# How Tradvolt builds a cost model

Every study on this site follows one discipline: separate what a supplier quoted, what a public source states, what is a scenario assumption, and what is a calculated result. Where an input is not available, it is written down as an open item for the buyer to confirm — it is not filled with an invented number.

This methodology hub gives engineering, finance, and procurement teams the exact accounting rules behind every Tradvolt landed-cost and total-cost-of-ownership (TCO) study so you can audit our numbers or stress-test a live supplier quote. Across all studies, Tradvolt computes present value of costs, net present value (NPV), internal rate of return (IRR), simple and discounted payback, Levelised Cost of Energy (LCOE), Levelised Cost of Storage (LCOS), and EV-vs-ICE TCO per kilometre from a single year-by-year cash-flow architecture. To prevent hidden optimism, every model enforces a strict four-way boundary between supplier-quoted figures, cited public facts (OEM datasheets, IEC/UL standards, WCO HS headings, IRENA/BNEF benchmarks), explicit bounded scenario defaults (specific yield, duty cycle, port utilisation, WACC, tariff escalation), and unresolved customs duty or VAT rates flagged as `PENDING — lookup`. Use the four asset-class templates below—Landed Cost, Battery & Storage TCO, Solar PV TCO, and EV Charging TCO—together with our verification protocol to decide which cost lines belong in your tender evaluation and which open inputs must be confirmed before contract award.

## The shared principle

The overall approach, including how evidence dates and exclusions are handled, is described on [how we model landed cost and total cost of ownership](/process/). The pages below apply that approach to specific equipment classes.

Across all equipment classes, the computation engine in `tco_model.py` builds a year-by-year cash-flow table from Year 0 through the stated analysis horizon (validated between 1 and 60 years) on a single consistent basis—either nominal/undiscounted or real/discounted, never mixed. Capital outlays enter at Year 0 or their scheduled installation year, fixed annual operating costs start in Year 1 and compound at the stated annual escalation percentage, scheduled component replacements enter in their designated year, and any end-of-horizon residual value is recorded as a negative cost in the terminal year. Each year's net flow (`benefit - cost`) and delivered energy are discounted by `1 / (1 + discount_rate)^year` so that net present value (NPV), bisection internal rate of return (IRR), cumulative-sum simple and discounted payback, and levelised energy cost (LCOE or LCOS) are mathematically consistent.

## Method pages by equipment class

- [Landed cost](/methods/landed-cost/) — what sits between a supplier price and a delivered unit: the agreed Incoterm baseline, export inland haulage, ocean or air freight, marine insurance, border charges (customs duty, levies, VAT, brokerage and port handling), and destination delivery, with tariff classification and duty rates recorded as pending until confirmed with the destination authority.

- [Battery and storage TCO](/methods/battery-tco/) — cycling, augmentation and end-of-life: models nominal kWh, usable fraction, round-trip efficiency (where charging energy drawn equals discharged energy divided by round-trip efficiency), annual cycle count, compound annual capacity fade, mid-life augmentation reserves, and present-value Levelised Cost of Storage (LCOS).

- [Solar PV TCO](/methods/solar-tco/) — yield, degradation and balance of system: models peak DC capacity (kWp), location specific yield (kWh/kWp/year), compound annual module degradation, self-consumption share versus export tariff, annual tariff escalation, mid-life inverter replacement reserves, and present-value Levelised Cost of Electricity (LCOE).

- [EV charging TCO](/methods/ev-charging-tco/) — utilisation, grid connection and service life: combines multi-port AC and DC charger hardware, switchgear, civil works, and grid connection capacity with fleet operating parameters (vehicles, annual kilometres, kWh per km, electricity price, and EV maintenance per km) against an internal-combustion diesel comparator to compute TCO per kilometre and horizon savings.

## What is deliberately excluded

Models do not monetize benefits that the buyer has not quantified — resilience, avoided outage cost, carbon value or brand effects — unless a study says so explicitly and states the basis. They do not assume a certification, a warranty term or a lead time that no document in the study establishes.

Baseline scenario calculations also omit unquoted financing fees, foreign-exchange hedging costs, peak demand-charge reductions on energy-only storage runs, ancillary-service or capacity-market payments, and national customs duties that depend on binding tariff rulings. Where a project's payback depends on those excluded streams, the study publishes the negative or conditional baseline result transparently and identifies which input levers must change before procurement.

## How to choose which model applies

Start from the question you are being asked to answer. If it is what the goods cost to have delivered, use [landed cost](/methods/landed-cost/) and stop there. If it is what the equipment will cost over its life, add the class that matches the equipment — [storage](/methods/battery-tco/), [solar](/methods/solar-tco/) or [charging](/methods/ev-charging-tco/) — and note that a hybrid site needs more than one.

Before relying on any single point estimate, test the three primary sensitivity levers defined for each asset class in the model engine—discount rate plus tariff and specific yield for solar PV, discharged-energy value and charging cost for battery storage, or diesel price per litre and electricity tariff for EV fleets—under plus-or-minus 20% shocks to see how NPV and payback respond.

All four share the same evidence discipline described on [how we model landed cost and total cost of ownership](/process/): what is quoted, what is public, what is assumed and what is calculated are kept separate, and an unavailable input is recorded as open rather than filled in.

## Start here: flagship studies & method notes

- [How landed cost is calculated](/methods/landed-cost/) — Step-by-step Year-0 landed-cost formula covering ex-factory/FOB supplier price, ocean freight & marine insurance, CIF customs value, HS tariff duties, import VAT/GST, port handling, and inland haulage.

- [How battery and storage TCO is modelled](/methods/battery-tco/) — Stationary storage LCOS model covering 88%–92% LFP round-trip efficiency, usable depth of discharge, calendar and cycle fade, mid-life augmentation reserves (such as Year 7), and charging electricity cost treatment.

- [How solar PV TCO is modelled](/methods/solar-tco/) — 25-year PV LCOE and cash-flow model covering module FOB and balance-of-system stack, Year-1 specific yield (kWh/kWp/yr), 0.5%/yr linear degradation, and mid-life string inverter replacement reserves.

- [How EV charging TCO is modelled](/methods/ev-charging-tco/) — Commercial EVSE depot and corridor TCO model separating AC (7–22 kW) vs. DC (60–480 kW) hardware, site civil works and grid connection capacity, port utilisation, and EV-vs-ICE fleet TCO per km.

- [How we model landed cost and total cost of ownership](/process/) — Tradvolt's five-step sourcing-evidence and verification protocol defining how OEM datasheets, IEC/UL standards, and official customs portals are separated from bounded model assumptions.

## Browse by buyer decision

### 1. Building the Year-0 landed-cost stack (FOB, freight, HS duty & VAT)

Decompose the charges between a Chinese factory gate and site delivery, and see how unresolved tariff headings are flagged for broker confirmation.

- [Method: How landed cost is calculated](/methods/landed-cost/)

- [Worked example: 670W Solar Panel — China to Ghana Landed Cost & TCO](/en/tco/import-solar-panel-670w-from-china-to-ghana-ground-mount-use-case-tco-landed-cost-tradvolt/)

- [Worked example: 610W Bifacial PV Module — China to Lithuania Agrivoltaic](/en/tco/import-610w-bifacial-pv-module-longi-hi-mo-6-jinko-tiger-neo-from-china-to-lithuania-agrivoltaic-tco-landed-cost-tradvolt/)

- [Worked example: Sungrow SH20T + CATL LFP — China to Italy Resort TCO](/en/tco/import-sungrow-sh20t-hybrid-inverter-catl-lfp-battery-from-china-to-italy-resort-tco-tradvolt/)

### 2. Modelling stationary battery LCOS, fade & augmentation reserves

Audit how daily cycling duty, round-trip efficiency, annual capacity fade, and mid-life augmentation reserves govern 10- to 15-year storage economics.

- [Method: How battery and storage TCO is modelled](/methods/battery-tco/)

- [Worked example: 10 MWh LFP BESS — Data Center, Southeast Asia (10-yr TCO)](/en/tco/10-mwh-lfp-bess-data-center-southeast-asia-10-yr-tco-tradvolt/)

- [Worked example: Hospital ESS 3 MWh — Middle East & Africa (15-yr TCO)](/en/tco/hospital-ess-3-mwh-middle-east-africa-tco-use-case-tradvolt-com/)

- [Worked example: 2 MWh LFP Container ESS — China to Germany Datacenter](/en/tco/import-lfp-2-mwh-container-ess-from-china-to-germany-datacenter-ess-tco-tradvolt/)

### 3. Computing 25-year solar PV LCOE, yield & inverter replacement

Examine how location-specific yield, linear module degradation, tariff escalation, and Year-12 inverter replacement reserves drive PV payback.

- [Method: How solar PV TCO is modelled](/methods/solar-tco/)

- [Worked example: 2 MWp Rooftop Solar — Indian Convention Center (25-yr TCO)](/en/tco/2-mwp-rooftop-solar-for-indian-convention-center-use-case-tco/)

- [Worked example: 1.005 MWp Ground-Mount 670W Solar — China to Ghana](/en/tco/import-solar-panel-670w-from-china-to-ghana-ground-mount-use-case-tco-landed-cost-tradvolt/)

- [Worked example: 620W Solar Panel — China to Chile Ground-Mount TCO](/en/tco/import-solar-panel-620w-from-china-to-chile-ground-mount-tco-tradvolt/)

### 4. Auditing EV charging utilisation, grid make-ready & claim verification

Evaluate port utilisation, transformer and civil works CapEx, EV-vs-ICE fleet TCO per km, and how sourced facts are separated from assumptions.

- [Method: How EV charging TCO is modelled](/methods/ev-charging-tco/)

- [Protocol: How we model landed cost and total cost of ownership](/process/)

- [Worked example: 100-Port EVSE Depot — Automotive Assembly Plant, MEA](/en/tco/100-port-evse-depot-tco-automotive-assembly-plant-mea-tradvolt/)

- [Worked example: 120 kW DC EVSE — China to Netherlands Bus Depot](/en/tco/import-120kw-dc-evse-from-china-to-netherlands-bus-depot-25-yr-tco-tradvolt/)

## Frequently asked questions about Tradvolt cost modelling

### 1. How does Tradvolt discount costs, benefits, and energy throughput in its LCOE and LCOS formulas?

In every computed Tradvolt study, both annual cash flows (costs and benefits) and annual energy throughput (kWh generated or discharged after annual degradation) are discounted at the stated project discount rate (WACC). LCOE and LCOS are calculated as the present value of discounted lifecycle costs divided by the present value of discounted energy throughput over the 10- to 25-year horizon, keeping the time basis strictly aligned with Net Present Value (NPV).

### 2. What items are deliberately excluded from Tradvolt's baseline TCO models?

Unless a study explicitly states a monetised basis, baseline models exclude unquantified co-benefits such as avoided outage or SLA downtime penalties, resilience value, demand-charge savings on energy-only runs, ancillary services revenue, carbon credits, FX hedging costs, and project financing fees. Similarly, models never assume customs duty exemptions, product certifications, or warranty terms that are not established by a cited document.

### 3. How does the battery TCO model avoid double-counting charging electricity cost?

In stationary storage studies (such as the [10 MWh Southeast Asia data center BESS](/en/tco/10-mwh-lfp-bess-data-center-southeast-asia-10-yr-tco-tradvolt/) and [3 MWh MEA hospital ESS](/en/tco/hospital-ess-3-mwh-middle-east-africa-tco-use-case-tradvolt-com/) models), the cost of grid or solar electricity drawn to charge the battery—adjusted for DC/AC round-trip efficiency (typically 88%–92% for LFP)—is already included inside the annual Cost column of the year-by-year cash-flow table. Therefore, charging electricity is not added a second time when computing LCOS from the present value of costs.

### 4. Why does the solar TCO model include a mid-life cash-flow spike between Year 10 and Year 15?

While crystalline silicon PV modules are typically modelled over a 25-year operating horizon with 0.4%–0.55% annual linear degradation, three-phase string inverters carry shorter standard warranty envelopes. Tradvolt's 25-year solar PV models (such as the [2 MWp Indian convention center rooftop study](/en/tco/2-mwp-rooftop-solar-for-indian-convention-center-use-case-tco/)) book an explicit inverter replacement or overhaul reserve—for example, 10% of initial CapEx in Year 12—so lifecycle LCOE and NPV reflect realistic power-electronics replacement.