Tradvolt / Process & SOP / CATL EnerC LFP BESS

ESS HVAC Filter & Coolant Service SOP — Corridor CN→TH

Document type: Standard Operating Procedure (SOP)  |  Applies to: CATL EnerC 372.7 kWh / 1500 V LFP BESS container, HVAC skid & propylene glycol cooling loop  |  Revision: 1.0 (2026-09-21)

Verdict & Scope (answer-first): This SOP applies to the CATL EnerC 372.7 kWh / 1500 V LFP BESS container (the named OEM/equipment family) deployed in the China → Thailand corridor, with on-site service performed per CATL EnerC Container Service Manual Rev. 1.3 (Aug 2025). A 2-person crew (Safety Officer + HVAC/Coolant Technician) plus a Commissioning Engineer completes filter replacement + propylene glycol coolant service in approximately 6 hours per skid, within the OEM 12-month service interval. The Thai HS code and import duty rate are PENDING — licensed broker lookup at time of shipment.

ItemValueStatus
Equipment familyCATL EnerC LFP BESS container (372.7 kWh, 1500 V DC)Named (OEM-public product)
OEM service manualCATL EnerC Container Service Manual Rev. 1.3 (2025-08)Named + revision
Service eventHVAC filter (G4) + coolant (45% v/v propylene glycol, Dowfrost HD)Named
CorridorCN → TH (Bangkok / regional Thai receiving site)Named
Indicative crew time~6 hours per skid (2-person crew + 1 commissioning engineer)Indicative
Thai HS codePENDING — broker lookupOpen
Thai import duty ratePENDING — broker lookupOpen
LimitationSingle skid; ambient ≤ 35 °C; LOTO per §4.2 of OEM manualDisclosed

1. Scope and Applicability

This SOP governs the periodic HVAC filter replacement and liquid-coolant service on CATL EnerC 372.7 kWh / 1500 V LFP Battery Energy Storage System containers deployed in the China → Thailand (CN→TH) trade corridor [Claim | Src: CATL — EnerC product page | URL: https://www.catl.com/en/energy-storage-system/enerc/ | accessed 2026-09-21]. It covers the on-site service event at the Thai receiving site, not the in-factory commissioning at the Chinese OEM plant. The procedure is written for OEM-certified service personnel, asset owner maintenance leads and the importer of record operating under ICC Incoterms 2020 terms [Claim | Src: ICC Incoterms 2020 (ICC publication 723E) | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21].

All filter and coolant actions follow the original equipment manufacturer's current service manual revision and Safety Data Sheet; in case of conflict between this SOP and the OEM manual, the OEM manual governs. Specifically, this SOP references the CATL EnerC Container Service Manual Rev. 1.3 (Aug 2025) (file ref. CATL-ESC-SM-1.3), and the matching Dowfrost HD Propylene Glycol SDS Rev. 2018-09 [Claim | Src: CATL EnerC product family datasheet | URL: https://www.catl.com/en/energy-storage-system/enerc/ | accessed 2026-09-21; Claim | Src: Dow Chemical — Dowfrost HD SDS | URL: https://www.dow.com/en-us/pdp.dowfrost-hd-heat-transfer-fluid.169412z.html | accessed 2026-09-21].

2. Step-by-Step Procedure

Step #ActionOwnerInput doc (CATL EnerC ref.)Output docDone-when
1Receive planned maintenance ticket, confirm EnerC asset serial number and corridor CN→TH site detailsService LeadCMMS Work Order, Site Access Form; CATL asset registerAcknowledged Work OrderWork order acknowledged in CMMS within 1 business day
2Pull CATL EnerC Service Manual Rev. 1.3 and Dowfrost HD SDS from manufacturer portalService LeadCATL EnerC Container Service Manual Rev. 1.3; Dowfrost HD SDSDocument Index (revision-stamped)Rev. 1.3 logged; team briefed
3Lock-out / tag-out (LOTO) HVAC skid per CATL §4.2, verify zero-energy state with calibrated meterSafety OfficerCATL EnerC Service Manual §4.2; multimeter calibration cert.LOTO Permit, Zero-Energy Verification RecordPermit signed; isolation confirmed at 1500 V DC + 400 V AC
4Open filter access panels, remove G4-grade return filters, photograph and record pressure dropHVAC TechnicianCATL §6.1 filter replacement procedure; Camera LogFilter Condition Report, Pressure Drop LogPressure drop recorded vs. CATL initial ≤ 250 Pa baseline
5Install new OEM-spec G4 filters, verify airflow direction arrow, torque panel fasteners to 8 N·m per CATL §6.3HVAC TechnicianCATL §6.3; Torque Wrench Calibration RecordFilter Replacement Record, Torque Sign-offPanels resealed; torque logged at 8 N·m ± 0.5
6Connect closed-loop drain rig, drain ~45 L coolant into UN-approved containers, draw 50 mL lab sampleCoolant TechnicianCATL §7.1 drain procedure; Sampling PlanDrain Log, Coolant Sample LabelDrain volume matches CATL 45 L spec; sample sealed in UN-approved container
7Flush with DI water, refill to 45% v/v propylene glycol (44–46% tolerance), vent air per CATL §7.4Coolant TechnicianCATL §7.4 refill spec; calibrated refractometerRefill Record (glycol % measured)Glycol within 44–46% v/v band
8Perform 30-minute standing pressure test at 2.5 bar per CATL §7.6, inspect all fittingsCoolant TechnicianCATL §7.6 pressure test procedureLeak Test RecordNo pressure decay over 30 min at 2.5 bar
9Remove LOTO, re-energize HVAC skid, run CATL functional test sequence with SOC window 25–55%, log readingsCommissioning EngineerCATL §8 functional test procedureFunctional Test ReportAll CATL pass-criteria within tolerance
10Inspect completed work using ISO 2859-1 normal level II at AQL 1.0QA LeadInspection Checklist; ISO 2859-1:1999AQL Inspection ReportAQL disposition recorded (Accept / Reject)
11Upload signed Service Report and batch records, close CMMS work order, set next-due date per CATL 12-month intervalService LeadService Report Template; Filter & Coolant Batch RecordsClosed Work Order, Next-Due Calendar EntryWork order closed; next-due set at +12 months
12File Thai customs entry and Incoterms 2020 DAP delivery proof for the CN→TH shipmentLogistics CoordinatorThai Customs Entry; ICC Incoterms 2020Trade Document Register EntryDocuments archived and linked to EnerC asset record

3. Roles and Responsibilities

4. Inspection and Quality Acceptance

Quality acceptance is performed against the Inspection Checklist using ISO 2859-1:1999 normal inspection level II at AQL 1.0 [Claim | Src: ISO 2859-1:1999 — Sampling procedures for inspection by attributes | URL: https://www.iso.org/standard/1141.html | accessed 2026-09-21]. Each filter and each coolant fitting is treated as an inspection unit; non-conforming units shall be reworked or scrapped per the CATL EnerC non-conformance procedure (§9 of the Service Manual).

5. Document Checklist

#FilenamePurposeOwner
1CMMS_Work_Order_Template.pdfPlanned maintenance ticketService Lead
2CATL_EnerC_SM_Rev1.3.pdfOEM service manual Rev. 1.3 (2025-08)Service Lead
3Dowfrost_HD_SDS.pdfPropylene glycol Safety Data SheetService Lead
4LOTO_Permit_Form.pdfLock-out / tag-out authorization (CATL §4.2)Safety Officer
5Filter_Condition_Report.pdfRemoved G4 filter inspection recordHVAC Technician
6Filter_Replacement_Record.pdfNew filter install + 8 N·m torque recordHVAC Technician
7Coolant_Drain_Log.pdf~45 L drain volume & UN container trackingCoolant Technician
8Coolant_Refill_Record.pdf44–46% v/v propylene glycol & refill volumeCoolant Technician
9Leak_Test_Record.pdf30-min standing pressure test @ 2.5 bar (CATL §7.6)Coolant Technician
10Functional_Test_Report.pdfRe-energization test (SOC 25–55%)Commissioning Engineer
11AQL_Inspection_Report.pdfISO 2859-1 AQL 1.0 dispositionQA Lead
12Service_Report_Template.pdfFinal customer-facing reportService Lead
13TH_Customs_Entry_Record.pdfThai customs filing (CN→TH)Logistics Coordinator
14Incoterms_2020_DAP_Delivery_Proof.pdfICC Incoterms 2020 DAP delivery evidenceLogistics Coordinator

6. Timeline and Dependencies

PhaseActivityIndicative durationDepends on
Pre-mobilizationSteps 1–2indicative: 0.5 dayCMMS ticket issued; CATL portal access confirmed
Site arrival & safetyStep 3 (LOTO per CATL §4.2)indicative: 0.5 hourSite access granted; LOTO kit on site
Filter serviceSteps 4–5 (G4 filter, 8 N·m torque)indicative: 1.0 hourReplacement G4 filters on site and inspected
Coolant serviceSteps 6–8 (45 L drain, 45% refill, 2.5 bar test)indicative: 3.0 hoursDowfrost HD concentrate + DI water on site
Re-energize & testStep 9 (SOC 25–55%)indicative: 1.0 hourLOTO removed; grid available
QA & close-outSteps 10–12indicative: 0.5 dayAll records uploaded to CMMS

Note on duration: All durations above are indicative for a single EnerC container under normal ambient conditions (≤ 35 °C site temp, SOC window 25–55%). Actual durations are UNCERTAIN for parallel containers, ambient > 35 °C, or when cool-down cycles extend the LOTO window per CATL EnerC Service Manual §4.2.

7. Cost Slots (Indicative)

Cost slotUnitStatus
Replacement G4 filter set (CATL-spec)per EnerC containerindicative — request quote
Dowfrost HD propylene glycol concentrate (CATL-spec)per litreindicative — request quote
Coolant disposal (UN-approved container, certified vendor)per 45 L drumindicative — request quote
On-site service labour (2-person crew + commissioning engineer)per technician-dayindicative — request quote
Mobilization & demobilization (Bangkok / regional Thai hub)per tripindicative — request quote
Thai customs brokerage fee (CN→TH entry)per shipmentUNCERTAIN — depends on declared value & HS classification
Thai import duty% of CIFUNCERTAIN — see §8

8. Duty / HS Block — Thailand Import

Equipment / parts in scope: CATL EnerC 372.7 kWh LFP BESS container, G4 HVAC filter assemblies and Dowfrost HD propylene glycol coolant service parts shipped under the CN→TH corridor.

Harmonized System (HS) code: PENDING — broker lookup. A reasonable working line for review is HS 8507.60 (lithium-ion electric accumulators) with separators; the Thai Customs Tariff and the WCO HS 2022 explanatory notes must be consulted at the time of each shipment [Claim | Src: WCO Harmonized System 2022 — Section VI, Ch. 85, Note 3 (lithium-ion accumulators) | URL: https://www.wcoomd.org/-/media/wco/public/global/pdf/topics/nomenclature/instruments-and-tools/hs-nomenclature-2022/2022_hs_nomenclature_section_vi_chapters_84_85.pdf | accessed 2026-09-21; Claim | Src: Thai Customs Tariff No. 2507 (HS 2022 version in force) — HS 8507.60 line entry | URL: https://www.customs.go.th/tariffsearch_result.php?tariff_code=8507.60&lang=EN | accessed 2026-09-21].

Import duty rate: PENDING — broker lookup. The applicable WTO MFN rate under the Thai Customs Tariff at HS 8507.60 shall be confirmed against the Thailand Customs Department tariff database at the time of shipment declaration; current indications suggest a rate in the 0–10% range, but this is UNCERTAIN until confirmed [Claim | Src: Thai Customs Department — Tariff and Statistics (current Thai MFN rates) | URL: https://www.customs.go.th/tariffsearch.php?lang=EN | accessed 2026-09-21].

Disclaimer: Tradvolt does not provide legal, tax or customs advice. The HS classification and applicable duty, excise and VAT treatment must be confirmed by a licensed Thai customs broker and the importer of record prior to each shipment. Trade term allocation follows ICC Incoterms 2020 [Claim | Src: ICC Incoterms 2020 (publication 723E) | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21].

9. Compliance References

10. Request a Quote

For filter and coolant service on a CATL EnerC 372.7 kWh LFP BESS in the CN→TH corridor, contact Tradvolt with the EnerC asset serial number, site location in Thailand, last service date and the OEM manual revision on file.

Request Quote — replies in 48h

Claim Row Index

  1. [Claim | Src: CATL — EnerC product page | URL: https://www.catl.com/en/energy-storage-system/enerc/ | accessed 2026-09-21]
  2. [Claim | Src: Dow Chemical — Dowfrost HD SDS landing | URL: https://www.dow.com/en-us/pdp.dowfrost-hd-heat-transfer-fluid.169412z.html | accessed 2026-09-21]
  3. [Claim | Src: ICC Incoterms 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21]
  4. [Claim | Src: IEC Webstore — IEC 62619:2022 | URL: https://webstore.iec.ch/publication/61533 | accessed 2026-09-21]
  5. [Claim | Src: ISO — ISO 2859-1:1999 | URL: https://www.iso.org/standard/1141.html | accessed 2026-09-21]
  6. [Claim | Src: UL Standards — UL 1973 product page | URL: https://www.shopulstandards.com/ProductDetail.aspx?UniqueKey=36405 | accessed 2026-09-21]
  7. [Claim | Src: UN Manual of Tests and Criteria, 7th rev. ed., Part III, §38.3 | URL: https://www.unece.org/fileadmin/DAM/trans/danger/publi/manual/Rev7/Manual%20of%20Tests%20and%20Criteria%20Part%20III%20Section%2038.3.pdf | accessed 2026-09-21]
  8. [Claim | Src: FIATA — FBL model rules & multimodal documents | URL: https://fiata.org/fiata-documents/ | accessed 2026-09-21]
  9. [Claim | Src: WCO Harmonized System 2022 — Section VI (Ch. 84–85) | URL: https://www.wcoomd.org/-/media/wco/public/global/pdf/topics/nomenclature/instruments-and-tools/hs-nomenclature-2022/2022_hs_nomenclature_section_vi_chapters_84_85.pdf | accessed 2026-09-21]
  10. [Claim | Src: Thai Customs — HS 8507.60 tariff line entry | URL: https://www.customs.go.th/tariffsearch_result.php?tariff_code=8507.60&lang=EN | accessed 2026-09-21]
  11. [Claim | Src: Thai Customs — tariff search (current Thai MFN) | URL: https://www.customs.go.th/tariffsearch.php?lang=EN | accessed 2026-09-21]