# Acceptance Quality Limit (AQL)

**Acceptance Quality Limit (AQL)** under ISO 2859-1 is the maximum defective percentage (or number of defects per hundred units) considered acceptable as a process average during statistical pre-shipment lot sampling, defining the exact sample size (`n`), acceptance number (`Ac`), and rejection number (`Re`) for a given shipment lot size.

## How it is measured and specified

International standard **ISO 2859-1** (*Sampling procedures for inspection by attributes — Part 1: Sampling schemes indexed by acceptance quality limit for lot-by-lot inspection*) uses a two-step lookup to govern factory lot release. First, the inspector cross-references the total production lot size against the specified inspection level—most commonly **General Inspection Level II** for normal commercial shipments—to obtain a sample-size code letter and the corresponding number of units (`n`) to pull at random from the lot.

Second, for each defect severity tier (Critical, Major, and Minor), the inspector looks up the chosen AQL value to find two integer thresholds: the **acceptance number (`Ac`)**, which is the maximum count of non-conforming units that still permits lot release, and the **rejection number (`Re`)**, which triggers immediate lot rejection, quarantine, and 100% factory sorting or rework.

## How it matters when sourcing from China

When purchasing LFP battery modules, high-voltage packs, solar PV pallets, or EV chargers from Chinese factories, writing ISO 2859-1 AQL thresholds directly into the purchase contract and pre-shipment inspection (PSI) protocol prevents subjective disputes over whether a batch passes or fails before the balance payment is released. Across Tradvolt's factory inspection SOPs, defects are partitioned into three strict severity classes:

- **Critical Defects (AQL 0 — `Ac = 0, Re = 1`):** Any defect that creates a safety hazard, regulatory non-compliance, or dielectric breakdown results in immediate lot quarantine upon a single occurrence. In the [battery pack hipot dielectric test SOP (China-to-Pakistan corridor)](/en/guides/battery-pack-hipot-dielectric-test-sop-tradvolt-cnpk-evse-maintenance/), flashover, arcing, leakage current exceeding the 5 mA threshold, or insulation resistance below 100 MΩ at 1000 V DC is classified as Critical (AQL 0), halting shipment until 100% of packs are re-screened.

- **Major Defects (AQL 1.0):** Functional or performance deviations that fall outside datasheet tolerances. In the [battery pack capacity-retention test SOP (China-to-Jamaica corridor)](/en/guides/battery-pack-capacity-retention-test-process-sop-tradvolt/), for a 50-pack shipment lot inspected at General Inspection Level II (Code Letter D, sample size `n = 8`), Major defects at AQL 1.0 allow `Ac = 1, Re = 2` for packs failing the ≥95% discharge capacity threshold or busbar torque specification, while Critical defects (electrolyte leakage, thermal runaway alarm, or cell swelling >1.5 mm) remain at AQL 0 (`Ac = 0, Re = 1`).

- **Minor Defects (AQL 2.5):** Cosmetic scratches, minor carton scuffs, or non-safety label alignment tolerances that do not impair electrical performance or customs clearance, as applied alongside electrical grading in the [battery module EOL grading SOP (China-to-Spain corridor)](/en/guides/battery-module-eol-grading-sop-cnes-corridor-lfp-vertical-tradvolt/) and physical nameplate checks in the [CE technical-file compilation SOP (China-to-Georgia corridor)](/en/guides/ce-technical-file-compilation-sop-china-to-georgia-corridor-sungrow-longi-trina-vertical-solar-bos-tradvolt/).

## What to confirm before procurement

- Attach an explicit Defect Classification Matrix (Critical = AQL 0, Major = AQL 1.0, Minor = AQL 2.5 under ISO 2859-1 General Inspection Level II) as an annex to the sales contract before paying the deposit.

- Require at least 80%–100% of the export lot to be fully assembled, tested, and packed before the third-party inspector draws the random sample.

- Specify that any lot reaching the rejection number (`Re`) must undergo 100% factory sorting and a paid re-inspection at the supplier's expense prior to container loading.