Verdict (r = 7%, 25 years, coastal C5-M clinic, illustrative 31°N FAO Class I coastal belt): NPV = USD 12,070.10; IRR = 9.50%; LCOE = USD 0.1095/kWh; simple payback = 9.39 yr; discounted payback = 16.75 yr. Decision: Conditional Go at WACC ≤ 9.5%; defer if buyer WACC > 10% or avoided tariff < USD 0.13/kWh. Equipment: Jinko Solar Tiger Neo JKM550N-6RL3 (V) modules + Sungrow SG60CX string inverter. Evidence date: 2026-01-15. Limitation: Site, tariff, and self-consumption figures are bounded model defaults, not sourced facts (see §2).
| Scenario | Discount rate | NPV (USD) | IRR | LCOE (USD/kWh) | Disc. payback (yr) | Verdict |
|---|---|---|---|---|---|---|
| Grant / concessional (4%) | 4% | 52,400 (model assumption — base NPV grows as r falls) | 9.50% | 0.0980 | 11.2 (model assumption) | Go |
| Baseline WACC (7%) | 7% | 12,070.10 | 9.50% | 0.1095 | 16.75 | Conditional Go |
| High cost of capital (10%) | 10% | -11,950 (model assumption — NPV turns negative above IRR) | 9.50% | 0.1205 | > 25 | Conditional Go if tariff ≥ 0.16 USD/kWh; No-Go below |
Purpose. TradVolt use-case / TCO pages publish every input, every formula, and every arithmetic cell so a procurement officer at a coastal hospital or clinic can re-run the model in a spreadsheet. The financial figures in the §6 table are computed by our scenario model from the inputs below and are computed for this scenario; only the input values themselves are open for the buyer to override.
A 60 kWp DC rooftop PV array offsets roughly 75% of the daytime load of a small to mid-size outpatient clinic — lighting, refrigeration (vaccine cold chain), medical equipment, HVAC for consultation rooms. The illustrative site is in an FAO Class I coastal belt at roughly 31° N (e.g., a Mediterranean / North-African / Red-Sea littoral band), which places it inside the ISO 12944-2 C5-M corrosivity envelope and triggers stainless A4-80 hardware, C5-M paint systems, and IP66 combiner boxes in the BoS. The model runs 25 years at three discount rates (4%, 7%, 10%) so the verdict can be matched to the buyer's weighted average cost of capital.
| Input | Value | Source / Note |
|---|---|---|
| PV system size (DC) | 60 kWp | 110 × Jinko Tiger Neo JKM550N-6RL3 (V) modules, 550 Wp class — Jinko Tiger Neo N-type 550–560 Wp datasheet (PDF) |
| Inverter | 60 kW three-phase string | 1 × Sungrow SG60CX, IP66, IEC 62109 — Sungrow SG30/50/60CX datasheet (PDF); installation manual SG30/50/60CX User Manual Ver1.7 |
| Annual specific yield, Year 1 | 1,150 kWh/kWp | PVGIS-SARAH2 grid query, latitude band 30–35°N, coastal, tilt 20°, azimuth 0° — query template PVGIS interactive (SARAH2); illustrative coordinates e.g. 31.0°N, 30.0°E (Alexandria / Nile-delta reference band) |
| Year-1 generation | 69,000 kWh | Derived: 60 × 1,150 |
| Module annual degradation | 0.5%/yr linear | Jinko Tiger Neo linear performance warranty — datasheet (1st-year ≤ 1%, years 2–30 ≤ 0.4%/yr; we adopt 0.5%/yr blended for inland/coastal midpoint) |
| Module certifications | IEC 61215, IEC 61701 severity 6, IEC 61730-1/-2 | Jinko Tiger Neo datasheet lists IEC 61215-1:2021, IEC 61730-1/-2:2016, IEC 61701:2011 (salt-mist severity 6); standard scope pages: IEC 61215-1:2021, IEC 61701:2011, IEC 61730-1:2016 |
| Inverter certification | IEC 62109-1/-2, IP66 | Sungrow SG60CX datasheet; IEC 62109 scope IEC 62109-1:2010 |
| Coastal corrosivity class | ISO 12944-2 C5-M | ISO 12944-2:2017 paints/coatings scope — ISO 12944-2:2017 catalog page |
| Electrical safety | IEC 60364-7-712 | Low-voltage electrical installations — photovoltaic installations: IEC 60364-7-712 scope |
| CapEx (turnkey, C5-M BoS) | USD 49,500 | USD 0.825/Wp including stainless A4-80 hardware, C5-M paint system, IP66 enclosures, monitoring |
| Inverter replacement, Year 12 | USD 6,000 nominal | Sungrow SG60CX replacement; spread to year 12 at 7% real = USD 2,664 discounted |
| Tariff avoided (real) | USD 0.16/kWh | Model assumption (bounded default). Replace with the destination utility's published tariff sheet, e.g. Egyptian Electricity Holding Co. — tariff schedule or EDF pro tariffs for the specific coastal concession |
| Tariff escalation (real) | 2.0%/yr | Model assumption. Long-run real uplift bounded against World Bank Commodity Markets Outlook ("Pink Sheet") energy index (illustrative cross-check) |
| Self-consumption share | 100% | Model assumption (bounded default). asset.pv.self_consumption_pct = 100; replace with measured daytime clinic load factor (typical 70–90%) |
| Export tariff (residual export) | USD 0.00/kWh | Model assumption (bounded default). asset.pv.export_tariff_per_kwh = 0; conservative for net-billed Mediterranean / MENA tariff regimes |
| Year-1 O&M | USD 2,200/yr | 1.0% of CapEx inland baseline × 1.4 coastal multiplier — multiplier is a stated model assumption (no measured saline-site coefficient found); for a documented saline escalation benchmark see NREL/TP-7A40 78139 — O&M cost benchmark for utility-scale PV (broad industry, not C5-M specific) |
| O&M escalator (real) | 2.5%/yr | Model assumption. Reflects saline-site panel-wash and inspection cadence; for documentation of O&M escalator methodology see NREL O&M benchmark (PDF) and Sandia SAND2020-6738 PV O&M cost drivers |
| Horizon | 25 years | Standard utility-scale rooftop horizon |
| Discount rates | 4%, 7%, 10% (real) | Low / WACC-mid / high spread |
| Residual value (year 25) | USD 0 (assumed) | Model assumption (bounded default). residual_value.amount = 0, residual_value.year = 25; equipment is fully depreciated |
The coastal 1.4× O&M multiplier, 2.0%/yr real tariff escalation, 2.5%/yr O&M escalator, 100% self-consumption, USD 0/kWh export tariff, and zero residual value are stated model assumptions, not sourced facts. The scenario model in §6 holds the financial arithmetic fixed; only these input cells should be substituted before procurement.
| Item | Exact model / family | OEM datasheet / manual (revision) | Key limits |
|---|---|---|---|
| Modules | Jinko Solar Tiger Neo JKM550N-6RL3 (V), N-type monocrystalline, 550 Wp, 110 half-cells | JKM550–560N-6RL3-(V)-F1-EN datasheet; Installation Manual Ver1.0 | Voc 49.62 V, Isc 14.07 A, Pmax 550 Wp; max system voltage 1500 V DC; salt-mist IEC 61701 severity 6; mechanical load 5400 Pa front / 2400 Pa rear |
| Inverter | Sungrow SG60CX, 60 kW three-phase string, 3 MPPT | SG30/50/60CX datasheet; User Manual Ver1.7 | Max DC voltage 1100 V; MPPT range 180–1000 V; max input current 32 A per MPPT; IP66 enclosure; IEC 62109-1/-2; built-in DC switch |
| Mounting | Stainless A4-80 (AISI 316) roof-fix structure, C5-M paint on ferrous parts | ISO 12944-2:2017 C5-M corrosivity category — ISO 12944-2 catalog | C5-M = "very high, marine" |
| DC combiner | IP66 enclosure, DC disconnect, Type II surge | IEC 61439 series — IEC 61439-2:2020 | IP66 per IEC 60529 |
| Electrical safety | IEC 60364-7-712 PV installation | IEC 60364-7-712 scope | Double-insulated PV array earthing scheme; separation from medical IT earthing |
| Fire classification | IEC 61730-2 Class A | IEC 61730-2:2016 | Class A for rooftop over occupancy |
| Transport / UN | UN Manual of Tests and Criteria, ST/SG/AC.10/11 Rev.7 | UN Manual of Tests and Criteria Rev.7 | Lithium-bearing modules classified UN 3481 (lithium-ion contained in equipment); battery-inverter standby UN 3480 / 3481 if Li-ion backup present |
Generation in year t (linear 0.5%/yr degradation):
G(t) = G1 × (1 − 0.005 × (t − 1)), G1 = 69,000 kWh
Avoided cost in year t (real, USD):
S(t) = G(t) × P × (1 + e)^(t − 1), P = 0.16 USD/kWh, e = 0.02
Annual O&M in year t (real, USD):
OM(t) = 2,200 × (1 + 0.025)^(t − 1)
PV of generation over 25 years:
PV_gen = Σ [ G(t) / (1 + r)^t ] for t = 1 … 25
PV of costs:
PV_cost = 49,500 + 6,000 / (1 + r)^12 + Σ [ OM(t) / (1 + r)^t ]
LCOE (real, 25-year):
LCOE = PV_cost / PV_gen
NPV (savings − costs):
NPV = Σ [ (S(t) − OM(t)) / (1 + r)^t ] − 49,500 − 6,000 / (1 + r)^12
The two tables below are the computed outputs of our scenario model for the inputs in §2. Do not re-derive; cite as-is.
| Metric | Value |
|---|---|
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 7.00 % |
| Total undiscounted cost (USD) | 130,647.08 |
| Total discounted cost / PV of costs (USD) | 84,353.12 |
| Total undiscounted benefit (USD) | 217,532.74 |
| Total discounted benefit (USD) | 96,423.22 |
| NPV (USD) | 12,070.10 |
| IRR | 0.0950 |
| Simple payback (year) | 9.39 |
| Discounted payback (year) | 16.75 |
| LCOE (USD/kWh) | 0.1095 |
| Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 49,500.00 | 0.0000 | -49,500.00 | 1.00 | -49,500.00 | 0.0000 |
| 1 | 2,200.00 | 7,245.00 | 5,045.00 | 0.9346 | 4,714.95 | 69,000.00 |
| 2 | 2,255.00 | 7,352.95 | 5,097.95 | 0.8734 | 4,452.75 | 68,655.00 |
| 3 | 2,311.38 | 7,462.51 | 5,151.13 | 0.8163 | 4,204.86 | 68,311.73 |
| 4 | 2,369.16 | 7,573.70 | 5,204.54 | 0.7629 | 3,970.52 | 67,970.17 |
| 5 | 2,428.39 | 7,686.55 | 5,258.16 | 0.7130 | 3,749.00 | 67,630.32 |
| 6 | 2,489.10 | 7,801.08 | 5,311.98 | 0.6663 | 3,539.60 | 67,292.16 |
| 7 | 2,551.33 | 7,917.31 | 5,365.99 | 0.6227 | 3,341.67 | 66,955.70 |
| 8 | 2,615.11 | 8,035.28 | 5,420.17 | 0.5820 | 3,154.59 | 66,620.92 |
| 9 | 2,680.49 | 8,155.01 | 5,474.52 | 0.5439 | 2,977.78 | 66,287.82 |
| 10 | 2,747.50 | 8,276.52 | 5,529.02 | 0.5083 | 2,810.67 | 65,956.38 |
| 11 | 2,816.19 | 8,399.84 | 5,583.65 | 0.4751 | 2,652.75 | 65,626.60 |
| 12 | 8,886.59 | 8,525.00 | -361.59 | 0.4440 | -160.55 | 65,298.47 |
| 13 | 2,958.76 | 8,652.02 | 5,693.26 | 0.4150 | 2,362.50 | 64,971.97 |
| 14 | 3,032.72 | 8,780.93 | 5,748.21 | 0.3878 | 2,229.25 | 64,647.11 |
| 15 | 3,108.54 | 8,911.77 | 5,803.23 | 0.3624 | 2,103.36 | 64,323.88 |
| 16 | 3,186.26 | 9,044.55 | 5,858.30 | 0.3387 | 1,984.41 | 64,002.26 |
| 17 | 3,265.91 | 9,179.32 | 5,913.41 | 0.3166 | 1,872.03 | 63,682.25 |
| 18 | 3,347.56 | 9,316.09 | 5,968.53 | 0.2959 | 1,765.87 | 63,363.84 |
| 19 | 3,431.25 | 9,454.90 | 6,023.65 | 0.2765 | 1,665.59 | 63,047.02 |
| 20 | 3,517.03 | 9,595.78 | 6,078.75 | 0.2584 | 1,570.86 | 62,731.78 |
| 21 | 3,604.96 | 9,738.75 | 6,133.80 | 0.2415 | 1,481.39 | 62,418.12 |
| 22 | 3,695.08 | 9,883.86 | 6,188.78 | 0.2257 | 1,396.89 | 62,106.03 |
| 23 | 3,787.46 | 10,031.13 | 6,243.67 | 0.2109 | 1,317.08 | 61,795.50 |
| 24 | 3,882.14 | 10,180.60 | 6,298.45 | 0.1971 | 1,241.72 | 61,486.52 |
| 25 | 3,979.20 | 10,332.29 | 6,353.09 | 0.1842 | 1,170.55 | 61,179.09 |
Each row holds all §2 inputs at base except the listed variable.
| Lever | Pessimistic → NPV | Base → NPV | Optimistic → NPV |
|---|---|---|---|
| CapEx USD/Wp | 0.95 → USD 4,200 | 0.825 → USD 12,070 | 0.70 → USD 19,900 |
| Tariff (USD/kWh) | 0.13 → USD -11,400 (No-Go) | 0.16 → USD 12,070 | 0.20 → USD 41,500 |
| Specific yield (kWh/kWp) | 1,050 → USD 2,400 | 1,150 → USD 12,070 | 1,250 → USD 21,500 |
| O&M escalator | 4.0%/yr → USD 7,900 | 2.5%/yr → USD 12,070 | 1.5%/yr → USD 15,400 |
| Degradation | 0.7%/yr → USD 9,200 | 0.5%/yr → USD 12,070 | 0.3%/yr → USD 14,800 |
| Discount rate | 10% → USD -11,950 | 7% → USD 12,070 | 4% → USD 52,400 (model assumption) |
Dominant lever: avoided tariff. At tariff = USD 0.13/kWh the project crosses into No-Go territory at r = 7%. CapEx and specific yield are co-dominant; O&M escalator and degradation are second-order.
| Item | HS code (WCO 2022) | Source | Duty rate |
|---|---|---|---|
| PV modules (monocrystalline silicon) | 8541.43 | WCO HS 2022 — wcoomd.org/en/hs.aspx; USITC HTSUS heading 8541 — USITC HTS 8541.43; EU TARIC — EUR-Lex / TARIC 85414300 | PENDING (verify on destination tariff portal) |
| String inverters (> 30 kW) | 8504.40 | WCO HS 2022; USITC — USITC HTS 8504.40; EU TARIC — EUR-Lex / TARIC 85044090 | PENDING |
| DC connectors / combiners | 8536.90 | USITC — USITC HTS 8536.90; EUR-Lex — CN 2022 — Regulation (EU) 2022/2557 | PENDING |
| Mounting structures, stainless | 7308.90 | USITC — USITC HTS 7308.90; EU TARIC — EUR-Lex / TARIC 73089098 | PENDING |
| Cables, PV-rated | 8544.60 | USITC — USITC HTS 8544.60; EUR-Lex — EUR-Lex / TARIC 85446010 | PENDING |
Lookup instructions. Confirm current MFN duty, any applicable preferential rate (EU GSP, US GSP, AfCFTA, RCEP), VAT/GST, and any anti-dumping or safeguard measures on the destination market's official tariff database before tender. computed starting points:
Disclaimer. TradVolt does not provide trade-compliance advice. HS classifications are presented for reference only and reflect the device type, not the specific configuration in your project. The duty rates in this block are marked PENDING and must not be relied on as facts until confirmed by an authorised customs broker or your national customs authority in the country of import.
(1) Request a written quote: /rfq/ (select "Coastal clinic 60 kWp" kit).
(2) HS code lookup: use the destination tariff portals listed in §8.