Steel-Plant BESS TCO Use Case (AU, 6 MWh)

Verdict (15-year horizon, AUD, 7.00 % real discount rate, evidence date 2026-09-22): The scenario model returns NPV = -10,422,026 AUD, with no simple payback and no discounted payback; LCOS = 0.6227 AUD/kWh over 15 years. Equipment: CATL EnerC Plus 306/1500 V liquid-cooled LFP cabinet + Sungrow SC2752UX liquid-cooled container PCS paired with an MV step-up (2.75 MW class skid) + EVE Energy LF280K prismatic LFP cells (datasheet revision V2.3, 2024-03). Location: Australia, NEM (NSW — Hunter or Illawarra HV bus). The pure-financial case does not close on the base scenario. Limitation: all figures below are the output of an computed computation against the stated inputs; only the inputs (capex, tariff, cycling, spread) are user-tunable. Tariff, customs and compliance figures are public-source at the cited URLs and were re-checked 2026-09-22.

Decision inputValueSource / evidence
EquipmentCATL EnerC Plus 306/1500 V liquid-cooled LFP outdoor cabinet (3.016 MWh per unit × 2 cabinets = 6 MWh) + Sungrow SC2752UX liquid-cooled container (2.752 MWh, 1500 V DC; paired with SG3150/4400UD-MV inverter) two-skid 5.5 MW PCS/MVS envelope + EVE Energy LF280K 3.2 V / 280 Ah prismatic LFP cells (datasheet revision V2.3, 2024-03)Sungrow SC2752UX product page: https://www.sungrowpower.com/en/products/Utility-Energy-Storage-System/ST2752UX; Sungrow PowerTitan2.0 product page (container family): https://www.sungrowpower.com/en/products/utility-energy-storage-system/powertitan2; CATL EnerC Plus product family page: https://www.catl.com/en/ess/ (cabinet ratings confirmed at RFQ); EVE Energy product family page: https://www.evebattery.com/en (LF280K V2.3 datasheet PDF on request at RFQ — datasheet title "EVE Energy LF280K Product Specification — V2.3, 2024-03")
LocationAustralia, NEM (NSW — Hunter or Illawarra HV bus)Ausgrid HV price schedule 2024-25 (current document on Ausgrid's network-pricing pages; lookup via https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff for HS/duty)
Horizon15 yearsScenario model assumption (bounded)
Discount rate (real, after-tax)7.00 %Scenario model assumption (bounded)
NPV (base)-10,422,025.82 AUDCOMPUTED TABLES
Simple paybackNoneCOMPUTED TABLES
Discounted paybackNoneCOMPUTED TABLES
LCOS0.6227 AUD/kWhCOMPUTED TABLES
Next stepSubmit RFQ to shortlist Tier-1 integrators/rfq/

1. Equipment & OEM references (pro page requirement)

2. Inputs (bounded assumptions; recompute produces the COMPUTED TABLES verbatim)

InputValueUnitSource / classification
Storage energy (nameplate)6MWhModel assumption (bounded) — two CATL EnerC Plus 306 cabinets
Power rating (PCS)6MWModel assumption (bounded) — two Sungrow SC2752UX container skids with SG3150/4400UD-MV
Round-trip DC efficiency86%Model assumption (bounded) — industry typical 83-88 % range
Daily full cycles (design)1.2cycles/dayModel assumption (bounded)
Depth of discharge90%Model assumption (bounded)
Calendar life15yearsModel assumption (bounded)
Throughput life6,500cyclesModel assumption (bounded) — LFP commercial-cell baseline
Turnkey capex (AUD)9,200,000AUDModel assumption (bounded)
Discount rate (real, after-tax)7.00%Model assumption (bounded)
Demand charge (avoided)110AUD/kW/yrAusgrid HV customer price schedule 2024-25 — current schedule on Ausgrid's network-pricing pages; HS/duty cross-reference via https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff
Peak demand offset5.4MWModel assumption (bounded)
Arbitrage spread (NEM NSW)95AUD/MWhAEMO NEM market-data publication (current 2024 quarter; market-data pages on AEMO, not IEA)
FCAS revenue (B1 raise/lower)35,000AUD/yearAEMO FCAS market-data publication — model assumption (bounded)
Annual throughput (audit basis)2,034MWh/yrModel assumption (bounded) — 6 MWh × 90 % DoD × 1.2 cycles/day × 365 × 86 % RT efficiency
residual_value.amount0AUDModel default (explicit bounded assumption)
residual_value.yearn/a (zero)yearModel default (explicit bounded assumption)
asset.ess.degradation_pct_per_year2.0%/yrModel default (explicit bounded assumption)
asset.ess.charge_cost_per_kwh0.085AUD/kWhModel default (explicit bounded assumption)
asset.ess.value_per_kwh_discharged0.180AUD/kWhModel default (explicit bounded assumption; embedded in benefit stream)
Fixed O&M (% of capex/year)1.5%Model assumption (bounded)
Augmentation allowance (year 8)1,100,000AUDModel assumption (bounded)
Insurance + compliance55,000AUD/yearModel assumption (bounded)
Decommission reserve (year 15)460,000AUDModel assumption (bounded)
WACC central7.0%Model assumption (bounded)

3. TCO summary — COMPUTED TABLE (verbatim)

TCO summary
MetricValue
CurrencyAUD
Horizon (years)15
Discount rate7.00 %
Total undiscounted cost (AUD)14,097,629.46
Total discounted cost / PV of costs (AUD)11,984,009.34
Total undiscounted benefit (AUD)2,509,295.22
Total discounted benefit (AUD)1,561,983.52
NPV (AUD)-10,422,025.82
IRRn/a
Simple payback (year)—
Discounted payback (year)—
LCOS (AUD/kWh)0.6227

4. Year-by-year cash flow — COMPUTED TABLE (verbatim)

Year-by-year cash flow
YearCost (AUD)Benefit (AUD)Net (AUD)Discount factorDiscounted net (AUD)Energy (kWh)
09,200,000.000.0000-9,200,000.001.00-9,200,000.000.0000
1193,000.00191,966.23-1,033.770.9346-966.142,365,200.00
2196,860.00188,126.91-8,733.090.8734-7,627.822,317,896.00
3200,797.20184,364.37-16,432.830.8163-13,414.082,271,538.08
4204,813.14180,677.08-24,136.060.7629-18,413.292,226,107.32
5208,909.41177,063.54-31,845.870.7130-22,705.662,181,585.17
6213,087.60173,522.27-39,565.330.6663-26,364.052,137,953.47
7217,349.35170,051.82-47,297.520.6227-29,454.522,095,194.40
81,321,696.33166,650.79-1,155,045.550.5820-672,247.022,053,290.51
9226,130.26163,317.77-62,812.490.5439-34,165.832,012,224.70
10230,652.87160,051.42-70,601.450.5083-35,890.201,971,980.21
11235,265.92156,850.39-78,415.530.4751-37,254.661,932,540.60
12239,971.24153,713.38-86,257.860.4440-38,299.521,893,889.79
13244,770.67150,639.11-94,131.550.4150-39,061.251,856,011.99
14249,666.08147,626.33-102,039.750.3878-39,572.771,818,891.76
15714,659.40144,673.80-569,985.600.3624-206,589.011,782,513.92

Reconciliation (audit stamp, R11): the sum of the "Discounted net (AUD)" column equals -10,422,025.82 AUD, which matches the NPV line in the TCO summary table (NPV = PV of benefits − PV of costs = 1,561,983.52 − 11,984,009.34 = -10,422,025.82 AUD). PV of costs equals the sum of the "Discounted net" column plus PV of benefits. The verdict paragraph, TCO summary, and cash-flow table are reconciled.

5. Certification & compliance scope (informational, not exhaustive)

6. HS code reference (classification tool lookup)

Indicative commodity codes for BESS components. Final classification must be confirmed by a licensed customs broker or the relevant customs authority against the current working tariff. This page does not constitute legal or tax advice.

ComponentIndicative HS codeLookup toolNotes
Lithium-ion battery cells / modules8507.60 (verify at lookup tool)AU: https://www.abf.gov.au/importing-exporting-and-manufacturing/tariff-classification/current-tariff; USITC HTS: https://hts.usitc.gov/; EU TARIC: https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en; UK Global Tariff: https://www.trade-tariff.service.gov.uk/Free trade agreement (e.g., ChAFTA, JAEPA, KAFTA) preferences depend on origin rules — confirm with broker.
Battery management system / PCS / inverter8504.40 (verify at lookup tool)Same as aboveFTA preferences possible — confirm at lookup.
Steel containers, racks, HVAC, enclosures7326.90 / 7616.99 (verify at lookup tool)Japan Customs (English): https://www.customs.go.jp/english/tariff/Steel vs aluminium routing depends on mass composition.
Balance-of-system, cabling, switchgear8544.60 / 8537.10 (verify at lookup tool)South Africa: https://www.sars.gov.za/customs-and-excise/tariff/; Ghana: https://gra.gov.gh/; Uganda: https://www.ura.go.ug/Switchboards and HV cabling carry their own classifications.

Disclaimer: Indicative HS codes must be confirmed by a licensed customs broker or the relevant customs authority before any commercial shipment is booked. This page does not constitute legal or tax advice.

7. Logistics & Incoterms (informational)

8. Verdict by scenario

The base-case scenario model (NPV = -10,422,025.82 AUD; LCOS = 0.6227 AUD/kWh; no simple payback; no discounted payback) is the only arithmetic published on this page. Any capex-, tariff- or revenue-variation scenario is qualitative; the underlying cash-flow annual table is the sole computed numeric.

Bottom line: at current Australian benchmarks, a stand-alone 6 MWh / 6 MW BESS at a steel plant does not clear a pure-financial hurdle over a 15-year horizon at a 7.00 % real discount rate. The case should be justified by operational benefits (power-quality, demand-charge certainty, spill avoidance) and then stress-tested against the COMPUTED TABLES.

9. Call to action

Request a formal RFQ for the 6 MWh steel-plant BESS configuration (CATL EnerC Plus + Sungrow SC2752UX / SG3150/4400UD-MV + EVE LF280K V2.3).

Evidence pack re-checked 2026-09-22 against the COMPUTED TABLES and the cited public sources. No internal-review markup is published with this page.