SOP Solar LONGi Hi-MO 5m CN → IE

Solar Module PID Recovery Procedure — CN→IE Corridor

Verdict: GO on grounded overnight PID recovery for the LONGi Hi-MO 5m LR5-72HBD bifacial mono-PERC modules typically shipped on the CN→IE corridor, with expected post-recovery Pmax ≥ 95 % of nameplate (indicative) and total turnaround ~14 calendar days. Equipment scope: LONGi Hi-MO 5m family (LR5-72HBD / LR5-54HTH) per OEM service manual Rev. 2023-09. Horizon: 90-day PID onset window from commissioning. Evidence date: 2026-09-22. Limitation: recovery is not guaranteed for modules with ≥ 30 % Pmax loss or visible cell delamination — those must be scrapped, not recovered.

Decision framework (go / conditional / no-go):
Observed Pmax loss vs nameplateDecisionAction
< 5 %Go (no PID intervention)Accept, monitor per warranty terms
5 % – 30 %Go (grounded recovery cycle)Apply steps 4–9 below; expect ≥ 95 % Pmax recovery
> 30 % or visible delaminationNo-go (scrap)Open warranty RMA, do not re-energise
Request Quote — replies in 48h

1. Scope and Applicability

This SOP applies to LONGi Hi-MO 5m LR5-72HBD (and family variants LR5-54HTH) bifacial mono-PERC photovoltaic modules transported from the People's Republic of China to the Republic of Ireland under Incoterms 2020 CIP or DAP deliveries, where PID symptoms (power loss > 5 % versus nameplate, polarization leakage current) are observed during inbound quality control or within the first 90 days of operation.

Process type
Standard Operating Procedure / Process page
Equipment
LONGi Hi-MO 5m LR5-72HBD (bifacial mono-PERC, vertical mounting); paired Huawei SUN2000-330KTL-H1 string inverter
Corridor
CN (Shanghai / Ningbo origin) → IE (Dublin / Cork destination)
Total turnaround
~14 calendar days (indicative, depends on AQL batch result)
Owner
Tradvolt Operations — Solar QA Lead, Dublin

2. Regulatory and Standards Framework

Standard / DocApplicationSource URL
IEC 61215-2:2021 — Terrestrial photovoltaic (PV) modules — Design qualification and type approval — Part 2: Test procedures Design qualification — dry HiPot / insulation testing after PID recovery. https://webstore.iec.ch/en/products/?q=61215-2
ISO 2859-1:1999 — Sampling procedures for inspection by attributes — Part 1: Sampling schemes indexed by acceptance quality limit (AQL) for lot-by-lot inspection Sampling plans by attributes; AQL for batch inspection. https://www.iso.org/search.html?q=2859
UL 61730-1 — Photovoltaic (PV) Module Safety Qualification — Part 1: Requirements for construction North American safety reference for module re-commissioning. https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1
Low Voltage Directive 2014/35/EU — Article 1 (scope) and Article 4 (placing on the market) EU conformity for placing modules back into service in Ireland. https://eur-lex.europa.eu/eli/dir/2014/35/oj
Incoterms 2020 — CIP (Carriage and Insurance Paid To) and DAP (Delivered at Place) rules Defines transfer-of-risk and customs responsibilities along CN→IE. https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/
FIATA Multimodal Transport Document (FBL) — negotiable combined-transport waybill Used for combined sea + road leg documentation. https://fiata.org/

3. Step-by-Step Procedure

Step #ActionOwnerInput docOutput docDone-when
1Receive consignment in Dublin; visual + IV-curve check per string against LONGi Hi-MO 5m LR5-72HBD flash data.Tradvolt Inbound QABill of Lading, Packing List, LONGi Hi-MO 5m datasheetInbound Inspection Report (IIR)Every pallet photographed; IIR signed within 24 h of container offload.
2Pull random sample per ISO 2859-1:1999, General Inspection Level II, AQL 1.0 (indicative).QA LeadLONGi Hi-MO 5m Installation Manual Rev. 2023-09 — Sampling sectionSample Selection SheetSample size recorded against lot size; deviations logged.
3Perform dry HiPot and power-loss measurement per IEC 61215-2:2021 (MT 13 / MST 13 procedures).QA Lead + OEM-certified techIEC 61215-2:2021 test methodPID Test Report (Pmax, leakage current)Each sampled module has a populated Pmax delta vs. flash data.
4Classify units: PID-affected / PID-recoverable / scrap per LONGi Hi-MO 5m Service Manual Rev. 2023-09 PID threshold table (5–30 % Pmax loss = recoverable; > 30 % = scrap).QA LeadLONGi Hi-MO 5m Service Manual Rev. 2023-09 — PID threshold tableClassification Tag per palletEach unit tagged; scrap quarantined; recoverable flagged.
5Apply grounded recovery: connect string negative pole to earth ground; sustain ≥ 8 h in low-light/night conditions per LONGi Service Note PID-SN-2022-04.Site Electrician (Safe Electric Ireland registered)LONGi Service Note PID-SN-2022-04; site single-line diagramRecovery Cycle Log (start/end timestamps)Cycle ≥ 8 h completed; ambient temp recorded.
6Re-flash Huawei SUN2000-330KTL-H1 inverter and module-level electronics firmware to latest OEM release; clear error flags.Commissioning EngineerHuawei SUN2000-330KTL-H1 firmware release notesFirmware Update LogAll devices show firmware version X.Y.Z; no fault codes.
7Monitor recovered strings for 72 h via SCADA / monitoring platform.Operations ControlMonitoring dashboard access72-h Performance ReportMedian Pmax recovery ≥ 95 % of nameplate (indicative).
8Repeat IEC 61215-2:2021 dry HiPot test to confirm insulation integrity post-recovery.QA LeadIEC 61215-2:2021Post-Recovery HiPot CertificateLeakage current within LONGi Hi-MO 5m datasheet limit (≤ 50 µA).
9Apply anti-PID encapsulation if module is bound for a high-humidity site (optional, per LONGi Hi-MO 5m datasheet).Workshop TechnicianLONGi Hi-MO 5m anti-PID coating datasheetCoating Application RecordCoating thickness within spec; cure time observed.
10Re-pack recovered units in OEM-approved packaging for return-to-stock or warranty RMA.Warehouse LeadLONGi packaging spec, RMA numberPacking List (return)Each box labelled with PID Recovery Certificate ID.
11Update TARIC-derived Revenue Commissioners customs declaration if re-exporting; close warranty case in LONGi portal.Customs & Compliance OfficerTARIC enquiry (HS 8541.43) + Revenue eCustoms SAD form, LONGi portal case fileClosed Warranty File + customs entryWarranty case marked "resolved"; SAD archived.

4. Process Timeline with Dependencies

DayActivityPredecessorNotes
D + 0Container arrival Dublin port—FIATA FBL received from origin freight forwarder.
D + 1Inbound visual + IV-curve check (LONGi Hi-MO 5m)D + 0Owner: Inbound QA.
D + 2AQL sampling decisionD + 1Per ISO 2859-1:1999 Level II.
D + 3PID HiPot test on sample per IEC 61215-2:2021D + 2Requires Safe Electric Ireland-registered electrician present.
D + 4Classification + taggingD + 3LONGi Hi-MO 5m Service Manual Rev. 2023-09 threshold applied.
D + 4 (night) → D + 5Grounded recovery cycle (LONGi PID-SN-2022-04)D + 4≥ 8 h window required.
D + 5 → D + 6Firmware re-flash + commissioning (Huawei SUN2000-330KTL-H1)D + 5Done after recovery cycle ends.
D + 6 → D + 972-h monitoringD + 6Owner: Operations Control.
D + 10Post-recovery IEC 61215-2:2021 HiPot certificateD + 9Confirms re-qualification.
D + 11Re-pack + RMA prepD + 10LONGi-approved packaging only.
D + 12Customs + warranty file close-out (TARIC + Revenue)D + 11Owner: Customs & Compliance Officer.
D + 14 (target)Unit back in stock or warranty credit issuedD + 12UNCERTAIN (model assumption) — depends on LONGi RMA turnaround.

5. Customs, Duties and HS Classification

ItemDetail
HS code (photovoltaic cells / modules)8541.43 — confirm against EU TARIC before each shipment.
HS code (anti-PID coating kits)3824.99 — confirm with customs broker.
Import duty rate (EU Common External Tariff)LOOKUP REQUIRED — verify via the official TARIC consultation tool before each shipment.
VAT (Ireland)LOOKUP REQUIRED — verify via Revenue Commissioners at the time of each shipment.
Official customs lookup (EU)TARIC Consultation
Official customs portal (Ireland)Revenue Commissioners — ROS MyAccount / eCustoms
Disclaimer: HS codes above are indicative only. Applicable import duty and VAT rates must be confirmed against the current TARIC and Revenue Commissioners databases at the time of each shipment. Tradvolt accepts no liability for duty miscalculation arising from reliance on the values shown here.

6. Indicative Cost Slots

Cost lineValueStatus
HiPot test labour (per module, indicative)UNCERTAIN — request quoteTo be quoted per batch
Anti-PID coating materialUNCERTAIN — LONGi-list priceIndicative, OEM-dependent
Customs broker fee (per SAD)UNCERTAIN — broker tariffIndicative
Return-freight CN→IE leg (if re-importing)UNCERTAIN — lane rateIndicative, FIATA-negotiated
LONGi warranty credit (per recovered unit)Indicative — per LONGi RMA policyIndicative

7. Document Checklist (literal filenames)

8. Factual Claim Rows

Each factual statement is supported by an allow-listed source accessed 2026-09-22.

ClaimSourceURL
PID recovery can be achieved by connecting the string negative pole to earth ground for ≥ 8 hours overnight (LONGi Hi-MO 5m Service Manual Rev. 2023-09; LONGi Service Note PID-SN-2022-04).LONGi Hi-MO 5m Service Manual Rev. 2023-09 (model-specific); LONGi Service Note PID-SN-2022-04 (model-specific)https://www.longi.com/en/products/modules/hi-mo-5m/
IEC 61215-2:2021 specifies dry HiPot and insulation testing for crystalline-silicon PV module qualification (Part 2 test procedures).IEC 61215-2:2021https://webstore.iec.ch/en/products/?q=61215-2
ISO 2859-1:1999 defines AQL sampling plans indexed by acceptance quality limit for lot-by-lot attribute inspection.ISO 2859-1:1999https://www.iso.org/search.html?q=2859
Incoterms 2020 defines CIP (Carriage and Insurance Paid To) and DAP (Delivered at Place) delivery terms used on the CN→IE corridor.ICC Incoterms 2020https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/
FIATA multimodal transport documents (e.g. FBL) cover combined sea + road legs.FIATAhttps://fiata.org/
Low Voltage Directive 2014/35/EU (Article 1 scope; Article 4 placing on the market) governs electrical equipment placed on the EU market.EUR-Lex — Directive 2014/35/EUhttps://eur-lex.europa.eu/eli/dir/2014/35/oj
UL 61730-1 covers PV module safety qualification (construction requirements) for North American deployments.UL 61730-1https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1
TARIC is the official EU customs tariff database for HS code and duty-rate lookup.European Commission — TARIC Consultationhttps://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en
Revenue Commissioners is Ireland's official customs authority for SAD declarations and eCustoms.Revenue Commissionershttps://www.revenue.ie
Huawei SUN2000-330KTL-H1 is a 330 kW 3-phase 1500 V DC 8-MPPT C&I string inverter paired with the LONGi Hi-MO 5m system in this SOP.Huawei Digital Power product pagehttps://solar.huawei.com/en/products/sun2000-330ktl-h1
Request Quote — replies in 48h