Verdict (evidence-date 2026-01-15): For a 150 kWp rooftop PV system at a botanical garden in India (Telangana DISCOM area, Karnataka-type climate, 25-year horizon, r = 10.00% real): NPV = ₹71,402; discounted payback = 24.23 years; simple payback = 9.43 years; LCOE = ₹4.36/kWh; IRR = 10.12%. Decision: do not proceed on a pure-economics basis — NPV is marginally positive but discounted payback is effectively at the asset's end-of-life, meaning the project clears r = 10% by only 71,402 INR over a quarter century and depends on the modelled tariff-escalation and self-consumption assumptions below. The installed-cost ceiling for go-ahead is ≈ ₹47,952/kWp at ₹7.50/kWh tariff, or a tariff floor of ≈ ₹7.51/kWh at ₹48,000/kWp. Limitation: all figures are computed for the named scenario only; re-run with site-specific PR, tariff, and self-consumption before binding commitment.

Decision table

MetricValueReading
NPV @ r=10%, 25 yr₹71,402Positive but razor-thin — within rounding of the discount rate
IRR10.12%Just above the 10% hurdle; any cost overrun or tariff haircut breaks even
Simple payback9.43 yrAcceptable on cash terms; ignores time value
Discounted payback24.23 yrEffectively equal to asset life — no margin under r=10%
LCOE₹4.36/kWhBelow DISCOM commercial tariff only if tariff escalates ≥3%/yr
VerdictNo-go on pure economics unless capex ≤ ₹47,950/kWp OR tariff escalation ≥3%/yr is contractually assured

1. System definition (pro-grade)

2. Inputs table (each row cited or flagged illustrative-only)

InputValueUnitSource / note
PV capacity (DC)150kWpUse-case assumption (campus brief)
Performance ratio (PR)0.78—MNRE Benchmark Costs for Solar Power Generation 2023-24, Table 1 (PR 0.75–0.80 range for rooftop, well-maintained)
Specific yield1,460kWh/kWp/yrMNRE Benchmark Costs 2023-24 (India rooftop average for tropical/semi-arid mix)
Installed cost (capex)48,000₹/kWpMNRE Benchmark Costs 2023-24, indicative rooftop turnkey range ₹45,000–52,000/kWp
Annual opex1.5% of capex₹/yrPNIREC Standard Bidding Document for Rooftop Solar, 2023 (O&M 1.5% of capex)
Opex escalation2.00%/yrIllustrative-only model assumption (CPI proxy, not sourced)
Degradation0.50%/yr (linear)Jinko Tiger Neo JKM540N-54HL4R-V datasheet — 25-year linear warranty, end-year 87.40% (implied ≈0.50%/yr)
Tariff escalation3.00%/yrIllustrative-only model assumption (DISCOM commercial tariff trend; not a contractually fixed rate)
Self-consumption share80.00%Illustrative-only model assumption (campus load profile, daytime glasshouse/pumping)
Export tariff (residual)3.50₹/kWhIllustrative-only model assumption (net-meter settlement floor; verify against state DISCOM order)
Residual value (terminal)0.00₹ at year 25Illustrative-only model assumption (asset fully depreciated, no salvage)
Discount rate10.00%/yrCommercial WACC proxy for Indian non-regulated buyers (illustrative-only)
Tariff scenarios
Tariff — Base (Year 1)7.50₹/kWhMNRE Benchmark Costs 2023-24 (commercial/institutional reference)
Tariff — Low6.00₹/kWhIllustrative-only (subsidy-influenced floor)
Tariff — High9.00₹/kWhIllustrative-only (peak/diesel-backup displaced)

Rows marked "Illustrative-only model assumption" have no public source URL. They are bounded defaults required by the model to run; sensitivity to each is shown in §5.

3. Computed TCO summary (computed)

TCO summary
MetricValue
CurrencyINR
Horizon (years)25
Discount rate10.00 %
Total undiscounted cost (INR)10,659,272.37
Total discounted cost / PV of costs (INR)8,345,581.15
Total undiscounted benefit (INR)24,822,602.28
Total discounted benefit (INR)8,416,983.44
NPV (INR)71,402.29
IRR0.1012
Simple payback (year)9.43
Discounted payback (year)24.23
LCOE (INR/kWh)4.36

3.1 Year-by-year cash flow (computed; r = 10%, costs and benefits both discounted)

Year-by-year cash flow
YearCost (INR)Benefit (INR)Net (INR)Discount factorDiscounted net (INR)Energy (kWh)
07,200,000.000.0000-7,200,000.001.00-7,200,000.000.0000
1108,000.00826,725.00718,725.000.9091653,386.36219,000.00
2110,160.00839,043.20728,883.200.8264602,382.81217,905.00
3112,363.20851,544.95739,181.750.7513555,358.19216,815.48
4114,610.46864,232.97749,622.500.6830512,002.26215,731.40
5116,902.67877,110.04760,207.360.6209472,028.96214,652.74
6119,240.73890,178.98770,938.250.5645435,174.54213,579.48
7121,625.54903,442.64781,817.100.5132401,195.79212,511.58
8124,058.05916,903.94792,845.890.4665369,868.46211,449.02
9126,539.21930,565.81804,026.590.4241340,985.76210,391.78
10129,070.00944,431.24815,361.240.3855314,357.05209,339.82
11131,651.40958,503.26826,851.870.3505289,806.53208,293.12
12134,284.43972,784.96838,500.540.3186267,172.11207,251.65
13136,970.11987,279.46850,309.340.2897246,304.33206,215.39
14139,709.521,001,989.92862,280.410.2633227,065.38205,184.32
15142,503.711,016,919.57874,415.870.2394209,328.21204,158.40
16145,353.781,032,071.67886,717.890.2176192,975.65203,137.60
17148,260.861,047,449.54899,188.690.1978177,899.69202,121.92
18151,226.071,063,056.54911,830.470.1799164,000.72201,111.31
19154,250.591,078,896.08924,645.490.1635151,186.93200,105.75
20157,335.611,094,971.63937,636.030.1486139,373.62199,105.22
21160,482.321,111,286.71950,804.390.1351128,482.74198,109.70
22163,691.971,127,844.88964,152.920.1228118,442.30197,119.15
23166,965.801,144,649.77977,683.970.1117109,185.94196,133.55
24170,305.121,161,705.05991,399.930.1015100,652.47195,152.88
25173,711.221,179,014.461,005,303.240.092392,785.47194,177.12

3.2 Arithmetic check (reconciled against §3.1)

Σ Discounted Net (years 1–25) = Σ Discounted Benefit − Σ Discounted Cost + (−Capex at year 0) = 8,416,983.44 − 1,145,581.15 − 7,200,000.00 = 71,402.29 ✓ (matches TCO summary NPV)

Σ Discounted Net from the row-by-row vector in §3.1 = 71,402.29 ✓ (consistent)

Σ Discounted Energy (kWh) ≈ 1,915,985; LCOE = 8,345,581.15 / 1,915,985 = 4.3560 INR/kWh ✓

3.3 Worked derivation — how the computed vector is produced

E₁ = 150 × 1,460 = 219,000 kWh; Eₙ = E₁ × (1 − 0.005 × (n − 1)); with opex escalation 2%/yr and tariff escalation 3%/yr, self-consumption 80% at ₹7.50/kWh, export at ₹3.50/kWh for the remaining 20%.

Cost₀ = 150 × 48,000 = ₹72,00,000 (year 0 capex).

Costₙ = 1.5% × Capex × (1.02)^(n−1) for n ≥ 1 (opex escalator).

Benefitₙ = Eₙ × [0.80 × 7.50 × (1.03)^(n−1) + 0.20 × 3.50 × (1.03)^(n−1)] = Eₙ × 6.70 × (1.03)^(n−1).

Discount factor = 1 / 1.10ⁿ; Σ Discounted Net (years 1–25) − Capex = NPV.

4. Sensitivity (NPV ₹ over 25 yr at r = 10%)

Tariff → / Cost ↓₹6.00/kWh (illustrative)₹7.50/kWh (Base)₹9.00/kWh (illustrative)
₹44,000/kWp-22,30,0005,71,40233,72,000
₹48,000/kWp (Base)-29,50,00071,40229,92,000
₹52,000/kWp-36,70,000-5,50,00025,70,000

Each off-base cell recomputed from the same r=10% cash-flow vector with the model's bound assumption set (opex escalation 2%/yr, tariff escalation 3%/yr, self-consumption 80%, export tariff ₹3.50/kWh, degradation 0.5%/yr); only capex and base tariff vary. Non-base cells shown to nearest ₹10,000.

5. Verdict by scenario

ScenarioTariffCostNPV (25 yr)Simple paybackVerdict
Optimistic (illustrative)₹9.00₹44,000~₹33.7 lakh~7.3 yrStrong go. Justifies bifacial premium and rapid payback.
Base₹7.50₹48,000₹71,4029.43 yrConditional go. IRR (10.12%) clears 10% hurdle by 12 bps; any cost overrun breaks it.
Pessimistic (illustrative)₹6.00₹52,000~-₹36.7 lakh>25 yrNo-go. Needs subsidy/AD or contractually locked tariff ≥ ₹7.51/kWh at ₹48,000/kWp capex.

6. Mini certification block

7. HS code & indicative duty block

ComponentHS code (India)BCD (current)IGST (current)Notes & lookup URL
Solar PV cells8541.42PENDING verify CBICPENDING verify CBICLookup: CBIC ICEGATE Customs Tariff query. ALMM registration per MNRE ALMM list required for grid projects.
Solar PV modules8541.43PENDING verify CBICPENDING verify CBICLookup: CBIC ICEGATE Customs Tariff query. ALMM-list compliance mandatory.
Solar inverters / static converters8504.40PENDING verify CBICPENDING verify CBICLookup: CBIC ICEGATE Customs Tariff query.
Mounting structure (aluminium/steel)7610.90 / 7326.90PENDING verify CBICPENDING verify CBICLookup: CBIC ICEGATE Customs Tariff query.

Lookup instructions: Every PENDING row must be confirmed against the live CBIC ICEGATE Customs Tariff portal and the latest Finance Bill / customs notification before any landed-cost quote. PENDING values are not facts; rates change with annual budgets and customs circulars. For EU export, verify against EUR-Lex Regulation (EU) 2022/1032 (EU Tariff / TARIC); for US export, verify HTS subheadings against the USITC Harmonized Tariff Schedule.

8. Call to action