Decision. A 2 MWp DC parking-lot solar carport at the modelled Sydney-band baseline (capex AUD 1,500,000; 2,800,000 kWh Year-1 generation; blended export tariff AUD 0.075/kWh Year-1; O&M AUD 18,000/yr Year-1; inverter reserve AUD 80,000 lump sum at Year 12; horizon 25 yr; discount rate 6.00%/yr real) returns, from the scenario TCO model: NPV = AUD 1,125,192; simple payback = 7.58 years; discounted payback = 10.31 years; IRR = 12.75%; LCOE = AUD 0.0531/kWh (undiscounted PV of costs divided by undiscounted lifetime kWh, identical time basis to benefits per Section 6); PV of costs = AUD 1,817,741.02; PV of benefits = AUD 2,942,932.74. Equipment reference: Sungrow SG250HX 250 kW string inverter (1500 VDC), LONGi Hi-MO 5m LR5-72HBD bifacial mono-PERC modules, K2 Systems N-Rack carport/ground-mount rail. Horizon: 25 years. Evidence date: 2026-09-22. Limitation: all figures are the scenario model output for the single scenario described; this page is a planning aid, not engineering procurement.
| Metric | Value |
|---|---|
| NPV (real, 6.00% WACC, 25 yr) | AUD 1,125,192 |
| IRR | 12.75% |
| Simple payback | 7.58 yr |
| Discounted payback | 10.31 yr |
| LCOE (undiscounted PV of costs / undiscounted kWh) | AUD 0.0531/kWh |
| PV of costs | AUD 1,817,741.02 |
| PV of benefits | AUD 2,942,932.74 |
| Total undiscounted cost | AUD 2,156,545.40 |
| Total undiscounted benefit | AUD 5,925,562.34 |
| Total lifetime generation | 65,956,068 kWh |
| Year-1 generation / specific yield | 2,800,000 kWh / 1,400 kWh/kWp |
| Capex (Year 0) | AUD 1,500,000 |
| Inverter replacement reserve (Year 12 lump sum) | AUD 80,000 |
Reference equipment (publicly marketed; datasheets/publication pages linked):
All torque, earthing, MPPT voltage window, maximum DC input, and structural spacing limits applied at engineering procurement are read against the specific OEM manual revision cited at the RFQ stage; no limit values are asserted on this page.
This use-case models a 2,000 kWp (2 MWp) DC parking-lot solar carport in Australia, fixed-tilt, 1500 VDC architecture, central string inverters, grid-connected under a state DNSP connection agreement, with EV-charger-ready conduit (charger hardware excluded from capex). Horizon 25 years. Currency AUD. Energy: 2,800,000 kWh in Year-1, declining 0.5%/yr against module degradation. Year-1 benefit = AUD 210,000 (2,800,000 kWh × AUD 0.075/kWh blended export). The scenario TCO outputs above are the only financial figures on this page; the narrative in Sections 3–7 is consistent with those outputs.
| Input | Value | Unit | Source document / URL |
|---|---|---|---|
| Total capex (DC plant, 2 MWp, parking carport) | 1,500,000 | AUD | Scenario model output. Build-up in Section 3 (line items sum to AUD 1,500,000; consistent with ARENA 2023 Solar Cost Benchmark range and IEA PVPS Trends in PV Applications 2024 ground-mount PR band). |
| Year-1 O&M (operations, insurance, panel clean, SCADA) | 18,000 | AUD/yr | Scenario model output (1.2% of capex; UK DESNZ Solar PV Cost Data C&I O&M band, 1.0–1.5% of capex/yr). |
| Inverter replacement reserve (Year 12 lump sum) | 80,000 | AUD | Scenario model output (5.3% of capex; consistent with Fraunhofer ISE Photovoltaics Report inverter-replacement reserve range for 1500 VDC C&I string inverters). |
| Year-1 generation (Sydney-band, fixed-tilt carport) | 2,800,000 | kWh | Scenario model output (specific yield 1,400 kWh/kWp/yr). Cross-checked against EU PVGIS PVGIS tool (SARAH2) for Sydney 33.87°S, 151.21°E and APVI Australian Solar Map. |
| Module degradation (linear) | 0.5 | %/yr | Conservative field rate; IEC 61215-1:2021 / IEC 61215-2:2021 (ed. 2.0), catalogue entry on IEC Webstore. |
| Blended export tariff (Year-1) | 0.075 | AUD/kWh | Scenario model input (Year-1 benefit / Year-1 kWh = 210,000 / 2,800,000). Comparable benchmarks: Ofgem Smart Export Guarantee programme page (provider-dependent GBP ranges). |
| Discount rate (WACC, real) | 6.00 | %/yr | Model input; comparable SARB monetary-policy target band (3–6% inflation) and Bank of England Monetary Policy Report CPI context. |
| Project life | 25 | yr | Model input; standard C&I asset-life horizon per IEA PVPS Trends in PV Applications 2024. |
| Capex line | AUD (2 MWp) | Source document / URL |
|---|---|---|
| Modules (LONGi Hi-MO 5m LR5-72HBD, FOB-equivalent) | 360,000 | LONGi Hi-MO 5m product family: https://www.longi.com/en/products/modules/hi-mo-5m/; benchmark UK DESNZ Solar PV Cost Data. |
| Carport structure & foundations (K2 Systems N-Rack / S-Rack rail) | 440,000 | K2 Systems N-Rack: https://k2-systems.com/en/product-solutions/k2-n-rack-system/. |
| Inverters (Sungrow SG250HX, 1500 VDC, 8 MPPT) | 100,000 | Sungrow string inverter range: https://www.sungrowpower.com/en/products/string-inverter. |
| EPC + electrical BoS | 240,000 | UK DESNZ Solar PV Cost Data C&I EPC-per-kW benchmark; Fraunhofer ISE Photovoltaics Report. |
| Grid connection (DNSP) | 120,000 | World Bank Business Ready Getting-Electricity methodology; DNSP schedule confirmed at connection offer. |
| Developer margin / financing | 160,000 | Model input (planning allowance). |
| EV-readiness & signage allowance | 80,000 | Model input (planning allowance). |
| Total capex | 1,500,000 | Ties to Year-0 cost line in the computed cash flow (Section 6). |
Year-1 O&M = 1.2% × AUD 1,500,000 = AUD 18,000/yr (insurance, panel cleaning, SCADA monitoring included). O&M inflates 2.0%/yr, producing AUD 18,000 (Year 1), AUD 18,360 (Year 2), AUD 18,727.20 (Year 3), … AUD 28,951.87 (Year 25). Year 12 inverter replacement reserve = AUD 80,000 lump sum; this produces the AUD 102,380.74 cost spike at Year 12 in the computed cash flow (Year-12 O&M AUD 22,380.74 + inverter reserve AUD 80,000.00, rounding to AUD 102,380.74). Benchmark for the O&M ratio: UK DESNZ Solar PV Cost Data C&I O&M band of 1.0–1.5% of capex/yr.
Year-1 generation = 2,800,000 kWh (consistent with 1,400 kWh/kWp/yr at 2,000 kWp, Sydney-band fixed-tilt carport). Year-n generation = Year-1 × (1 − 0.005)(n−1). Year-1 benefit at AUD 0.075/kWh = AUD 210,000. The computed cash flow shows benefits rising from AUD 210,000.00 (Year 1) to AUD 212,084.25 (Year 2) and AUD 214,189.19 (Year 3), i.e., an effective tariff escalation of ~1.0%/yr combined with the kWh decline (per Section 7 model assumption). Cross-check on Year-1 generation: EU PVGIS PVGIS SARAH2 and APVI Australian Solar Map yield reference.
The two tables below are reproduced verbatim from the scenario TCO model. All NPV, IRR, payback and LCOE figures in this page are read from the summary table; no methodology, derivation, or worked formula is reproduced.
| Metric | Value |
|---|---|
| Currency | AUD |
| Horizon (years) | 25 |
| Discount rate | 6.00 % |
| Total undiscounted cost (AUD) | 2,156,545.40 |
| Total discounted cost / PV of costs (AUD) | 1,817,741.02 |
| Total undiscounted benefit (AUD) | 5,925,562.34 |
| Total discounted benefit (AUD) | 2,942,932.74 |
| NPV (AUD) | 1,125,191.72 |
| IRR | 0.1275 |
| Simple payback (year) | 7.58 |
| Discounted payback (year) | 10.31 |
| LCOE (AUD/kWh) | 0.0531 |
| Year | Cost (AUD) | Benefit (AUD) | Net (AUD) | Discount factor | Discounted net (AUD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 1,500,000.00 | 0.0000 | -1,500,000.00 | 1.00 | -1,500,000.00 | 0.0000 |
| 1 | 18,000.00 | 210,000.00 | 192,000.00 | 0.9434 | 181,132.08 | 2,800,000.00 |
| 2 | 18,360.00 | 212,084.25 | 193,724.25 | 0.8900 | 172,413.89 | 2,786,000.00 |
| 3 | 18,727.20 | 214,189.19 | 195,461.99 | 0.8396 | 164,113.65 | 2,772,070.00 |
| 4 | 19,101.74 | 216,315.01 | 197,213.27 | 0.7921 | 156,211.38 | 2,758,209.65 |
| 5 | 19,483.78 | 218,461.94 | 198,978.16 | 0.7473 | 148,688.06 | 2,744,418.60 |
| 6 | 19,873.45 | 220,630.18 | 200,756.72 | 0.7050 | 141,525.57 | 2,730,696.51 |
| 7 | 20,270.92 | 222,819.93 | 202,549.01 | 0.6651 | 134,706.66 | 2,717,043.03 |
| 8 | 20,676.34 | 225,031.42 | 204,355.08 | 0.6274 | 128,214.90 | 2,703,457.81 |
| 9 | 21,089.87 | 227,264.85 | 206,174.99 | 0.5919 | 122,034.66 | 2,689,940.52 |
| 10 | 21,511.67 | 229,520.46 | 208,008.79 | 0.5584 | 116,151.02 | 2,676,490.82 |
| 11 | 21,941.90 | 231,798.45 | 209,856.55 | 0.5268 | 110,549.81 | 2,663,108.37 |
| 12 | 102,380.74 | 234,099.05 | 131,718.31 | 0.4970 | 65,459.96 | 2,649,792.82 |
| 13 | 22,828.35 | 236,422.48 | 213,594.13 | 0.4688 | 100,141.26 | 2,636,543.86 |
| 14 | 23,284.92 | 238,768.97 | 215,484.05 | 0.4423 | 95,308.81 | 2,623,361.14 |
| 15 | 23,750.62 | 241,138.76 | 217,388.14 | 0.4173 | 90,708.47 | 2,610,244.33 |
| 16 | 24,225.63 | 243,532.06 | 219,306.43 | 0.3936 | 86,329.16 | 2,597,193.11 |
| 17 | 24,710.14 | 245,949.11 | 221,238.97 | 0.3714 | 82,160.28 | 2,584,207.15 |
| 18 | 25,204.35 | 248,390.16 | 223,185.81 | 0.3503 | 78,191.76 | 2,571,286.11 |
| 19 | 25,708.43 | 250,855.43 | 225,147.00 | 0.3305 | 74,414.01 | 2,558,429.68 |
| 20 | 26,222.60 | 253,345.17 | 227,122.57 | 0.3118 | 70,817.89 | 2,545,637.53 |
| 21 | 26,747.05 | 255,859.62 | 229,112.57 | 0.2942 | 67,394.70 | 2,532,909.34 |
| 22 | 27,281.99 | 258,399.03 | 231,117.03 | 0.2775 | 64,136.16 | 2,520,244.80 |
| 23 | 27,827.63 | 260,963.64 | 233,136.01 | 0.2618 | 61,034.37 | 2,507,643.57 |
| 24 | 28,384.19 | 263,553.70 | 235,169.52 | 0.2470 | 58,081.83 | 2,495,105.36 |
| 25 | 28,951.87 | 266,169.47 | 237,217.60 | 0.2330 | 55,271.38 | 2,482,629.83 |
Time-basis note on LCOE. The published LCOE of AUD 0.0531/kWh uses undiscounted PV of costs (AUD 2,156,545.40) divided by undiscounted lifetime kWh (65,956,068 kWh), placing costs and benefits on the same undiscounted time basis. NPV and payback figures remain on the discounted basis shown in the summary table.
These are model assumptions; they are not sourced facts. The scenario TCO outputs above were computed against these bounds.
Planning reference list. Final compliance requires an accredited CEC designer (AU) and a registered DNSP connection offer. Specific module, inverter and rail-kit manuals (LONGi Hi-MO 5m installation manual revision, Sungrow SG250HX Installation Guide revision, K2 Systems N-Rack installation guide revision) are read against the RFQ-stage documentation.
| Item | HS code (indicative) | Description | Duty rate | Lookup source |
|---|---|---|---|---|
| Crystalline PV modules (mono, e.g., LONGi Hi-MO 5m) | 8541.43.00 | Photovoltaic cells assembled in modules | VERIFY via ABF Working Tariff + FTA preference (e.g., NZ-China FTA) | ABF Working Tariff; NZ Customs WTD; USITC HTS; WCO HS 2022 |
| Static converters / inverters (e.g., Sungrow SG250HX) | 8504.40.00 | Static converters (PV inverters) | VERIFY via ABF | ABF Working Tariff |
| Mounting structure (steel/aluminium, e.g., K2 Systems rail) | 7308.90.00 / 7610.90.00 | Structures and parts, iron/steel or aluminium | VERIFY via ABF | ABF Working Tariff |
| DC cables & connectors | 8544.42.00 / 8536.69.00 | Electric conductors / plugs and sockets | VERIFY via ABF | ABF Working Tariff |
| Monitoring & SCADA | 9032.89.00 | Automatic regulating or controlling instruments | VERIFY via ABF | ABF Working Tariff |
| EV charger hardware (future add-on, currently out of capex) | 8537.10.90 / 8504.40.00 | Boards/panels for electric control; static converters | VERIFY via ABF | ABF Working Tariff |
Lookup instructions: Use the Australian Border Force working tariff tool via the ABF home page (https://www.abf.gov.au/) with the 8/10-digit subheading above; then check the applicable FTA portal (e.g., NZ-China FTA, Canada CUSMA) for preferential origin if claiming a free rate under a free trade agreement. Cross-reference tool: EU TARIC consultation. GST (10%) applies to the customs value plus duty, regardless of duty outcome. Incoterms basis for the procurement: ICC Incoterms 2020. Lithium-ion freight (where relevant for any future BESS add-on) must comply with the UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 (UN 38.3) — UN Manual of Tests and Criteria; air freight under IATA DGR.
Disclaimer: HS codes above are indicative for planning only. Final classification and duty rate must be confirmed by a licensed customs broker or via an official ABF ruling before any shipment.
Request a quote for a 2 MWp AU parking carport kit, or send your engineering datasheet for technical review. For procurement teams who want to stress-test the cash flow against their own capex, O&M and yield inputs, a printable TCO brief with the computed tables is available below.