UK Bakery Chain — 500 kWh ESS TCO Use Case

Verdict (computed base case, 10-year horizon, 8.00% discount rate, GBP): NPV = −£212,383.51; simple payback = none within 10 years; discounted payback = none within 10 years; LCOS = £0.4072/kWh. Equipment reference: CATL LFP 280 Ah prismatic cells housed in a Sungrow ST2752UX commercial liquid-cooled cabinet with Huawei Smart PCS reference architecture. Location: United Kingdom (GB distribution network, half-hourly settlement). Evidence date: model run 2024-12 on 2024-Q4 inputs. Limitation: this page presents the scenario TCO only; no UKCA / CE certificate, no UN 38.3 test summary, and no IEC / BS EN certificate of conformity is presented here — none should be inferred from this page.

Decision Table

QuestionAnswer
Headline NPV (computed)−£212,383.51 at 8.00% over 10 years
Simple payback (10-yr horizon)None — cumulative net cash flow is negative in every modelled year
Discounted payback (10-yr horizon)None — discounted cumulative net is negative in every modelled year
Levelised cost of storage£0.4072 / kWh discharged over 10 years (computed)
Total undiscounted cost vs benefitCosts £373,072.63 vs benefits £190,265.07 — net cash shortfall £182,807.56 over the horizon
PV of costs vs PV of benefitsPV(costs) £341,677.38 vs PV(benefits) £129,293.86 — net −£212,383.51
RecommendationDo not proceed on this scenario as-stated. Re-spec to a lower Capex band, secure a higher demand-charge saving per kW, or extend the horizon beyond 10 years. Confirm duty rates, grid charges, and balancing-services stacking revenue with a customs broker, your DNO, and your supplier before procurement.
Disclaimer: All financial figures on this page are outputs of our scenario TCO model run on the inputs declared in §3. They are computed for this scenario only. Energy and demand tariffs vary by region, half-hour settlement period, and supplier contract. No certificate, accreditation, or third-party attestation is presented on this page.

1. Equipment Reference (real, publicly marketed models)

SubsystemModel / family (real, public)Public datasheet / product page
Battery cellsCATL LFP 280 Ah prismatic cell (LFP-280 family for ESS)CATL energy storage landing page (cell-level datasheet distributed under NDA; public product index confirms 280 Ah LFP cell family for ESS)
Battery cabinetSungrow ST2752UX (commercial / industrial C&I liquid-cooled container; 2,752 kWh / 1500 V DC; pairs with SG3150/4400UD-MV inverter)Sungrow ST2752UX product page
Power conversion (reference architecture)Huawei Smart PCS family (FusionSolar commercial generator / Smart PCS product line)Huawei Digital Power official about page
EMS / controllerSungrow iSolarCloud / ComBox monitoring & control (bundled with ST2752UX)Sungrow corporate landing page

Equipment naming above identifies the publicly marketed product family only. This page does NOT present any UKCA certificate, CE Declaration of Conformity, UN 38.3 test summary, IEC 62619 / IEC 63056 CB certificate, or BS EN 50549 / G99 type-test certificate. Any limits on torque, state-of-charge window, voltage range, or round-trip efficiency used below must be confirmed against the OEM installation and operation manual revision supplied with the specific serial-numbered unit at delivery.

2. Scope & Approach

Scenario: a 500 kWh usable / 250 kW commercial LFP battery energy storage system (BESS) deployed at a UK bakery chain to clip morning oven-driven peak demand and to enable a limited amount of load shifting on tariff differential. The model treats one daily equivalent cycle with weekend and seasonal derating (≈ 300 cycles/yr), 90% depth-of-discharge (model assumption), 88% round-trip efficiency, a 10-year horizon, and an 8.00% real discount rate. All figures are in GBP, undiscounted unless stated. The financial figures in §4 and §5 are copied verbatim from the scenario model output; the prose around them is descriptive only.

3. Inputs Table (named, bounded)

InputSymbolValueUnitSource / status
Usable capacityE500kWhProject brief (assumption, no external citation)
Round-trip efficiencyη0.88—Project assumption bounded by LFP commercial cabinet range; confirm against OEM manual revision for the specific cabinet delivered
Depth of dischargeDoD0.90—Project assumption bounded by typical LFP commercial SoC window; confirm against OEM manual
Cycles per yearC300cycles/yr≈ 1 daily equivalent with weekend / seasonal derating (assumption)
Capex turnkeyCx280,000.00GBPProject assumption; public 2024 commercial-cabinet LFP turnkey benchmarks reported by BloombergNEF Battery Price Survey 2024 (range £420–£560/kWh for utility-scale turnkey; commercial-cabinet turnkey typically lower). Working value £280,000 = £560/kWh on the 500 kWh base as a conservative capex ceiling — this is a model assumption, not a sourced figure.
Annual fixed Opex (Year 1)Ox,18,500.00GBP/yrProject assumption: ~3.0% of Capex. Escalated at 2.0%/yr (assumption, no external citation)
Demand charged65.00GBP/kW/yrMidpoint of a published demand range; provenance: UK supplier half-hourly demand tariffs typically £45–£85/kW/yr across regions and contract terms (model assumption). Confirm with the buyer's supplier quote.
Energy tariff (import)p0.245GBP/kWhMidpoint of a published small C&I import range 21–28 p/kWh (model assumption). Confirm with the buyer's supplier quote.
Peak reductionPr150kWProject assumption (no external citation): ~60% of the 250 kW inverter rating clipped against the morning oven peak
High-rate share of energy displacedf0.60—Project assumption (no external citation): bakery ovens run predominantly at morning peak
Degradation per yearδ2.0%/yr of nameplate usable energyModel assumption, bounded by typical LFP commercial cabinet ageing; confirm against OEM warranty curve for the specific cabinet
Residual valueRV0.00GBP at year 10Model assumption: zero terminal salvage at year 10 (assumption, no external citation)
Residual value yearRVyr10yearModel assumption (assumption, no external citation)
Value per kWh dischargedv0.245GBP/kWhModel assumption: equals import tariff p (no external citation)
Charge cost per kWhcc0.000GBP/kWhModel default (bounded assumption): grid-charge energy cost is netted out via import-tariff equivalence v=p; explicit bounded default = 0.000 GBP/kWh so that energy benefit = v × discharged, not v × (charged+discharged).
Project lifetimeN10yearsProject assumption bounded by typical commercial LFP warranty horizon (10 yr / 6,000 cycles); confirm with OEM warranty document
Discount rater0.0800—Project assumption (no external citation): typical UK commercial hurdle rate range 7–9%

3.1 Capex benchmark note

BloombergNEF 2024 commercial LFP turnkey benchmark range: £420–£560/kWh. Midpoint = £490/kWh. Because no public source for a small commercial-cabinet turnkey band was found, the model uses £280,000 (£560/kWh applied to the 500 kWh base) as a conservative capex ceiling; this is a model assumption, not a sourced figure. Buyers should request a fixed quote from a named supplier.

3.2 Demand midpoint of range

Working demand range: £45–£85/kW/yr. Midpoint = (45 + 85)/2 = £65/kW/yr. Used directly as d = 65. Unit provenance: GBP per kW of half-hourly metered maximum demand per year.

3.3 Energy midpoint of range

Working energy range: 21–28 p/kWh. Midpoint = (21 + 28)/2 = 24.5 p/kWh = £0.245/kWh. Used directly as p = 0.245.

4. TCO Summary (computed, copy verbatim)

TCO summary
MetricValue
CurrencyGBP
Horizon (years)10
Discount rate8.00 %
Total undiscounted cost (GBP)373,072.63
Total discounted cost / PV of costs (GBP)341,677.38
Total undiscounted benefit (GBP)190,265.07
Total discounted benefit (GBP)129,293.86
NPV (GBP)-212,383.51
IRR-0.1678
Simple payback (year)—
Discounted payback (year)—
LCOS (GBP/kWh)0.4072

5. Year-by-Year Cash Flow (computed, copy verbatim)

Year-by-year cash flow
YearCost (GBP)Benefit (GBP)Net (GBP)Discount factorDiscounted net (GBP)Energy (kWh)
0280,000.000.0000-280,000.001.00-280,000.000.0000
18,500.0020,802.2712,302.270.925911,390.99135,000.00
28,670.0020,386.2311,716.230.857310,044.78132,300.00
38,843.4019,978.5011,135.100.79388,839.40129,654.00
49,020.2719,578.9310,558.660.73507,760.93127,060.92
59,200.6719,187.359,986.680.68066,796.77124,519.70
69,384.6918,803.619,418.920.63025,935.52122,029.31
79,572.3818,427.538,855.150.58355,166.90119,588.72
89,763.8318,058.988,295.160.54034,481.61117,196.95
99,959.1017,697.807,738.700.50023,871.28114,853.01
1010,158.2917,343.857,185.560.46323,328.31112,555.95

Scenario model convention: "Cost" = positive cash outflow in the year (Capex at Year 0, Opex at Year 1+); "Benefit" = positive cash inflow (avoided energy and demand costs). "Net" = Benefit − Cost (positive = net cash inflow). "Discount factor" = 1/(1+r)t with r = 0.08. "Energy" = modelled kWh discharged in the year, net of degradation applied to the dischargeable energy base.

5.1 Reading the table

6. Sensitivity (formula-based, indicative)

Sensitivity is recomputed by holding the formula TCO = Capex + Σ Opext/(1+r)t − Σ (Benefitt)/(1+r)t constant and varying Capex, cycles C, and tariff p. Where the computed sensitivity row in the model differs from a hand-derivation of the same inputs (e.g. because degradation is honoured in the model but not in the simple formula), the computed row is the computed number for this page.

ScenarioCapex (GBP)Opex (GBP/yr)Tariff p (GBP/kWh)Cycles C (per yr)TCO_nom 10y — simple formula (GBP)TCO_nom 10y — scenario model (GBP)
S0 Base280,0008,500 (escalated 2%/yr)0.245300212,384 (NPV reference)−212,384 (NPV; net of benefits)
S1 Tariff −20%280,0008,5000.196300not modelled on this pagenot modelled on this page
S2 Tariff +20%280,0008,5000.294300not modelled on this pagenot modelled on this page
S3 Cycles −20%280,0008,5000.245240not modelled on this pagenot modelled on this page
S4 Cycles +20%280,0008,5000.245360not modelled on this pagenot modelled on this page
S5 Capex −20%224,0008,5000.245300not modelled on this pagenot modelled on this page
S6 Capex +20%336,0008,5000.245300not modelled on this pagenot modelled on this page
S7 Worst stack (tariff −, cycles −, capex +)336,0008,5000.196240199,310 (simple, with trace below)not modelled on this page
S8 Best stack (tariff +, cycles +, capex −)224,0008,5000.294360−67,920 (simple, with trace below)not modelled on this page

6.1 S7 recomputation trace (~£199,310)

S_e = 500 × 240 × 0.88 × 0.60 × 0.196 = 12,418.944 GBP/yr. S_d = 9,750 GBP/yr. S = 22,168.944 GBP/yr. Total Savings 10 yr (simple, no escalation) = 221,689.44 GBP. TCO_nom (simple) = 336,000 + 85,000 − 221,689.44 = 199,310.56 ≈ £199,310.

6.2 S8 recomputation trace (~−£67,920)

S_e = 500 × 360 × 0.88 × 0.60 × 0.294 = 27,941.76 GBP/yr. S_d = 9,750 GBP/yr. S = 37,691.76 GBP/yr. Total Savings 10 yr (simple) = 376,917.60 GBP. TCO_nom (simple) = 224,000 + 85,000 − 376,917.60 = −67,917.60 ≈ −£67,920. (Negative TCO_nom = net positive cash position.)

7. HS / Commodity Code Lookup

PENDING formal duty-rate confirmation. Indicative classification only. Rates below are NOT YET VERIFIED. Confirm with the official UK Trade Tariff look-up before any customs declaration.
Commodity code (UK Global Tariff)Description (working)UK duty rateStatus / lookup source
8504.40.00.00Static converters (power converters / PCS for batteries)PENDINGUK Trade Tariff — 8504 40 00 00
8507.60.00.00Lithium-ion accumulators (cells and modules)PENDINGUK Trade Tariff — 8507 60 00 00
8537.10.00.00Boards, panels, consoles for electric control (BESS control unit)PENDINGUK Trade Tariff — 8537 10 00 00

Cross-check guidance: the UK Global Tariff replaced the EU CET on 1 Jan 2021; EU rates are not computed for GB import declarations. Use the UK Trade Tariff look-up (commodity code → "UK import duties" tab → "measures") and the UK Trade Tariff Volume 3 for binding interpretative notes. For EU export side, consult the EU TARIC consultation. For origin and preferential treatment consult the gov.uk rules of origin guidance. For air transport of lithium cells, consult ICAO Dangerous Goods and IATA DGR.

8. Compliance Touchpoints (no certificate presented on this page)

No certificate, declaration of conformity, test summary, or attestation is presented on this page. Items below are required compliance touchpoints for a GB-deployed C&I LFP BESS. Each must be sourced from the OEM or test house for the specific serial-numbered unit before procurement or commissioning.

9. CTAs

Request a single absolute RFQ

10. Allow-listed Source URLs cited on this page

11. Model Defaults (bounded assumptions, no external citation)

End of use case. computed figures in §4 and §5 are computed for this scenario; the sensitivity table in §6 shows S7 and S8 recomputation traces on the simple formula and notes that computed S1–S6 sensitivities are not modelled on this page. The base-case NPV of −£212,383.51 means that on these declared inputs the project does not pay back within 10 years.