Verdict (computed base case, 10-year horizon, 8.00% discount rate, GBP): NPV = −£212,383.51; simple payback = none within 10 years; discounted payback = none within 10 years; LCOS = £0.4072/kWh. Equipment reference: CATL LFP 280 Ah prismatic cells housed in a Sungrow ST2752UX commercial liquid-cooled cabinet with Huawei Smart PCS reference architecture. Location: United Kingdom (GB distribution network, half-hourly settlement). Evidence date: model run 2024-12 on 2024-Q4 inputs. Limitation: this page presents the scenario TCO only; no UKCA / CE certificate, no UN 38.3 test summary, and no IEC / BS EN certificate of conformity is presented here — none should be inferred from this page.
| Question | Answer |
|---|---|
| Headline NPV (computed) | −£212,383.51 at 8.00% over 10 years |
| Simple payback (10-yr horizon) | None — cumulative net cash flow is negative in every modelled year |
| Discounted payback (10-yr horizon) | None — discounted cumulative net is negative in every modelled year |
| Levelised cost of storage | £0.4072 / kWh discharged over 10 years (computed) |
| Total undiscounted cost vs benefit | Costs £373,072.63 vs benefits £190,265.07 — net cash shortfall £182,807.56 over the horizon |
| PV of costs vs PV of benefits | PV(costs) £341,677.38 vs PV(benefits) £129,293.86 — net −£212,383.51 |
| Recommendation | Do not proceed on this scenario as-stated. Re-spec to a lower Capex band, secure a higher demand-charge saving per kW, or extend the horizon beyond 10 years. Confirm duty rates, grid charges, and balancing-services stacking revenue with a customs broker, your DNO, and your supplier before procurement. |
| Subsystem | Model / family (real, public) | Public datasheet / product page |
|---|---|---|
| Battery cells | CATL LFP 280 Ah prismatic cell (LFP-280 family for ESS) | CATL energy storage landing page (cell-level datasheet distributed under NDA; public product index confirms 280 Ah LFP cell family for ESS) |
| Battery cabinet | Sungrow ST2752UX (commercial / industrial C&I liquid-cooled container; 2,752 kWh / 1500 V DC; pairs with SG3150/4400UD-MV inverter) | Sungrow ST2752UX product page |
| Power conversion (reference architecture) | Huawei Smart PCS family (FusionSolar commercial generator / Smart PCS product line) | Huawei Digital Power official about page |
| EMS / controller | Sungrow iSolarCloud / ComBox monitoring & control (bundled with ST2752UX) | Sungrow corporate landing page |
Equipment naming above identifies the publicly marketed product family only. This page does NOT present any UKCA certificate, CE Declaration of Conformity, UN 38.3 test summary, IEC 62619 / IEC 63056 CB certificate, or BS EN 50549 / G99 type-test certificate. Any limits on torque, state-of-charge window, voltage range, or round-trip efficiency used below must be confirmed against the OEM installation and operation manual revision supplied with the specific serial-numbered unit at delivery.
Scenario: a 500 kWh usable / 250 kW commercial LFP battery energy storage system (BESS) deployed at a UK bakery chain to clip morning oven-driven peak demand and to enable a limited amount of load shifting on tariff differential. The model treats one daily equivalent cycle with weekend and seasonal derating (≈ 300 cycles/yr), 90% depth-of-discharge (model assumption), 88% round-trip efficiency, a 10-year horizon, and an 8.00% real discount rate. All figures are in GBP, undiscounted unless stated. The financial figures in §4 and §5 are copied verbatim from the scenario model output; the prose around them is descriptive only.
| Input | Symbol | Value | Unit | Source / status |
|---|---|---|---|---|
| Usable capacity | E | 500 | kWh | Project brief (assumption, no external citation) |
| Round-trip efficiency | η | 0.88 | — | Project assumption bounded by LFP commercial cabinet range; confirm against OEM manual revision for the specific cabinet delivered |
| Depth of discharge | DoD | 0.90 | — | Project assumption bounded by typical LFP commercial SoC window; confirm against OEM manual |
| Cycles per year | C | 300 | cycles/yr | ≈ 1 daily equivalent with weekend / seasonal derating (assumption) |
| Capex turnkey | Cx | 280,000.00 | GBP | Project assumption; public 2024 commercial-cabinet LFP turnkey benchmarks reported by BloombergNEF Battery Price Survey 2024 (range £420–£560/kWh for utility-scale turnkey; commercial-cabinet turnkey typically lower). Working value £280,000 = £560/kWh on the 500 kWh base as a conservative capex ceiling — this is a model assumption, not a sourced figure. |
| Annual fixed Opex (Year 1) | Ox,1 | 8,500.00 | GBP/yr | Project assumption: ~3.0% of Capex. Escalated at 2.0%/yr (assumption, no external citation) |
| Demand charge | d | 65.00 | GBP/kW/yr | Midpoint of a published demand range; provenance: UK supplier half-hourly demand tariffs typically £45–£85/kW/yr across regions and contract terms (model assumption). Confirm with the buyer's supplier quote. |
| Energy tariff (import) | p | 0.245 | GBP/kWh | Midpoint of a published small C&I import range 21–28 p/kWh (model assumption). Confirm with the buyer's supplier quote. |
| Peak reduction | Pr | 150 | kW | Project assumption (no external citation): ~60% of the 250 kW inverter rating clipped against the morning oven peak |
| High-rate share of energy displaced | f | 0.60 | — | Project assumption (no external citation): bakery ovens run predominantly at morning peak |
| Degradation per year | δ | 2.0 | %/yr of nameplate usable energy | Model assumption, bounded by typical LFP commercial cabinet ageing; confirm against OEM warranty curve for the specific cabinet |
| Residual value | RV | 0.00 | GBP at year 10 | Model assumption: zero terminal salvage at year 10 (assumption, no external citation) |
| Residual value year | RVyr | 10 | year | Model assumption (assumption, no external citation) |
| Value per kWh discharged | v | 0.245 | GBP/kWh | Model assumption: equals import tariff p (no external citation) |
| Charge cost per kWh | cc | 0.000 | GBP/kWh | Model default (bounded assumption): grid-charge energy cost is netted out via import-tariff equivalence v=p; explicit bounded default = 0.000 GBP/kWh so that energy benefit = v × discharged, not v × (charged+discharged). |
| Project lifetime | N | 10 | years | Project assumption bounded by typical commercial LFP warranty horizon (10 yr / 6,000 cycles); confirm with OEM warranty document |
| Discount rate | r | 0.0800 | — | Project assumption (no external citation): typical UK commercial hurdle rate range 7–9% |
BloombergNEF 2024 commercial LFP turnkey benchmark range: £420–£560/kWh. Midpoint = £490/kWh. Because no public source for a small commercial-cabinet turnkey band was found, the model uses £280,000 (£560/kWh applied to the 500 kWh base) as a conservative capex ceiling; this is a model assumption, not a sourced figure. Buyers should request a fixed quote from a named supplier.
Working demand range: £45–£85/kW/yr. Midpoint = (45 + 85)/2 = £65/kW/yr. Used directly as d = 65. Unit provenance: GBP per kW of half-hourly metered maximum demand per year.
Working energy range: 21–28 p/kWh. Midpoint = (21 + 28)/2 = 24.5 p/kWh = £0.245/kWh. Used directly as p = 0.245.
| Metric | Value |
|---|---|
| Currency | GBP |
| Horizon (years) | 10 |
| Discount rate | 8.00 % |
| Total undiscounted cost (GBP) | 373,072.63 |
| Total discounted cost / PV of costs (GBP) | 341,677.38 |
| Total undiscounted benefit (GBP) | 190,265.07 |
| Total discounted benefit (GBP) | 129,293.86 |
| NPV (GBP) | -212,383.51 |
| IRR | -0.1678 |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| LCOS (GBP/kWh) | 0.4072 |
| Year | Cost (GBP) | Benefit (GBP) | Net (GBP) | Discount factor | Discounted net (GBP) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 280,000.00 | 0.0000 | -280,000.00 | 1.00 | -280,000.00 | 0.0000 |
| 1 | 8,500.00 | 20,802.27 | 12,302.27 | 0.9259 | 11,390.99 | 135,000.00 |
| 2 | 8,670.00 | 20,386.23 | 11,716.23 | 0.8573 | 10,044.78 | 132,300.00 |
| 3 | 8,843.40 | 19,978.50 | 11,135.10 | 0.7938 | 8,839.40 | 129,654.00 |
| 4 | 9,020.27 | 19,578.93 | 10,558.66 | 0.7350 | 7,760.93 | 127,060.92 |
| 5 | 9,200.67 | 19,187.35 | 9,986.68 | 0.6806 | 6,796.77 | 124,519.70 |
| 6 | 9,384.69 | 18,803.61 | 9,418.92 | 0.6302 | 5,935.52 | 122,029.31 |
| 7 | 9,572.38 | 18,427.53 | 8,855.15 | 0.5835 | 5,166.90 | 119,588.72 |
| 8 | 9,763.83 | 18,058.98 | 8,295.16 | 0.5403 | 4,481.61 | 117,196.95 |
| 9 | 9,959.10 | 17,697.80 | 7,738.70 | 0.5002 | 3,871.28 | 114,853.01 |
| 10 | 10,158.29 | 17,343.85 | 7,185.56 | 0.4632 | 3,328.31 | 112,555.95 |
Scenario model convention: "Cost" = positive cash outflow in the year (Capex at Year 0, Opex at Year 1+); "Benefit" = positive cash inflow (avoided energy and demand costs). "Net" = Benefit − Cost (positive = net cash inflow). "Discount factor" = 1/(1+r)t with r = 0.08. "Energy" = modelled kWh discharged in the year, net of degradation applied to the dischargeable energy base.
Sensitivity is recomputed by holding the formula TCO = Capex + Σ Opext/(1+r)t − Σ (Benefitt)/(1+r)t constant and varying Capex, cycles C, and tariff p. Where the computed sensitivity row in the model differs from a hand-derivation of the same inputs (e.g. because degradation is honoured in the model but not in the simple formula), the computed row is the computed number for this page.
| Scenario | Capex (GBP) | Opex (GBP/yr) | Tariff p (GBP/kWh) | Cycles C (per yr) | TCO_nom 10y — simple formula (GBP) | TCO_nom 10y — scenario model (GBP) |
|---|---|---|---|---|---|---|
| S0 Base | 280,000 | 8,500 (escalated 2%/yr) | 0.245 | 300 | 212,384 (NPV reference) | −212,384 (NPV; net of benefits) |
| S1 Tariff −20% | 280,000 | 8,500 | 0.196 | 300 | not modelled on this page | not modelled on this page |
| S2 Tariff +20% | 280,000 | 8,500 | 0.294 | 300 | not modelled on this page | not modelled on this page |
| S3 Cycles −20% | 280,000 | 8,500 | 0.245 | 240 | not modelled on this page | not modelled on this page |
| S4 Cycles +20% | 280,000 | 8,500 | 0.245 | 360 | not modelled on this page | not modelled on this page |
| S5 Capex −20% | 224,000 | 8,500 | 0.245 | 300 | not modelled on this page | not modelled on this page |
| S6 Capex +20% | 336,000 | 8,500 | 0.245 | 300 | not modelled on this page | not modelled on this page |
| S7 Worst stack (tariff −, cycles −, capex +) | 336,000 | 8,500 | 0.196 | 240 | 199,310 (simple, with trace below) | not modelled on this page |
| S8 Best stack (tariff +, cycles +, capex −) | 224,000 | 8,500 | 0.294 | 360 | −67,920 (simple, with trace below) | not modelled on this page |
S_e = 500 × 240 × 0.88 × 0.60 × 0.196 = 12,418.944 GBP/yr. S_d = 9,750 GBP/yr. S = 22,168.944 GBP/yr. Total Savings 10 yr (simple, no escalation) = 221,689.44 GBP. TCO_nom (simple) = 336,000 + 85,000 − 221,689.44 = 199,310.56 ≈ £199,310.
S_e = 500 × 360 × 0.88 × 0.60 × 0.294 = 27,941.76 GBP/yr. S_d = 9,750 GBP/yr. S = 37,691.76 GBP/yr. Total Savings 10 yr (simple) = 376,917.60 GBP. TCO_nom (simple) = 224,000 + 85,000 − 376,917.60 = −67,917.60 ≈ −£67,920. (Negative TCO_nom = net positive cash position.)
| Commodity code (UK Global Tariff) | Description (working) | UK duty rate | Status / lookup source |
|---|---|---|---|
| 8504.40.00.00 | Static converters (power converters / PCS for batteries) | PENDING | UK Trade Tariff — 8504 40 00 00 |
| 8507.60.00.00 | Lithium-ion accumulators (cells and modules) | PENDING | UK Trade Tariff — 8507 60 00 00 |
| 8537.10.00.00 | Boards, panels, consoles for electric control (BESS control unit) | PENDING | UK Trade Tariff — 8537 10 00 00 |
Cross-check guidance: the UK Global Tariff replaced the EU CET on 1 Jan 2021; EU rates are not computed for GB import declarations. Use the UK Trade Tariff look-up (commodity code → "UK import duties" tab → "measures") and the UK Trade Tariff Volume 3 for binding interpretative notes. For EU export side, consult the EU TARIC consultation. For origin and preferential treatment consult the gov.uk rules of origin guidance. For air transport of lithium cells, consult ICAO Dangerous Goods and IATA DGR.
End of use case. computed figures in §4 and §5 are computed for this scenario; the sensitivity table in §6 shows S7 and S8 recomputation traces on the simple formula and notes that computed S1–S6 sensitivities are not modelled on this page. The base-case NPV of −£212,383.51 means that on these declared inputs the project does not pay back within 10 years.