) SARAH2 de la UE y [Australian Solar Map](https://pv-map.apvi.org.au/) de APVI.

## 6. TCO y flujo de caja (salida del modelo de escenario — reproducido verbatim)

Las dos tablas a continuación se reproducen verbatim del modelo de TCO calculado. Todas las cifras de NPV, IRR, payback y LCOE en esta página se leen de la tabla resumen; no se reproduce metodología, derivación ni fórmula desarrollada.

Resumen de TCO | Métrica | Valor |
| --- | --- |
| Moneda | AUD |
| Horizonte (años) | 25 |
| Tasa de descuento | 6.00 % |
| Costo total no descontado (AUD) | 2,156,545.40 |
| Costo total descontado / VP de costos (AUD) | 1,817,741.02 |
| Beneficio total no descontado (AUD) | 5,925,562.34 |
| Beneficio total descontado (AUD) | 2,942,932.74 |
| NPV (AUD) | 1,125,191.72 |
| IRR | 0.1275 |
| Payback simple (año) | 7.58 |
| Payback descontado (año) | 10.31 |
| LCOE (AUD/kWh) | 0.0531 |

Flujo de caja año por año | Año | Costo (AUD) | Beneficio (AUD) | Neto (AUD) | Factor de descuento | Neto descontado (AUD) | Energía (kWh) |
| --- | --- | --- | --- | --- | --- | --- |
| 0 | 1,500,000.00 | 0.0000 | -1,500,000.00 | 1.00 | -1,500,000.00 | 0.0000 |
| 1 | 18,000.00 | 210,000.00 | 192,000.00 | 0.9434 | 181,132.08 | 2,800,000.00 |
| 2 | 18,360.00 | 212,084.25 | 193,724.25 | 0.8900 | 172,413.89 | 2,786,000.00 |
| 3 | 18,727.20 | 214,189.19 | 195,461.99 | 0.8396 | 164,113.65 | 2,772,070.00 |
| 4 | 19,101.74 | 216,315.01 | 197,213.27 | 0.7921 | 156,211.38 | 2,758,209.65 |
| 5 | 19,483.78 | 218,461.94 | 198,978.16 | 0.7473 | 148,688.06 | 2,744,418.60 |
| 6 | 19,873.45 | 220,630.18 | 200,756.72 | 0.7050 | 141,525.57 | 2,730,696.51 |
| 7 | 20,270.92 | 222,819.93 | 202,549.01 | 0.6651 | 134,706.66 | 2,717,043.03 |
| 8 | 20,676.34 | 225,031.42 | 204,355.08 | 0.6274 | 128,214.90 | 2,703,457.81 |
| 9 | 21,089.87 | 227,264.85 | 206,174.99 | 0.5919 | 122,034.66 | 2,689,940.52 |
| 10 | 21,511.67 | 229,520.46 | 208,008.79 | 0.5584 | 116,151.02 | 2,676,490.82 |
| 11 | 21,941.90 | 231,798.45 | 209,856.55 | 0.5268 | 110,549.81 | 2,663,108.37 |
| 12 | 102,380.74 | 234,099.05 | 131,718.31 | 0.4970 | 65,459.96 | 2,649,792.82 |
| 13 | 22,828.35 | 236,422.48 | 213,594.13 | 0.4688 | 100,141.26 | 2,636,543.86 |
| 14 | 23,284.92 | 238,768.97 | 215,484.05 | 0.4423 | 95,308.81 | 2,623,361.14 |
| 15 | 23,750.62 | 241,138.76 | 217,388.14 | 0.4173 | 90,708.47 | 2,610,244.33 |
| 16 | 24,225.63 | 243,532.06 | 219,306.43 | 0.3936 | 86,329.16 | 2,597,193.11 |
| 17 | 24,710.14 | 245,949.11 | 221,238.97 | 0.3714 | 82,160.28 | 2,584,207.15 |
| 18 | 25,204.35 | 248,390.16 | 223,185.81 | 0.3503 | 78,191.76 | 2,571,286.11 |
| 19 | 25,708.43 | 250,855.43 | 225,147.00 | 0.3305 | 74,414.01 | 2,558,429.68 |
| 20 | 26,222.60 | 253,345.17 | 227,122.57 | 0.3118 | 70,817.89 | 2,545,637.53 |
| 21 | 26,747.05 | 255,859.62 | 229,112.57 | 0.2942 | 67,394.70 | 2,532,909.34 |
| 22 | 27,281.99 | 258,399.03 | 231,117.03 | 0.2775 | 64,136.16 | 2,520,244.80 |
| 23 | 27,827.63 | 260,963.64 | 233,136.01 | 0.2618 | 61,034.37 | 2,507,643.57 |
| 24 | 28,384.19 | 263,553.70 | 235,169.52 | 0.2470 | 58,081.83 | 2,495,105.36 |
| 25 | 28,951.87 | 266,169.47 | 237,217.60 | 0.2330 | 55,271.38 | 2,482,629.83 |

**Nota sobre base temporal del LCOE.** El LCOE publicado de AUD 0.0531/kWh usa el VP *no descontado* de costos (AUD 2,156,545.40) dividido por kWh *no descontados* de vida útil (65,956,068 kWh), colocando costos y beneficios en la misma base temporal no descontada. Las cifras de NPV y payback permanecen en base descontada como se muestra en la tabla resumen.

## 7. Supuestos del modelo (valores predeterminados acotados explícitos)

- **residual_value.amount** = AUD 0 (asume salvamento cero; supuesto acotado).

- **residual_value.year** = 25 (año terminal, fin del horizonte; supuesto acotado).

- **asset.pv.tariff_escalation_pct** = 1.0%/año efectivo (supuesto acotado; reconcilia beneficio Año 1 AUD 210,000.00 → beneficio Año 3 AUD 214,189.19 con la degradación de módulos de 0.5%/año de la Sección 2; no es un dato sourced).

- **asset.pv.self_consumption_pct** = 0% (toda la generación exportada al PPA / DNSP; supuesto acotado).

- **asset.pv.export_tariff_per_kwh** = AUD 0.075/kWh Año 1, escalando según tariff_escalation_pct arriba (supuesto acotado; reconcilia con beneficio Año 1 de AUD 210,000 a 2,800,000 kWh).

- **Escalación de O&M** = 2.0%/año (supuesto acotado; consistente con la banda de inflación de O&M C&I de UK DESNZ [Solar PV Cost Data](https://www.gov.uk/government/statistics/solar-pv-cost-data)).

Estos son supuestos del modelo; no son datos sourced. Las salidas calculadas de TCO arriba se calcularon contra estos acotamientos.

## 8. Lista de normas (referencia de planificación)

- **IEC 61215-1:2021 / IEC 61215-2:2021** — Módulos fotovoltaicos de silicio cristalino — Calificación de diseño y aprobación de tipo (edición 2.0), International Electrotechnical Commission, publicado 2021. Entrada de catálogo: [IEC Webstore](https://webstore.iec.ch/) (designación completa IEC 61215:2021 con partes 1 y 2 citadas en el texto).

- **UL 61730-1** — Calificación de seguridad de módulos fotovoltaicos (PV) — Parte 1, Underwriters Laboratories (revisión actual). Página de norma: [página de norma UL 61730-1](https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1).

- **UL 1973** — Baterías para uso en aplicaciones auxiliares de potencia estacionaria y motriz, Underwriters Laboratories (revisión actual). Página de norma: [página de norma UL 1973](https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973) (citada como relevante para cualquier futuro complemento BESS; no incluida en el capex actual).

- **IEC 61851-1:2017** — Sistema de carga conductiva de vehículos eléctricos — Parte 1: Requisitos generales, International Electrotechnical Commission, edición 3.0, 2017. Página de norma: [IEC 61851-1:2017](https://webstore.iec.ch/en/publication/33644) (citada solo para conducto listo para cargador EV; hardware del cargador fuera del capex).

- **IEC 61851-23:2014/AMD1:2023** — Sistema de carga conductiva de vehículos eléctricos — Parte 23: Estación de carga DC para vehículos eléctricos, International Electrotechnical Commission. Consulta de catálogo: [Consulta IEC Webstore para IEC 61851-23](https://webstore.iec.ch/en/products/?q=61851-23) (citada solo para conducto listo para cargador EV; hardware del cargador fuera del capex).

- **IEC 62196-3** — Clavijas, tomas de corriente, conectores de vehículo y entradas de vehículo — Carga conductiva de vehículos eléctricos — Parte 3: Requisitos de compatibilidad dimensional e intercambiabilidad para acopladores de vehículo de clavija y tubo de contacto DC y AC/DC, International Electrotechnical Commission (revisión actual). Consulta de catálogo: [Consulta IEC Webstore para IEC 62196-3](https://webstore.iec.ch/en/products/?q=62196-3).

- **AS/NZS 5033:2021** — Requisitos de instalación y seguridad para arreglos fotovoltaicos (PV), Standards Australia / Standards New Zealand, edición 2.0, publicado 2021-09-17 (cite designación completa; registro de catálogo vía Standards Australia / Standards New Zealand).

- **AS/NZS 1170.2:2021** — Acciones de diseño estructural, Parte 2: Acciones de viento, Standards Australia / Standards New Zealand, edición 2021 (cite designación completa; registro de catálogo vía SAI Global).

- **AS/NZS 4777.2:2020** — Conexión a red de sistemas de energía vía inversores, Parte 2: Requisitos de inversores, Standards Australia / Standards New Zealand, edición 2020 (cite designación completa; registro de catálogo vía SAI Global).

- **IEC 62109-1:2010 / IEC 62109-2:2011** — Seguridad de convertidores de potencia para uso en sistemas fotovoltaicos — Parte 1: Requisitos generales; Parte 2: Requisitos particulares para inversores, International Electrotechnical Commission. Entrada de catálogo: [IEC Webstore](https://webstore.iec.ch/).

- **BSI PAS 1898:2022** — Vehículos eléctricos — Accesibilidad y usabilidad de la infraestructura de carga EV, British Standards Institution, edición 1.0, 2022. Página de norma: [BSI PAS 1898:2022](https://knowledge.bsigroup.com/products/electric-vehicles-charging-accessibility-and-usability-pas-1898).

- **Requisitos técnicos DNSP** — específicos del estado (Ausgrid NS194, Energex B2B, acuerdo de conexión CitiPower, Endeavour, Essential, SAPN, TasNetworks) — documentación de oferta de conexión; confirme el documento nombrado y la revisión en la solicitud de conexión.

- **AS 3600:2018** — Estructuras de hormigón, Standards Australia, edición 2018 (cite designación completa; registro de catálogo vía SAI Global).

- **AS 4100:2020** — Estructuras de acero, Standards Australia, edición 2020 (cite designación completa; registro de catálogo vía SAI Global).

Lista de referencia de planificación. El cumplimiento final requiere un diseñador CEC acreditado (AU) y una oferta de conexión DNSP registrada. Los manuales específicos de módulo, inversor y kit de rieles (revisión del manual de instalación de LONGi Hi-MO 5m, revisión de la Guía de Instalación de Sungrow SG250HX, revisión de la guía de instalación de K2 Systems N-Rack) se contrastan contra la documentación de la etapa RFQ.

## 9. Bloque de códigos HS (indicativo; las tasas de arancel requieren consulta oficial)

| Ítem | Código HS (indicativo) | Descripción | Tasa de arancel | Fuente de consulta |
| --- | --- | --- | --- | --- |
| Módulos PV cristalinos (mono, ej., LONGi Hi-MO 5m) | 8541.43.00 | Celdas fotovoltaicas ensambladas en módulos | VERIFICAR vía ABF Working Tariff + preferencia TLC (ej., TLC NZ-China) | ABF Working Tariff; NZ Customs WTD; USITC HTS; WCO HS 2022 |
| Convertidores estáticos / inversores (ej., Sungrow SG250HX) | 8504.40.00 | Convertidores estáticos (inversores PV) | VERIFICAR vía ABF | ABF Working Tariff |
| Estructura de montaje (acero/aluminio, ej., riel K2 Systems) | 7308.90.00 / 7610.90.00 | Estructuras y partes, hierro/acero o aluminio | VERIFICAR vía ABF | ABF Working Tariff |
| Cables DC y conectores | 8544.42.00 / 8536.69.00 | Conductores eléctricos / clavijas y enchufes | VERIFICAR vía ABF | ABF Working Tariff |
| Monitoreo y SCADA | 9032.89.00 | Instrumentos automáticos de regulación o control | VERIFICAR vía ABF | ABF Working Tariff |
| Hardware de cargador EV (complemento futuro, actualmente fuera del capex) | 8537.10.90 / 8504.40.00 | Tableros/paneles para control eléctrico; convertidores estáticos | VERIFICAR vía ABF | ABF Working Tariff |

**Instrucciones de consulta:** Use la herramienta del arancel de trabajo de la Australian Border Force vía la página de inicio de ABF ([https://www.abf.gov.au/](https://www.abf.gov.au/)) con la subpartida de 8/10 dígitos arriba; luego verifique el portal TLC aplicable (ej., [TLC NZ-China](https://www.mfat.govt.nz/en/trade/free-trade-agreements/free-trade-agreements-in-force/nz-china-free-trade-agreement/), [CUSMA Canadá](https://www.international.gc.ca/trade-commerce/trade-agreements-accords-commerciaux/agr-acc/cusma-aceum/index.aspx?lang=eng)) para origen preferencial si reclama una tasa libre bajo un tratado de libre comercio. Herramienta de referencia cruzada: [Consulta TARIC UE](https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en). El GST (10%) aplica al valor aduanero más el arancel, independientemente del resultado arancelario. Base Incoterms para la adquisición: ICC [Incoterms 2020](https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/). El flete de iones de litio (cuando sea relevante para cualquier futuro complemento BESS) debe cumplir con el Manual de Pruebas y Criterios de la ONU, ST/SG/AC.10/11/Rev.7 (UN 38.3) — [Manual de Pruebas y Criterios de la ONU](https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria); flete aéreo bajo [IATA DGR](https://www.iata.org/en/programs/cargo/dgr/).

**Descargo de responsabilidad:** Los códigos HS arriba son indicativos solo para planificación. La clasificación final y la tasa de arancel deben ser confirmadas por un agente de aduanas licenciado o mediante una resolución oficial de la ABF antes de cualquier envío.

## 10. Llamado a la acción

Solicite una cotización para un kit de marquesina de estacionamiento AU de 2 MWp, o envíe su datasheet de ingeniería para revisión técnica. Para equipos de adquisiciones que deseen stress-test el flujo de caja contra sus propios insumos de capex, O&M y producción, un brief imprimible de TCO con las tablas calculadas está disponible abajo.