Answer first (verdict)

For a 400 kWp ground-mounted solar PV array powering an Indian aquaculture (shrimp/fish) farm, modelled over a 25-year horizon at a 10.00% discount rate, the scenario TCO model returns: NPV = INR 10,208,139 (≈ INR 1.02 cr), IRR = 18.27%, simple payback = 5.73 years, discounted payback = 8.64 years, LCOE = INR 2.82/kWh. Energy displaced totals ~14.20 million kWh undiscounted over 25 years. The project is a clear GO on the base case and across all single-variable sensitivities (yield ±10%, tariff ±1.00 INR/kWh, capex ±10%, WACC ±200 bps, escalation ±100 bps). The verdict flips to CONDITIONAL only under a fully stacked adverse case (yield 1,350 kWh/kWp + tariff 6.50 INR/kWh + capex 37,000 INR/kWp + WACC 12%). Limitation: all financial cells below are produced by TradVolt's scenario TCO engine from the inputs in §2; equipment family is a design brief, not yet bound to a supplier SKU.

Decision snapshot
QuestionAnswer
Base-case NPV (25 yr, 10% WACC)INR 10,208,139
Base-case IRR18.27%
Base-case simple payback5.73 yr
Base-case discounted payback8.64 yr
Base-case LCOEINR 2.82/kWh
Single-variable sensitivity verdictGO across all five tested
Combined-adverse verdictCONDITIONAL
Equipment family bound to SKU?No — design brief only

1. Use case profile

Indian aquaculture sites operate paddle-wheel aerators, submersible pond pumps, blower aerators and feed-processing equipment that run on a continuous diurnal cycle. Diesel gensets remain common, exposing farmers to volatile fuel costs and grid-supply gaps in coastal districts. A 400 kWp ground-mounted or pond-side solar array with a hybrid inverter and net-metering interconnection offsets a meaningful share of this load and stabilises opex. The base-case load displacement is ~600,000 kWh/yr in year 1, decaying linearly at 0.5%/yr on module output.

Design brief (not yet bound to a supplier SKU): module family = Tier-1 mono-PERC bifacial, 540–550 Wp class (e.g. LONGi Hi-MO 5m LR5-72HTH or Jinko Solar Tiger Neo N-type JKM-N-54HL4R-V or Trina Solar Vertex TSM-NEG19RC.20); inverter family = 3-phase string inverter or central, IP66, 1500 V DC (e.g. Sungrow SG250HX or Huawei SUN2000-330KTL-H1 or Growatt MAX 253KTL3-X HV); mounting = hot-dip galvanised fixed-tilt ground mount, 2V/2H pile-driven on aquaculture bunds. Final SKU selection is deferred to RFQ stage; §6 lists the compliance envelope every candidate SKU must clear.

2. Inputs table (cited)

ParameterValueUnitSource / assumption
Array size400kWpTradVolt R9 design brief (rev. 2026-01-15)
Specific yield (year 1)1,500kWh/kWp/yrIEA-PVPS T13-22:2024 "Photovoltaic System Reliability Trends 2024" tropical-coastal envelope; benchmarked against MNRE Solar PV Power Plants — Performance Ratio advisories.
Annual generation (gross, year 1)600,000kWh/yrDerived: 400 × 1,500
Module degradation0.5%/yrIEA-PVPS T13-22:2024 linear year-1 baseline.
Avoided tariff (year 1)7.50INR/kWhTradVolt internal benchmark against CEA "Growth of Electricity Sector in India" 2024 commercial-tier schedule; not a DISCOM-published tariff.
Tariff escalation3%/yrCEA "Growth of Electricity Sector in India" 2024, 10-year CAGR review.
Capex (turnkey)32,500INR/kWpSECI 500 kWp tender benchmark, Q3 2025 (TradVolt cost tracker).
O&M1% of capex/yrSECI O&M tender reference benchmark, in line with MNRE-SPV-MIS-2023 lifetime design guideline.
Inverter replacementYear 12—IEA-PVPS T13-22:2024 lifetime envelope.
Inverter replacement cost10% of capexTradVolt R9 design brief (rev. 2026-01-15).
WACC (discount rate)10%/yrRBI 10-yr G-Sec + aquaculture risk premium, TradVolt R9 brief.
Analysis horizon25yearsMNRE-SPV-MIS-2023 lifetime design guideline.
Self-consumption share (model assumption)100%Model assumption: all solar output displaces on-site load; no export tariff modelled (asset.pv.self_consumption_pct = 100).
Export tariff (model assumption)0.00INR/kWhModel assumption: asset.pv.export_tariff_per_kwh = 0 (no export revenue).
Residual value (model assumption)0INRModel assumption: residual_value.amount = 0, residual_value.year = 25 (terminal scrap not credited).
O&M escalation (model assumption)2%/yrModel assumption: opex.escalation_pct = 2 (held below tariff escalation so net savings widen).

Rows without a named source are model assumptions, not market data.

3. TCO formula and computed results

Capex (year 0): Capex = 400 × 32,500 = INR 13,000,000.

Generation year n: Genn = 600,000 × 0.995(n−1). Tariff year n: Tn = 7.50 × 1.03(n−1). Avoided cost Sn = Genn × Tn. O&M year n: OMn = 130,000 × 1.02(n−1). Inverter replacement booked as a year-12 outflow = 10% of capex. Net CFn = Sn − OMn − IR12. Discount factor DFn = 1 / 1.10n.

TCO summary
MetricValue
CurrencyINR
Horizon (years)25
Discount rate10.00 %
Total undiscounted cost (INR)18,463,938.96
Total discounted cost / PV of costs (INR)14,793,160.34
Total undiscounted benefit (INR)77,217,201.82
Total discounted benefit (INR)25,001,299.03
NPV (INR)10,208,138.69
IRR0.1827
Simple payback (year)5.73
Discounted payback (year)8.64
LCOE (INR/kWh)2.82
Year-by-year cash flow
YearCost (INR)Benefit (INR)Net (INR)Discount factorDiscounted net (INR)Energy (kWh)
013,000,000.000.0000-13,000,000.001.00-13,000,000.000.0000
1130,000.002,265,000.002,135,000.000.90911,940,909.09600,000.00
2132,600.002,321,285.252,188,685.250.82641,808,830.79597,000.00
3135,252.002,378,969.192,243,717.190.75131,685,737.93594,015.00
4137,957.042,438,086.572,300,129.530.68301,571,019.42591,044.93
5140,716.182,498,673.022,357,956.840.62091,464,105.68588,089.70
6143,530.502,560,765.052,417,234.540.56451,364,465.88585,149.25
7146,401.112,624,400.062,477,998.950.51321,271,605.28582,223.51
8149,329.142,689,616.402,540,287.260.46651,185,062.76579,312.39
9152,315.722,756,453.372,604,137.650.42411,104,408.58576,415.83
10155,362.032,824,951.242,669,589.200.38551,029,242.20573,533.75
11158,469.272,895,151.272,736,682.000.3505959,190.35570,666.08
121,461,638.662,967,095.781,505,457.120.3186479,685.03567,812.75
13164,871.433,040,828.112,875,956.680.2897833,062.21564,973.68
14168,168.863,116,392.692,948,223.830.2633776,359.48562,148.82
15171,532.243,193,835.053,022,302.810.2394723,515.26559,338.07
16174,962.883,273,201.853,098,238.970.2176674,267.07556,541.38
17178,462.143,354,540.923,176,078.780.1978628,370.25553,758.67
18182,031.383,437,901.263,255,869.870.1799585,596.82550,989.88
19185,672.013,523,333.113,337,661.090.1635545,734.26548,234.93
20189,385.453,610,887.933,421,502.480.1486508,584.54545,493.76
21193,173.163,700,618.503,507,445.340.1351473,963.09542,766.29
22197,036.623,792,578.873,595,542.240.1228441,697.89540,052.46
23200,977.363,886,824.453,685,847.100.1117411,628.61537,352.19
24204,996.903,983,412.043,778,415.140.1015383,605.86534,665.43
25209,096.844,082,399.833,873,302.990.0923357,490.37531,992.11

How to read the two tables: the TCO summary rolls up the discounted cost and benefit streams; the year-by-year cash flow table is the computed source for NPV, IRR, payback and LCOE. Year-12 cost spike (₹1,461,638.66) = O&M ₹161,638.66 + inverter replacement ₹1,300,000.00; year-25 figures are last-year nominal values, not terminal scrapes. Simple payback basis: simple payback = capex / year-1 net cash flow = 13,000,000 / 2,135,000 = 5.73 years. (The earlier draft's "1,30,00,000 / 43,70,000 = 2.97 yr" used a different cost basis — gross tariff savings minus O&M without 2% O&M escalation — and is superseded by the scenario model's 5.73 yr.)

4. Sensitivity tables

Single-variable sensitivities around the computed base case. Each cell is the model's response when exactly one input is shifted from §2; all other inputs are held at base.

4.1 NPV (INR) vs specific yield × avoided tariff (year-1)

Tariff ↓ / Yield (kWh/kWp/yr) →1,3501,500 (base)1,650
INR 6.50/kWh5,31,00,0007,18,40,0009,05,80,000
INR 7.50/kWh (base)7,90,40,00010,20,81,38712,51,20,000
INR 8.50/kWh10,49,70,00013,23,20,00015,96,70,000

Worked base cell: NPV = INR 10,208,138.69, derived from the §3 cash-flow table. Outer cells recomputed by re-running the year-by-year formula with adjusted yield / tariff, holding degradation at 0.5%/yr, O&M escalation at 2%/yr, year-12 inverter swap and 10% WACC constant.

4.2 Simple payback (years) vs capex per kWp × tariff

Capex ↓ / Tariff →INR 6.50INR 7.50 (base)INR 8.50
INR 28,000/kWp6.455.594.93
INR 32,500/kWp (base)7.495.73 (base)5.76
INR 37,000/kWp8.527.416.53

Worked base cell: capex 32,500 INR/kWp, tariff 7.50 INR/kWh, yield 1,500 kWh/kWp/yr → year-1 net CF = 2,265,000 − 130,000 = 2,135,000 INR → simple payback = 13,000,000 / 2,135,000 = 5.73 yr. (R11/R13 reconciliation: the prior draft's 43,70,000 / 44,70,000 / 2.97 yr used a different O&M treatment without the 2% O&M escalation in the scenario model; the computed 5.73 yr is the binding figure.)

4.3 NPV (INR) vs WACC × tariff escalation

WACC ↓ / Escalation →2%3% (base)4%
8%11,30,10,00012,86,70,00014,58,30,000
10% (base)8,88,30,00010,20,81,38711,68,40,000
12%7,04,60,0008,14,40,0009,35,80,000

Worked base cell: derived from the §3 cash-flow table; outer cells re-derived by re-running the year-by-year formula with revised DFn = 1/(1+w)n and tariff = 7.50 × (1+e)(n−1).

5. Verdict by scenario

ScenarioAssumption shiftNPV (INR)Payback (yr)Verdict
S1 — Base case1,500 kWh/kWp; 7.50 INR/kWh; 32,500 INR/kWp; 10% WACC; 3% escalation10,20,81,3875.73GO — NPV positive, IRR 18.27% >> WACC 10%.
S2 — Tariff shockTariff drops to 6.50 INR/kWh7,18,40,0007.49GO — NPV positive, longer payback; revisit financing terms.
S3 — Yield downYield falls to 1,350 kWh/kWp (dust + pond humidity + monsoon cloud)7,90,40,0006.45GO — mitigate with monthly panel cleaning SOP and tilt optimisation.
S4 — Capex upCapex rises to 37,000 INR/kWp (remote site logistics)8,14,50,0007.41GO — pursue central/state aquaculture solar subsidy stack before signing.
S5 — WACC upCost of capital 12%8,14,40,0005.73GO — NPV remains positive; consider partial grant blending.
S6 — Combined adverseYield 1,350; Tariff 6.50; Capex 37,000; WACC 12%2,14,00,00010.65CONDITIONAL — project still NPV-positive but margin thin; only proceed with subsidy + low-cost debt.

6. Certification & HS-code block

6.1 Standards & certifications required

DomainStandardHyperlink
Module — design qualification (India)IS 14286 (BIS, mapped to IEC 61215)Bureau of Indian Standards
Module — design qualification (international)IEC 61215-1:2021IEC Webstore
Module — safetyIEC 61730-1/-2IEC Webstore
Inverter — safety (India)IS 16169 (mapped to IEC 62109)Bureau of Indian Standards
Inverter — safety (international)IEC 62109-1:2010 / IEC 62109-2:2011IEC Webstore
Grid interfaceIEEE 1547-2018 / IEEE 519-2022IEEE Standards
Aquaculture environmentalCAAQMS compliance for any diesel back-up; Coastal Regulation Zone clearance if within 500 m of HTL — verify with state CZMA.—
InsuranceAll-risk policy covering pond-side mounting corrosion + cyclone load (coastal districts).—

6.2 Equipment family — candidate SKUs (illustrative, RFQ-bounded)

SlotFamilyExample marketed SKUPublic reference
ModuleMono-PERC bifacial, 540–550 Wp, 144 half-cellLONGi Hi-MO 5m LR5-72HTH 540-555 MLONGi product page
Module (alt)N-type TOPCon, 430–460 Wp, 54-cellJinko Solar Tiger Neo JKM-N-54HL4R-VJinko Solar product page
Module (alt)N-type i-TOPCon, 420–445 Wp, 54-cellTrina Solar Vertex TSM-NEG19RC.20Trina Solar product page
String inverter250–330 kW, 1500 V DC, 3-phaseSungrow SG250HXSungrow utility-scale inverter page
String inverter (alt)300 kW, 1500 V DC, 3-phaseHuawei SUN2000-330KTL-H1Huawei Smart PV Utility page
String inverter (alt)250 kW, 1500 V DC, 3-phaseGrowatt MAX 253KTL3-X HVGrowatt product page
MountingHDG fixed-tilt ground mount, pile-drivenGeneric; SKU bound at RFQMNRE-SPV-MIS-2023 design guideline

Disclaimer: the equipment list above is a design-brief specification, not yet bound to a supplier SKU. Final SKU selection will be made at RFQ stage subject to BIS R-Number verification and the datasheets in §7.

6.3 HS-code block (for aquaculture-solar BoS reference)

HS codeDescriptionIndicative duty status
8541.43Solar cells, whether or not assembled in modulesBCD PENDING — confirm at ICEGATE tariff line.
8541.42Solar PV cells not in modulesBCD PENDING — confirm at ICEGATE.
8504.40Static converters (inverters)BCD PENDING — confirm at ICEGATE; some HSN lines carry separate IGST treatment.
7610.90Aluminium mounting structuresBCD PENDING — confirm at ICEGATE.
8544.49DC/AC cables, otherBCD PENDING — confirm at ICEGATE.

Lookup instructions: (i) Visit ICEGATE → "Tariff" → enter 6-digit HS code. (ii) Cross-check with CBIC "Customs Tariff" current edition. (iii) For DGFT incentives, cross-check ITC-HS at DGFT. Disclaimer: duty rates change via annual Finance Bill / customs notifications; TradVolt does NOT assert any duty rate as fact. All figures above are marked PENDING and require confirmation by the importer's CHA before shipment.

7. CTAs

CTA 1 — Request Quote: Request a 400 kWp aquaculture solar quote (IN)

CTA 2 — Download datasheet: Download the 400 kWp aquaculture solar datasheet (PDF)

8. Methodology notes

All TCO cells in §3 and §4 were produced by TradVolt's computed 25-year discounted-cash-flow engine from the inputs declared in §2 (single self-consumption share of 100%, zero export tariff, zero terminal residual). The engine applies linear module degradation of 0.5%/yr on year-1 output, escalates O&M at 2%/yr, escalates avoided tariff at 3%/yr, books inverter replacement (10% of capex) in year 12, and discounts all post-year-0 cash flows at 10.00%. LCOE is total undiscounted cost ÷ total undiscounted generation, not a discounted ratio. The earlier R9 draft showed different headline figures because it used a different O&M treatment (no escalation) and a different year-1 net CF basis; those numbers are superseded by the computed 5.73 yr simple payback / 10,208,139 INR NPV set.

9. Sources

IDDocumentURL
S-01IEA-PVPS T13-22:2024 "Photovoltaic System Reliability Trends 2024"https://iea-pvps.org/snapshot-reports/photovoltaic-system-reliability-trends-2024/
S-02CEA "Growth of Electricity Sector in India" 2024 (10-yr CAGR review)https://www.cea.nic.in/
S-03SECI tender reference (500 kWp Q3 2025 benchmark)https://www.seci.co.in/
S-04SECI O&M tender referencehttps://www.seci.co.in/
S-05RBI 10-yr G-Sec reference ratehttps://www.rbi.org.in/Scripts/FS_Overview.aspx?fn=2754
S-06MNRE-SPV-MIS-2023 lifetime design guidelinehttps://mnre.gov.in/en/yearly-archives/
S-07MNRE "Solar PV Power Plants — Performance Ratio" advisorieshttps://mnre.gov.in/en/yearly-archives/
S-08ICEGATE tariff lookuphttps://www.icegate.gov.in/
S-09CBIC Customs Tariff current editionhttps://www.cbic.gov.in/
S-10DGFT ITC-HShttps://www.dgft.gov.in/
S-11BIS — IS 14286 (module, mapped to IEC 61215)https://www.bis.gov.in/
S-12BIS — IS 16169 (inverter, mapped to IEC 62109)https://www.bis.gov.in/
S-13IEC 61215-1:2021 (module qualification)https://webstore.iec.ch/publication/61778
S-14IEC 61730-1/-2 (module safety)https://webstore.iec.ch/publication/6164
S-15IEC 62109-1:2010 / -2:2011 (inverter safety)https://webstore.iec.ch/publication/6390
S-16IEEE 1547-2018 / IEEE 519-2022 (grid interface)https://standards.ieee.org/ieee/1547/5915/
S-17LONGi Hi-MO 5m product page (illustrative SKU)https://www.longi.com/en/products/modules/
S-18Jinko Solar Tiger Neo product page (illustrative SKU)https://www.jinkosolar.com/en/products/
S-19Trina Solar Vertex product page (illustrative SKU)https://www.trinasolar.com/en-gl/products
S-20Sungrow SG250HX product page (illustrative SKU)https://en.sungrowpower.com/utility-scale-inverter
S-21Huawei SUN2000-330KTL-H1 product page (illustrative SKU)https://solar.huawei.com/en/products/Utility
S-22Growatt MAX 253KTL3-X HV product page (illustrative SKU)https://www.growatt.com/product

Rows without a public link above are either TradVolt internal benchmarks (clearly flagged in §2) or state-CZMA / insurance items that have no single national URL.