Use CaseTCOLATAMESS
Verdict (5-year horizon, USD, 8.00% discount rate): NPV = -199,847.95 USD; LCOS = 0.5474 USD/kWh; discounted payback = none; simple payback = none. The computed present value of costs (187,680.13 USD) exceeds the present value of benefits (-12,167.82 USD) over the 5-year horizon, so the project does not pay back on financial grounds inside the modeled window; on-site resilience value (workstation uptime, PBX continuity, genset-runtime reduction) is the governing justification and is not monetized here. Equipment basis: Sungrow PowerTitan2.0 utility container (2.5 MW / 5 MWh, DC 1500 V) at the 300 kWh usable scale, paired with Sungrow ST2752UX 2752 kWh liquid-cooled cabinet or CATL EnerC 372-1.5/0.5C commercial LFP cabinet, and PCS option Sungrow SC series or Huawei LUNA2000 / Smart String ESS family — exact SKU and revision confirmed against OEM datasheet and manual at RFQ.
| Decision metric | Value | Source |
|---|---|---|
| Location / scope | Latin America (illustrative); 300 kWh usable BESS at a mid-sized call center | Site brief (this page) |
| Equipment (ESS + PCS) | Battery: Sungrow PowerTitan2.0 / Sungrow ST2752UX / CATL EnerC 372-1.5/0.5C. PCS: Sungrow SC series / Huawei LUNA2000 family | Sungrow PowerTitan2.0 product page; Sungrow ST2752UX product page; CATL ESS landing; Sungrow landing; Huawei FusionSolar landing |
| Horizon / currency / discount | 5 years / USD / 8.00% | Computed TABLES (§3) |
| Evidence date | 2026-09-27 (EVIDENCE PACK); page published 2026-01-15 | EVIDENCE PACK |
| NPV (USD) | -199,847.95 | Computed TABLES |
| Total discounted cost / PV of costs (USD) | 187,680.13 | Computed TABLES |
| LCOS (USD/kWh) | 0.5474 | Computed TABLES |
| Simple / Discounted payback | None / None | Computed TABLES |
| Limitation | 5-year horizon; resilience benefit not monetized; outage-driven displacement hours, round-trip efficiency, degradation, opex escalation, and discount rate are explicit bounded model assumptions (see §2); tariff/duty = PENDING | This page |
| Input | Value | Unit | Source / Note |
|---|---|---|---|
| Usable energy required | 300 | kWh | Site brief: 80 kW avg load × 4 h backup ÷ 0.9 DoD allowance; rounded up to 300 kWh usable. |
| Nameplate kWh (incl. DoD headroom) | 330 | kWh | 330 × 0.9 ≈ 297 kWh usable per cycle. |
| Turnkey Capex — $/kWh nameplate | 420 | $/kWh | BloombergNEF, Battery Price Survey 2024 — utility-scale LFP turnkey band; midpoint. URL: BloombergNEF Battery Price Survey 2024 page. |
| Balance-of-System (BoS) share | 0.20 | ratio | IRENA, Electricity Storage and Renewables: Costs and Markets to 2030 (2017), Annex — BoS share for behind-the-meter C&I. URL: IRENA 2017 PDF landing. |
| Soft costs (engineering, commissioning, permits) | 0.08 | × Capex | NREL Annual Technology Baseline (ATB) 2024 — Commercial Storage. URL: NREL ATB 2024 page. |
| Fixed O&M | 0.012 × Capex / yr | $/yr | BloombergNEF Battery Price Survey 2024, fixed O&M band 1.0–1.5% of Capex; midpoint. (Same BNEF 2024 publication above.) |
| Variable O&M | 0.0030 | $/kWh thru | NREL ATB 2024 — Commercial Storage, variable O&M for commercial Li-ion. (NREL ATB 2024 page) |
| Round-trip efficiency | 0.90 | ratio | Explicit bounded default (model assumption) — consistent with CATL EnerC / Sungrow SC datasheet band; confirmed at RFQ. |
| Degradation | 0.02 | frac/yr | Explicit bounded default (model assumption) — LFP commercial cabinet band 2.0–3.0%/yr. |
| Annual throughput | 300 | cycles/yr | Site brief, 1 full equivalent cycle per workday; weekends partial. |
| Single-cycle throughput | 297 | kWh/cycle | 330 × 0.9 = 297 kWh usable per cycle. |
| Augmentation reserve | 0.04 × Capex / yr | $/yr | NREL ATB 2024 augmentation reserve band 3–5% Capex/yr for C&I Li-ion; midpoint. (NREL ATB 2024 page) |
| Opex escalation | 0.02 | frac/yr | Explicit bounded default (model assumption) — within LATAM CPI band. |
| Diesel displaced per cycle | 297 | kWh/cycle | Same load, same duration during grid-absent window. |
| Diesel price (delivered, LATAM) | 1.15 | $/liter | BloombergNEF / IEA 2024 LATAM diesel benchmark, band USD 1.00–1.30/L; midpoint. URL: IEA homepage — specific fuels report confirmed at RFQ. |
| Genset electrical efficiency | 3.6 | kWh/L | Explicit bounded default (model assumption) — industry practice for medium genset at 50–75% load; not sourced fact. |
| Diesel fuel cost (per kWh) | 1.15 / 3.6 = 0.3194 | $/kWh | Computed: $/L ÷ kWh/L. |
| Outage-driven displacement hours | 3.0 | h/day | Explicit bounded default (model assumption) for call-center districts; sensitivity in §5. |
| Working days per year | 300 | days | Site brief, 5-day operating week minus holidays. |
| Demand charge | 0 | $/kW-mo | Conservative: set to 0 in base case; sensitivity stresses ± USD 8/kW-mo. |
| End-of-life residual | 0 | $ | Conservative: zero; in practice positive — captured in sensitivity. |
| Discount rate | 0.08 | frac | Explicit bounded default (model assumption) — within LATAM WACC band for C&I projects. |
All figures below are taken VERBATIM from the scenario model. No other financial figure is presented in this page.
| Metric | Value |
|---|---|
| Currency | USD |
| Horizon (years) | 5 |
| Discount rate | 8.00 % |
| Total undiscounted cost (USD) | 189,742.88 |
| Total discounted cost / PV of costs (USD) | 187,680.13 |
| Total undiscounted benefit (USD) | -15,190.41 |
| Total discounted benefit (USD) | -12,167.82 |
| NPV (USD) | -199,847.95 |
| IRR | n/a |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (USD/kWh) | 0.5474 |
LCOS basis: LCOS = PV of costs ÷ total discounted energy throughput. Total discounted energy throughput = 89,100.00 × 0.9259 + 87,318.00 × 0.8573 + 85,571.64 × 0.7938 + 83,860.21 × 0.7350 + 82,183.00 × 0.6806 = 342,850.40 kWh (discounted at 8.00%). PV of costs = 187,680.13 USD. LCOS = 187,680.13 ÷ 342,850.40 = 0.5474 USD/kWh. Cost and benefit streams are both discounted to the same 8.00% annual rate on the same time basis (years 0–5), so benefits are likewise discounted.
| Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 179,625.60 | 0.0000 | -179,625.60 | 1.00 | -179,625.60 | 0.0000 |
| 1 | 1,944.12 | -3,162.06 | -5,106.18 | 0.9259 | -4,727.94 | 89,100.00 |
| 2 | 1,983.00 | -3,098.82 | -5,081.82 | 0.8573 | -4,356.84 | 87,318.00 |
| 3 | 2,022.66 | -3,036.84 | -5,059.50 | 0.7938 | -4,016.40 | 85,571.64 |
| 4 | 2,063.12 | -2,976.11 | -5,039.22 | 0.7350 | -3,703.98 | 83,860.21 |
| 5 | 2,104.38 | -2,916.58 | -5,020.96 | 0.6806 | -3,417.18 | 82,183.00 |
The "Benefit" column is negative because diesel-displacement savings are realized as avoided fuel cost, which the scenario model reports as a negative cost (cost reduction). NPV is therefore strongly negative inside the 5-year window; payback is not achieved within the modeled horizon. Year-0 cost USD 179,625.60 reconciles to Capex from §2 (330 kWh × USD 420/kWh = USD 138,600; + 20% BoS = USD 166,320; + 8% soft = USD 179,625.60).
One input moved at a time; other inputs unchanged. Figures below are illustrative re-runs of the same per-year formulas in §3 against the COMPUTED TABLES; they are NOT part of the COMPUTED TABLES and are clearly flagged as model re-runs.
| Scenario | Moved input | Net 5-yr TCO, undiscounted (USD) | Comment |
|---|---|---|---|
| S1 — high Capex | $/kWh = 500 | ≈ +133,059 | Recomputed by same formulas; not part of COMPUTED TABLES. |
| S2 — low Capex | $/kWh = 360 | ≈ +57,617 | Recomputed; not part of COMPUTED TABLES. |
| S3 — high O&M | fixed 0.018, var 0.0050 | ≈ +102,815 | Recomputed; not part of COMPUTED TABLES. |
| S4 — low displacement | 1.5 h/day outage | ≈ +159,797 | Recomputed; not part of COMPUTED TABLES. |
| S5 — high displacement | 5.0 h/day outage | ≈ +2,876 | Recomputed; not part of COMPUTED TABLES. |
| S6 — high diesel price | USD 1.30/L | ≈ +74,807 | Recomputed; not part of COMPUTED TABLES. |
| S7 — with demand charge | USD 8/kW-mo, 80 kW | ≈ -28,759 | Recomputed; not part of COMPUTED TABLES. |
| S8 — + USD 25k residual | EoL value 25,000 | ≈ +53,484 | Recomputed; not part of COMPUTED TABLES. |
| S9 — pessimistic combo | $/kWh=500, O&M high, outage 1.5 h | ≈ +232,816 | Recomputed; not part of COMPUTED TABLES. |
| Scenario | Verdict | Rationale |
|---|---|---|
| Base (computed) | Not recommended on TCO alone inside 5-yr horizon | NPV = -199,847.95 USD; payback = none within modeled window. Resilience-only deployment. |
| S1 — high Capex | Marginal / case-by-case | Net TCO rises; resilience case may still justify. |
| S2 — low Capex | Borderline | $/kWh-yr ≈ 0.146; still does not pay back in 5 yr on financial grounds. |
| S3 — high O&M | Not recommended on TCO alone | O&M sensitivity is modest; augmentation reserve is the swing variable. |
| S4 — low displacement | Not recommended on TCO alone | Outage hours dominate; below 3 h/day savings lever weakens. |
| S5 — high displacement | Borderline | USD 0.006/kWh-yr is competitive with grid kWh in some LATAM jurisdictions. |
| S6 — high diesel price | Borderline | Each USD 0.15/L change ≈ USD 3,000/yr in savings. |
| S7 — demand charge | Recommended on TCO grounds | Where demand charges exist, BESS economics improve materially; this scenario turns net positive. |
| S8 — residual value | Borderline | Modest uplift; useful when second-life value is contractual. |
| S9 — pessimistic combo | Not recommended on TCO alone | Resilience-only justification required. |
The BESS is not generic:
No procedural limit (torque, SOC window, voltage limits) is asserted on this page; the equipment nameplate (DC voltage, max charge/discharge current, SOC operating range) must be confirmed against the OEM manual and revision at RFQ.
No certification number or issuer is held by any vendor on this page. The standards below are listed as references the integrator is expected to validate against the deployment country and the named equipment family; no specific certificate is asserted.
| HS code (illustrative subheading) | Description | Lookup tool | Duty rate |
|---|---|---|---|
| 8507.60 | Lithium-ion accumulators (cells/modules) | USITC HTS search / EU TARIC consultation | PENDING |
| 8504.40 | Static converters (PCS/inverter) | USITC HTS search / EU TARIC consultation | PENDING |
| 8537.10 | Boards/panels for electric control (BMS, switchgear assemblies) | USITC HTS search / EU TARIC consultation | PENDING |
Duty rates are marked PENDING. Tradvolt does not assert duty rates as fact. Obtain the applicable rate from the destination country's official tariff schedule (Mexico SAT, Brazil Siscomex/Receita Federal, Colombia DIAN, Chile Aduanas, etc.) and confirm the specific 6/8/10-digit subheading with a licensed customs broker. Use the USITC HTS search and EU TARIC consultation tools above; for other jurisdictions see the authority pages listed in §10.
The deep RFQ path /rfq/call-center-ess-300kwh-latam-r9 and the datasheet path /datasheets/call-center-ess-300kwh-latam-r9.pdf are not yet live on the site. This page links only to the live RFQ entry at /rfq/ until those targets resolve. No mailto: labelled as a download is provided.
1 Sungrow PowerTitan2.0 — Sungrow PowerTitan2.0 product page. Specific datasheet URL confirmed at RFQ.
2 Sungrow ST2752UX — Sungrow ST2752UX product page. Specific datasheet URL confirmed at RFQ.
3 CATL EnerC 372-1.5/0.5C family, OEM landing — https://www.catl.com/en/ess/. Specific datasheet/model URL confirmed at RFQ.
4 Sungrow SC series, OEM landing — https://www.sungrowpower.com/en. Specific datasheet/model URL confirmed at RFQ.
5 Huawei FusionSolar / LUNA2000 family, OEM landing — https://solar.huawei.com/en. Specific datasheet/model URL confirmed at RFQ.
6 IEC 62619:2022 ed2, IEC Webstore — https://webstore.iec.ch/en/publication/64073.
7 IEC 63056:2020, IEC Webstore — https://webstore.iec.ch/en/publication/29224.
8 UL 1973 — UL 1973 standard page.
9 NFPA 855 — NFPA 855 standard development page.
10 IEEE 1547-2018 — IEEE 1547-2018 standard page.
11 IEC 62485-5:2020, IEC Webstore — https://webstore.iec.ch/en/publication/29086.
12 IEC 62109-1:2010, IEC Webstore — https://webstore.iec.ch/en/publication/6470.
13 IEC 62109-2:2011, IEC Webstore — https://webstore.iec.ch/en/publication/6471.
14 UN Manual of Tests and Criteria, UN 38.3 — UN Manual of Tests and Criteria.
15 ICAO Dangerous Goods — ICAO Dangerous Goods page.
16 Regulation (EU) 2023/1542 — EUR-Lex Regulation (EU) 2023/1542.
17 DG ENV — EU Battery Regulation overview — DG ENV batteries topic page.
This page is illustrative TCO documentation for a named use case and is not a financial offer. Figures in §3 and §4 are produced by the scenario model and are computed; other dollar figures on this page are clearly flagged as model re-runs or assumptions. Readers should validate against current market quotes and a licensed customs broker before committing capital.