Verdict: Use this SOP for any EVSE shipment (AC/DC chargers and any lithium-ion auxiliary battery modules) moving from a Chinese OEM facility to a Vietnamese consignee when the buyer (or seller's appointed agent) is responsible for pre-shipment inspection. Expected cycle time: 5–8 working days from PO date T0. Mandatory sampling: ISO 2859-1 General Inspection Level II, with AQL 1.0 for major defects and AQL 2.5 for minor defects; zero critical defects allowed. Equipment scope: Sungrow AC011E-01 (AC, 11 kW), Sungrow IDC30E (DC fast, 30 kW), Huawei FusionCharge AC 7 kW and Huawei FusionCharge DC 60 kW families, plus EVE Energy LF105 cells used in charger buffer packs. Horizon: as of 2026-09-21. Limitation: this page is process guidance only — it does not replace OEM warranty terms, customs broker rulings, or the underlying sales contract.
| Decision point | Outcome | Source |
|---|---|---|
| Apply SOP? | YES — CN→VN EVSE lane, ≥80% production complete | This document §1, §3 |
| AQL plan | ISO 2859-1, Level II, AQL 1.0 major / 2.5 minor, 0 critical | ISO 2859-1:1999 Table II-A — https://www.iso.org/standard/1141.html |
| UN38.3 re-check | Required for any Li-ion cell; T1–T8 summary ≤ 12 months | UN Manual of Tests and Criteria, Rev.7 (2023), §38.3 — https://unece.org/transport/documents/2023/file/114050 |
| Insulation limit | ≥ 1 MΩ between live parts and exposed conductive parts | IEC 61851-1:2017, cl. 11.4.1 — https://webstore.iec.ch/publication/7328 |
| Carton drop test | 0.5 m, 1 corner / 3 edges / 6 faces | ISO 4180:2019, Annex A — https://www.iso.org/standard/72151.html (referenced by OEM packing spec) |
Document type: Process / Standard Operating Procedure | Vertical: EVSE (Electric Vehicle Supply Equipment) | Trade lane: China → Vietnam
This SOP defines the mandatory pre-shipment inspection (PSI) sequence for Sungrow AC011E-01, Sungrow IDC30E, Huawei FusionCharge AC 7 kW and Huawei FusionCharge DC 60 kW units, plus spare parts and EVE Energy LF105 lithium-ion auxiliary battery modules, shipped from Chinese OEM facilities to Vietnamese import consignees. It consolidates statistical sampling per ISO 2859-1, the UN Manual of Tests and Criteria §38.3 transport re-check, and INCOTERMS® 2020 allocation of inspection responsibilities.
| Reference | Issuing body | Applicability | Document URL |
|---|---|---|---|
| IEC 61851-1:2017 | IEC | EV conductive charging system — general requirements | https://webstore.iec.ch/publication/7328 |
| IEC 62196-2 | IEC | Plugs, socket-outlets, vehicle connectors (Type 1/2) | https://webstore.iec.ch/publication/6316 |
| ISO 2859-1:1999 | ISO | Sampling procedures by attributes — AQL | https://www.iso.org/standard/1141.html |
| UN Manual of Tests and Criteria, Rev.7 (2023), §38.3 | UN | Lithium battery transport classification | https://unece.org/transport/documents/2023/file/114050 |
| ICC INCOTERMS® 2020 | ICC | Trade term allocation (FCA/FOB/CIF/DAP) | https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ |
| FIATA Multimodal Transport Documents | FIATA | Through bills of lading for combined transport | https://fiata.org/transport-documents/ |
| Sungrow AC011E-01 / IDC30E — Installation & Commissioning Manual | Sungrow | OEM limits, torque, insulation | https://en.sungrowpower.com/ev-charging |
| Huawei FusionCharge AC/DC — User Manual | Huawei | OEM limits, SOC behaviour, commissioning | https://e.huawei.com/en/products/ev-charging |
| EVE LF105 — Product Specification | EVE Energy | Cell datasheet — voltage, SOC, UN38.3 reference | https://www.eveenergy.com/en/product/lfp-105.html |
| Step # | Action | Owner | Input doc | Output doc | Done-when |
|---|---|---|---|---|---|
| 1 | Confirm PO, INCOTERMS® 2020 term, and inspection allocation (FCA/FOB → buyer; CIP/CIF/DAP → seller coordinates). | Tradvolt Order Manager | Purchase Order; Sales Contract | Inspection Allocation Note (IAN) | IAN signed by both parties; INCOTERMS code recorded. |
| 2 | Retrieve OEM datasheets and manuals: Sungrow AC011E-01 / IDC30E Installation & Commissioning Manual (rev. ≥2024) and Huawei FusionCharge AC/DC User Manual (rev. ≥2024); confirm CE/IEC/UL type-test reports ≤ 24 months old. | Tradvolt QA Lead | Supplier Document Pack (SDP) | Document Completeness Log | All CE/UL/IEC reports present, revision dates ≤ 24 months. |
| 3 | Verify UN38.3 test summary validity for any EVE LF105 cells shipped (T1–T8 completed per UN §38.3; summary dated ≤ 12 months; chemistry = LFP; nominal 3.2 V, 105 Ah). | Tradvolt QA Lead | UN38.3 Test Summary; MSDS | UN38.3 Re-check Record | Test summary matches cell chemistry (LFP) and watt-hour rating (105 Ah × 3.2 V = 336 Wh/cell). |
| 4 | Generate AQL sampling plan per ISO 2859-1: General Inspection Level II, AQL 1.0 (major), AQL 2.5 (minor), critical = 0. | Third-party Inspector | Lot size; ISO 2859-1:1999 Table II-A | AQL Sampling Plan Sheet | Sample size and accept/reject numbers recorded; plan attached to lot. |
| 5 | Execute AQL visual + functional checks: cosmetic defects, label legibility, plug insertion force per IEC 62196-2, insulation resistance ≥ 1 MΩ between live parts and exposed metal per IEC 61851-1:2017 cl. 11.4.1, ground continuity, Sungrow AC011E-01 torque on AC terminal block per OEM manual (typ. 1.2–1.5 N·m, confirm against current rev.), Huawei FusionCharge DC 60 kW auxiliary voltage check (24 V control circuit). | Third-party Inspector | AQL Sampling Plan Sheet; OEM Checklist | Inspection Worksheet | Defects within AQL limits; critical defects = 0. |
| 6 | Packaging verification: carton drop test 0.5 m, 1 corner / 3 edges / 6 faces per ISO 4180:2019 Annex A; IP rating intact (Sungrow AC011E-01 = IP65, IDC30E = IP54 per datasheets; Huawei FusionCharge AC = IP54, DC = IP54 per datasheet), desiccant present, handling marks per ISO 780. | Third-party Inspector | Packaging Specification | Packaging Inspection Record | No carton rupture; marks legible per ISO 780 pictograms. |
| 7 | Confirm marking: CE mark, rating label, country of origin, HS code, UN3481 (lithium) where applicable, Vietnamese-language warning label. | Third-party Inspector | Label Artwork; OEM datasheet | Marking Compliance Form | All mandatory marks photographed and verified. |
| 8 | Photograph lot (≥ 10 photos: pallet overview, random cartons, opened sample, label close-up, serial numbers). | Third-party Inspector | Digital camera; Lot ID | PSI Photo Set | Photos uploaded to Tradvolt inspection portal within 4 h. |
| 9 | Issue Pre-Shipment Inspection Report (PSIR): pass / conditional pass / fail. | Tradvolt QA Lead | Inspection Worksheet; Photo Set | PSIR (PDF) | PSIR uploaded, shared with buyer within 24 h of inspection. |
| 10 | Coordinate customs docs: commercial invoice, packing list, certificate of origin (FORM E for VN under ACFTA), UN38.3 summary, MSDS, FIATA FBL if multimodal. | Tradvolt Logistics Coordinator | PSIR; PO; Shipping Mark file | Customs Dossier | All docs stamped by customs broker; shipment released for export. |
| Phase | Duration | Earliest start | Dependencies |
|---|---|---|---|
| Doc retrieval (Steps 1–3) | 1–2 working days | PO confirmed | Supplier SDP received |
| Lot ready signal | 0 days | Production ≥ 80 % | Supplier notification |
| Inspector mobilization (Step 4–8) | 1–3 working days | Lot ready + Docs OK | Travel/visa arrangements |
| Inspection & PSIR (Steps 5–9) | 1 working day on-site | Inspector on-site | AQL plan issued |
| Customs dossier (Step 10) | 1–2 working days | PSIR issued | Form E issued by competent authority in CN |
| Total elapsed | 5–8 working days (indicative) | PO date T0 | All upstream clear |
Timings are indicative and depend on factory production schedule, public holidays in CN/VN, and inspector availability. Tradvolt does not warrant lead-times as contractual obligations.
PSIR_[PO#]_[Lot#]_v1.pdf — Pre-Shipment Inspection ReportAQL_Plan_[PO#]_[LotSize].xlsx — ISO 2859-1 sampling worksheet (Level II, AQL 1.0/2.5)UN38.3_Summary_EVE_LF105.pdf — Lithium cell test summary (T1–T8, ≤ 12 months old)MSDS_EVE_LF105_[IssueDate].pdf — Material Safety Data SheetFORM_E_[Invoice#].pdf — ACFTA Certificate of Origin (issued by China Customs / COC authority)CI_PL_[PO#].pdf — Commercial Invoice + Packing ListOEM_Datasheet_Sungrow_AC011E-01_or_IDC30E_or_Huawei_FusionCharge.pdf — EVSE type-test datasheetPSI_Photos_[PO#]_[Date].zip — Compressed photo evidenceMarking_Compliance_[PO#].pdf — Label & marking compliance form| Item | Likely HS heading | Duty rate (VN import) | Source portal |
|---|---|---|---|
| AC EVSE (Sungrow AC011E-01, Huawei FusionCharge AC 7 kW) | 8537.10 (control panels) or 8504.40 (static converters) — final classification depends on VN customs ruling | PENDING — lookup at Vietnam Customs Electronic Tariff | Vietnam General Department of Customs — https://www.customs.gov.vn/index.jsp?pageId=8 |
| DC fast charger (Sungrow IDC30E, Huawei FusionCharge DC 60 kW) | 8504.40 (static converters) — confirm at classification time | PENDING — lookup | Vietnam General Department of Customs — https://www.customs.gov.vn/index.jsp?pageId=8 |
| Lithium-ion cells (EVE LF105 standalone) | 8507.60 | PENDING — lookup | Vietnam General Department of Customs — https://www.customs.gov.vn/index.jsp?pageId=8 |
HS classifications above are indicative only. Final HS assignment, applicable MFN or ACFTA preferential rates, VAT, and any anti-dumping or safeguard duties must be verified by a qualified customs broker at the time of shipment against the official Vietnam Customs Electronic Tariff. Tradvolt does not provide legal or fiscal advice.
| Cost line | Basis | Unit | Amount |
|---|---|---|---|
| Third-party inspector fee (CN on-site) | Day rate, 1 inspector | USD / day | indicative — 350–500 |
| UN38.3 summary review (per EVE LF105 shipment) | Per shipment | USD | indicative — 80–120 |
| Form E issuance (CN authority) | Per invoice | CNY | UNCERTAIN — depends on local chamber |
| AQL rework / re-inspection (if fail) | Per re-visit | USD | indicative — 250–400 |
| Vietnam import duty | Per HS code | % CIF | PENDING — lookup at Vietnam Customs |
| Vietnam VAT | standard rate | % (D + CIF) | UNCERTAIN — confirm at clearance |
All cost figures are indicative and not quotations. Tradvolt will issue binding pricing only against a written Request for Quote.
Request Quote — replies in 48h