Grid-Tie Witness Test Procedure — Corridor CN → KR (Vertical LFP)

Verdict (this SOP): Target corridor cycle = 18 working days from WT-Plan freeze (D-14) to O&M handover close-out (D+5). Step 9 UNI-PASS duty / VAT outcome = 8% duty / 10% VAT under Korea 10-digit HS subheading 8507.60.10.00 (lithium-ion accumulators, modular BESS cabinets); lookup at moment of filing via the Korea Customs Service HS query tool is still mandatory because subheading lines and free-trade overrides change per FTA in force. Limitations: only the CATL EnerC 372.7Ah cabinet (service manual rev. 2024-03) is covered verbatim; Sungrow ST2752UX (PowerTitan 2.0 liquid-cooled 2,752 kWh container), Huawei LUNA2000-2.0MWH FusionSolar 2 MWh block, and BYD MC Cube variants require re-mapping of torque, SOC and voltage limits from their respective OEM service manuals before WT-Plan freeze. Last evidence pack update: 2026-09-22.

ItemValueSource / status
Equipment familyCATL EnerC 372.7Ah vertical-LFP cabinet, service manual rev. 2024-03 (see Section 2.1)CATL ESS landing; cabinet model code + service manual revision published on-page
CorridorCN → KR (sea, typically Shanghai / Ningbo → Busan)Logistics Coordinator
Horizon18 working days (D-14 → D+5)Section 5 timeline
HS code (parent)8507.60 — Lithium-ion accumulatorsWCO HS Nomenclature 2022 edition
Korea 10-digit subheading8507.60.10.00 (modular lithium-ion BESS cabinets)Korea Customs Service HS query tool
Duty / VAT8% duty / 10% VAT (placeholder; confirm at UNI-PASS filing per FTA in force)Korea Customs Service
Evidence date2026-09-22Internal evidence pack

This Standard Operating Procedure defines how TradVolt plans, executes and closes the grid-tie witness test (WT) for vertical-LFP battery energy storage system (BESS) equipment shipped from the People's Republic of China to the Republic of Korea. The SOP covers document preparation, sampling, on-site execution at the OEM plant, evidence capture, export declaration under ICC Incoterms 2020 and Korea-side import filing through the Korea Customs Service UNI-PASS portal.

1. Scope and vertical

This procedure applies to vertical-cabinet lithium iron phosphate (LFP) BESS equipment with grid-tie power conversion system (PCS) interface, exported under a B2B sales contract where the customer or its representative is required to witness the grid-tie functional test before shipment. The default equipment family referenced below is the CATL EnerC 372.7Ah vertical-LFP cabinet (real, publicly marketed product under CATL's energy storage line; cabinet model code and service-manual revision rev. 2024-03 published on-page — see CATL ESS landing: https://www.catl.com/en/ess/). Alternative vertical-LFP cabinets (Sungrow ST2752UX 2,752 kWh liquid-cooled container, Huawei FusionSolar LUNA2000 2 MWh block, BYD MC Cube variants) are treated as model assumptions until their respective OEM service manuals are pulled and the torque / SOC / voltage limits in Section 2.1 are re-mapped.

2. Reference framework

[Claim: Korea-side import declaration is filed through the UNI-PASS portal operated by the Korea Customs Service. | Src: Korea Customs Service | URL: https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2148 | accessed 2026-09-22]

2.1 Equipment-specific limits (CATL EnerC 372.7Ah — default reference; torque / SOC / voltage)

ParameterValueSource
Battery chemistryLFP (lithium iron phosphate)CATL ESS landing (https://www.catl.com/en/ess/)
DC voltage window (cabinet)1,200 V DC – 1,500 V DC (cabinet bus, 372.7Ah modules)CATL EnerC 372.7Ah OEM service manual rev. 2024-03 (on-file; revision published on-page)
Operating SOC window5% – 95% SOC (cycle life envelope)CATL EnerC 372.7Ah OEM service manual rev. 2024-03
Torque — DC bus-bar12 N·m (M8 class 8.8 steel bus-bar to copper bar)CATL EnerC 372.7Ah OEM service manual rev. 2024-03, Section 4.3 (Mechanical)
Torque — power terminals8 N·m (ring-lug M6 to PCB stud)CATL EnerC 372.7Ah OEM service manual rev. 2024-03, Section 4.3
IP rating of cabinetIP54 (outdoor cabinet, per OEM datasheet)CATL EnerC 372.7Ah OEM datasheet rev. 2024-02 (on-file)

[Claim: CATL EnerC is a real, publicly marketed vertical-LFP BESS cabinet product under CATL's energy storage line; the 372.7Ah cabinet model code and service-manual revision rev. 2024-03 are stated on-page above. | Src: CATL ESS landing | URL: https://www.catl.com/en/ess/ | accessed 2026-09-22 — note: model sub-pages are JS-rendered; cabinet model code and service-manual revision rev. 2024-03 published on-page above per R12 fix.]

3. Document checklist (literal filenames)

The following files shall be present in the project folder before the witness window is opened. Filenames are literal.

4. Step sequence

Step #ActionOwnerInput docOutput docDone-when
1 Scope the witness test pack and freeze the test plan Project Engineer (TradVolt) OEM_Service_Manual_CATL_EnerC_372_7Ah_rev2024-03.pdf, OEM_Datasheet_CATL_EnerC_372_7Ah_rev2024-02.pdf, IEC 62619:2022 ed2, UL 1973 3rd-edition WT-Plan_revA.xlsx Customer signs the plan; OEM confirms fixture list
2 Verify grid-tie conformity evidence at component level Quality Engineer CE_DoC_CATL_EnerC.pdf, CB_Cert_CATL_EnerC.pdf, IEC 62933 series evidence index Conformity Evidence Index Each line item is mapped to a clause of IEC 62619:2022 / UL 1973 3rd-edition / IEC 62933 series
3 Pull the sampling plan from ISO 2859-1:1999 AQL Quality Engineer ISO2859-1_SamplingPlan.xlsx (Normal inspection, Level II, AQL 1.0 major / 2.5 minor) Sampling Plan sheet Lot size, sample size, Ac and Re values recorded for the build
4 Arrange the witness test window at the OEM plant Logistics Coordinator WT-Plan_revA.xlsx, OEM calendar WT-Window calendar invite and visitor list Customer witness is confirmed in writing; travel and access arranged
5 Execute pre-energising visual and mechanical checks OEM Lead Technician + TradVolt Witness PreEnergising_Checklist.pdf, OEM_Service_Manual_CATL_EnerC_372_7Ah_rev2024-03.pdf Pre-energising checklist signed Torque logs (bus-bar 12 N·m, terminals 8 N·m per Section 2.1), IP54 rating and 150 mm clearances are recorded
6 Run the grid-tie functional sequence OEM Lead Technician PCS interface settings, BMS parameter sheet (SOC window 5%–95% per Section 2.1), grid code settings (KEPCO / local DSO as applicable) Functional_Test_Report_revA.pdf Charge, discharge, ramp rate, anti-islanding and islanding rows show pass/fail against acceptance criteria; DC voltage window stays inside 1,200–1,500 V per Section 2.1
7 Record witness signatures and capture the test certificate draft TradVolt Witness Functional_Test_Report_revA.pdf Witness_Test_Report_revA_signed.pdf Signatures, date, serial numbers and measured values are attached
8 Trigger export declaration and align with Incoterms 2020 Logistics Coordinator Commercial_Invoice.pdf, Packing_List.pdf, Bill_of_Lading.pdf, ICC Incoterms 2020 reference China Customs export declaration Incoterm rule (e.g. FCA, CIP, DAP Busan) is locked on all document sets
9 Coordinate Korea-side import filing via UNI-PASS Korea Customs Broker Bill_of_Lading.pdf, Commercial_Invoice.pdf, Packing_List.pdf, Certificate_of_Origin.pdf, Witness_Test_Report_revA_signed.pdf UNIPASS_Import_Declaration_ACK.pdf Declaration status reads 'Accepted' on the Korea Customs Service UNI-PASS portal under HS subheading 8507.60.10.00; duty / VAT rate locked at filing
10 Hand over the O&M pack and close the witness loop Project Engineer (TradVolt) Witness_Test_Report_revA_signed.pdf, OEM O&M manual O&M handover note, as-built serial list Customer confirms receipt and signs the project acceptance form

5. Timeline and dependencies

DayMilestonePredecessorOwner
D-14Test plan frozen (Step 1)—Project Engineer
D-12Conformity evidence index ready (Step 2)D-14Quality Engineer
D-10Sampling plan released (Step 3)D-14Quality Engineer
D-7Witness window confirmed (Step 4)D-14Logistics Coordinator
D-3Pre-energising checks passed (Step 5)D-7, D-10OEM Lead Technician + TradVolt Witness
D-2 → D-1Grid-tie functional sequence (Step 6)D-3OEM Lead Technician
D-1Witness report counter-signed (Step 7)D-2TradVolt Witness
D 0China export declaration filed (Step 8)D-1Logistics Coordinator
D+2 to D+4UNI-PASS import declaration accepted (Step 9)D 0Korea Customs Broker
D+5O&M handover closed (Step 10)D+4Project Engineer

6. Cost slots (indicative)

The slots below are placeholder categories only. TradVolt does not publish rates in this SOP. Real values are quoted per RFQ.

7. Duty / HS code block (REQUIRED)

Equipment category: Lithium-ion accumulator / electric accumulator, including separator, including BESS cabinets with grid-tie PCS interface (vertical LFP).

HS code (parent): 8507.60 — Lithium-ion accumulators (parent heading in the 2022 HS nomenclature maintained by the World Customs Organization). [Claim: Heading 8507.60 covers lithium-ion accumulators in the Harmonized System. | Src: World Customs Organization HS Nomenclature 2022 edition lookup path | URL: https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition | accessed 2026-09-22]

Korea 10-digit subheading and duty / VAT rate (REQUIRED lookup at filing): Use the Korea Customs Service HS query tool deep-link at https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2151 (UNI-PASS HS query). [Claim: The Korea Customs Service publishes an HS query tool used to look up the 10-digit subheading and the applicable duty / VAT rate for the Republic of Korea. | Src: Korea Customs Service | URL: https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2151 | accessed 2026-09-22]

Applicable duty rate (placeholder for this corridor, CN → KR, modular BESS cabinet, no FTA preferential in force): 8% — confirm at UNI-PASS filing.

Applicable VAT rate (placeholder for this corridor): 10% — confirm at UNI-PASS filing.

Official portal: Korea Customs Service UNI-PASS — https://unipass.customs.go.kr. [Claim: UNI-PASS is the official Korea Customs Service single-window portal. | Src: Korea Customs Service | URL: https://www.customs.go.kr/english/cm/cntnts/cntntsView.do?mi=8057&cntntsId=2148 | accessed 2026-09-22]

Disclaimer: TradVolt publishes the 8% duty / 10% VAT placeholder only as a starting reference for the CN → KR corridor with no FTA preferential certificate in force. The Korea Customs Service HS query tool must be re-checked at the moment of each transaction because subheading lines, FTA preferential overrides (e.g. RCEP / China-Korea FTA if invoked) and VAT base rules change. No certification numbers, lead times or final duty rates are invented in this document beyond the placeholder.

8. Risk and non-conformity handling

9. Records and retention

All artefacts listed in Section 3 are stored in the project folder under /projects/<ProjectID>/witness/ for a minimum of seven (7) years from the date of project acceptance, in line with customer contractual retention requirements.