Import a 240 kW DC EVSE from China to Albania — Highway-Hub Use-Case & Total Cost of Ownership

Indicative verdict. For the bounded assumption set below, a single 240 kW DC EVSE hub imported from China to Albania and operated for a 10-year horizon at an 8.00 % discount rate yields NPV = USD 365,028, a discounted payback of 0.0 years, a simple payback of 0.0 years, an EV TCO of USD 0.080 / km vs ICE USD 0.316 / km (savings USD 0.236 / km; USD 944,000 over the horizon). Equipment scope: 240 kW DC fast charger (dual-CCS2), highway-hub deployment class. Location: Tirana–Durrës–border corridor, Albania. Horizon: 10 years. Evidence date: 2026-09-21. Limitation: figures are produced by the computed Tradvolt TCO model against the stated bounded default inputs (see §3); every CapEx, OpEx, fleet and energy assumption is a model assumption until replaced by live RFQ and DSO tariff data — the page is a planning scaffold, not a quote.

Decision table — at-a-glance

Decision leverValueUnitSource / status
Equipment class240 kW DC fast charger (dual-CCS2), Chinese OEM—Reference class — Sungrow IDC240E family as worked example; confirm SKU at RFQ
OEM (worked example)Sungrow Power Supply Co., Ltd. (legal entity); product family referenced: IDC180E / IDC240E-class public DC fast charger datasheet—OEM product page (see §5)
LocationAlbania — Tirana / Durrës highway corridor—Use-case assumption
Horizon10yearsModel assumption
Discount rate8.00%Model assumption
NPV365,028.43USDComputed (scenario TCO model)
Discounted payback0.0yearComputed — driven by zero-modelled CapEx/OpEx default
Simple payback0.0yearComputed — driven by zero-modelled CapEx/OpEx default
TCO per km — EV0.0800USD/kmComputed
TCO per km — ICE0.3160USD/kmComputed
Savings per km0.2360USD/kmComputed
Savings over horizon944,000.00USDComputed (undiscounted)
CurrencyUSD—Model default
Evidence date2026-09-21—Page compile date

Vertical: EVSE (DC fast charging) · Corridor: Tirana–Durrës–border highways · Audience: charge-point operators, fleet depots, concessionaires. Reference / planning document

1. Use-case brief — Highway-Hub 240 kW

The reference equipment class is a 240 kW DC fast charger supporting CCS2 at the upper end of the public-charging envelope. For long-range BEVs the typical 10–80 % SoC top-up window is 15–25 minutes; specific time depends on the vehicle's BMS voltage window, peak acceptance current, and battery temperature. On an Albanian highway hub (A1 / SH1 corridor or a service area near a border crossing), the use-case is short-dwell high-power sessions dominated by passenger BEVs in transit, with periodic light commercial and coach opportunities during off-peak windows.

Claim: 10–80 % SoC top-up in 15–25 minutes for a long-range BEV on a 240 kW DC charger is achievable under favourable battery temperature and pack state-of-health conditions; the window is vehicle- and condition-dependent.
Src: Sungrow IDC180E / IDC240E-class public DC fast charger datasheet — DC output voltage window and current envelope (worked-example OEM; confirm SKU at RFQ).
URL: https://en.sungrowpower.com/product/IDC180E (public product page; datasheet PDF linked from product page).
Accessed: 2026-09-21.

Decision factors for this deployment class:

2. Computed TCO summary (scenario model — verbatim)

Source of truth: All figures below are produced by the computed Tradvolt TCO model from the page's own scenario. They are computed and must not be hand-edited.
TCO summary
MetricValue
CurrencyUSD
Horizon (years)10
Discount rate8.00 %
Total undiscounted cost (USD)0.0000
Total discounted cost / PV of costs (USD)0.0000
Total undiscounted benefit (USD)544,000.00
Total discounted benefit (USD)365,028.43
NPV (USD)365,028.43
IRRn/a
Simple payback (year)0.0000
Discounted payback (year)0.0000
TCO per km — EV (USD/km)0.0800
TCO per km — ICE (USD/km)0.3160
Savings per km (USD/km)0.2360
Savings over horizon (USD)944,000.00

2.1 Year-by-year cash flow (verbatim)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
00.00000.00000.00001.000.00000.0000
10.000054,400.0054,400.000.925950,370.370.0000
20.000054,400.0054,400.000.857346,639.230.0000
30.000054,400.0054,400.000.793843,184.470.0000
40.000054,400.0054,400.000.735039,985.620.0000
50.000054,400.0054,400.000.680637,023.730.0000
60.000054,400.0054,400.000.630234,281.230.0000
70.000054,400.0054,400.000.583531,741.880.0000
80.000054,400.0054,400.000.540329,390.630.0000
90.000054,400.0054,400.000.500227,213.540.0000
100.000054,400.0054,400.000.463225,197.730.0000

3. Inputs — bounded model assumptions and sourced facts

Inputs the scenario model did not receive a value for are presented below as explicit bounded defaults. They are model assumptions, not sourced facts. Replace each one with a live RFQ/Derived value before any commercial decision.

InputBounded default (model assumption)UnitStatus
opex.fixed0.00USD/yearModel assumption — replace with annual fixed OpEx (lease, comms, SaaS, insurance, maintenance ex-energy)
residual_value.amount0.00USDModel assumption
residual_value.year10yearModel assumption (end of horizon)
capex[0].amount → capex[10].amount0.00 (each year 0–10)USDDROPPED-ITEM in current scenario — these line items are not populated by the computed run; total CapEx stream is therefore zero in the computed cash flow
asset.ev_fleet.vehiclesnot populatedcountModel assumption — set to site fleet size at RFQ
asset.ev_fleet.km_per_yearnot populatedkm/yrModel assumption — site study
asset.ev_fleet.kwh_per_kmnot populatedkWh/kmModel assumption — vehicle mix-weighted
asset.ev_fleet.electricity_per_kwhnot populatedUSD/kWh (or ALL/kWh)Model assumption — DSO tariff letter
asset.ev_fleet.diesel_l_per_kmnot populatedL/kmModel assumption — ICE comparator
asset.ev_fleet.diesel_per_lnot populatedUSD/L (or ALL/L)Model assumption
asset.ev_fleet.maint_ev_per_kmnot populatedUSD/kmModel assumption
asset.ev_fleet.maint_ice_per_kmnot populatedUSD/kmModel assumption
asset.ev_fleet.ice_capex_per_vehiclenot populatedUSD/vehicleModel assumption

The computed USD 54,400 annual benefit, the USD 365,028 NPV and the 0.0-year discounted payback are the direct consequence of the bounded default set (zero CapEx, zero OpEx, zero residual value, flat annual benefit stream). Any commercial use requires re-running the model with the populated inputs above.

4. CapEx / OpEx framework — what to populate before re-running the model

Status: Framework rows below are not yet populated in the computed run (DROPPED-ITEM). Populate each cell from the cited source and re-run the scenario TCO model to refresh §2.

4.1 CapEx line items (sourced where a public reference is named)

Line itemBasisUnitSource / status
Charger unit (240 kW DC, dual-CCS2) — Sungrow IDC240E family as worked-example SKUOEM FOB / EXW ChinaUSD / unitQuote-driven; reference public product page: https://en.sungrowpower.com/product/IDC180E (IDC180E / IDC240E-class; confirm SKU at RFQ)
Spare parts kit (filters, fuses, contactors)OEM bundleUSD / unitQuote-driven
Packaging & seaworthy cratingForwarderUSD / unitQuote-driven
Ocean freight CN → Port of DurrësFCL/LCL, 30–40 days transitUSD / unitQuote-driven — 30–40 day Shanghai/Shekou → Durrës transit window is a planning reference for Far East → Adriatic services on the Asia–Mediterranean trade lane; verify with forwarder scheduling
Marine insurance (ICC-A)~0.3–0.5 % of cargo valueUSD / unitQuote-driven — 0.3–0.5 % is a planning reference for ICC-A all-risk cargo cover on a single FCL of industrial electrical equipment; bindable rate is policy-specific
Customs clearance & broker (AL)Albanian Customs brokerUSD / shipmentQuote-driven
Inland transport Durrës → siteTirana / SH1 hubsUSD / unitQuote-driven
Site preparation (MV transformer, cabling, canopy, signage)Civil contractorUSD / siteQuote-driven
Installation, commissioning & grid syncOEM or local EPCUSD / siteQuote-driven
Network / OCPP back-office onboardingCPO platformUSD / unitQuote-driven
Duty + VAT (paid at import)Albanian Customs tariff lookup% of CIFSee §6

4.2 OpEx line items

Line itemUnitSource / status
Electricity (energy throughput × tariff)ALL / kWh or USD / kWhTariff-driven — DSO tariff letter
Demand / capacity chargeALL / kW / monthTariff-driven — DSO tariff letter
Site lease / concession feeALL / monthQuote-driven
Connectivity (4G/5G, OCPP)USD / monthQuote-driven
Preventive maintenance (annual OEM service)USD / yearQuote-driven
Spare-parts consumptionUSD / yearQuote-driven
Back-office / SaaS feeUSD / monthQuote-driven
Insurance (CAR/EAR + operational)USD / yearQuote-driven
Staff / remote operationsUSD / yearQuote-driven

5. Compliance & certifications

Compliance text below cites the specific international standard families plus the specific OEM product datasheet that operationalises them on the worked-example unit. The OEM's actual certificate number, issuer and validity must come from the certificate PDF shipped with the unit you procure; Tradvolt does not republish third-party certificates.

TopicStandard / frameworkDocument title + URLIssuer / portalStatus
EV conductive charging system (general)IEC 61851-1IEC 61851-1:2017 — Electric vehicle conductive charging system — Part 1: General requirements (webstore record) — https://webstore.iec.ch/publication/33644IECConfirm certificate number + issuer + validity on the OEM certificate PDF for the SKU procured
DC charging control / communicationIEC 61851-23 (DC)IEC 61851-23:2014 — Electric vehicle conductive charging system — Part 23: DC electric vehicle charging station — https://webstore.iec.ch/publication/6032IECConfirm certificate number + issuer + validity on OEM certificate PDF
DC charging connector (CCS2 / Combo 2)IEC 62196-3IEC 62196-3:2022 — Plugs, socket-outlets, vehicle connectors and vehicle inlets — Conductive charging of electric vehicles — Part 3: Dimensional compatibility and interchangeability requirements for DC and AC/DC pin type contact accessories — https://webstore.iec.ch/publication/65838IECConfirm certificate number + issuer + validity on OEM certificate PDF
Communication / Plug & ChargeISO 15118-1/-2/-3 (and -20 for V2G)ISO 15118-1:2019 — Road vehicles — Vehicle to grid communication interface — Part 1: General information and use-case definition — https://www.iso.org/standard/69113.html (record page for ISO 15118-1:2019)ISOOptional — confirm certificate number + issuer + validity on OEM certificate PDF if Plug & Charge is in scope
Back-office protocolOCPP 1.6 / OCPP 2.0.1Open Charge Alliance — OCPP 2.0.1 specification page (download record): https://www.openchargealliance.org/protocols/ocpp-201/ ; OCPP 1.6: https://www.openchargealliance.org/protocols/ocpp-16/Open Charge Alliance (OCA)Confirm certification listing on OCA product list and certificate number on OEM dossier
EMC (industrial)IEC 61000-6-2 / IEC 61000-6-4IEC 61000-6-2:2016 — Electromagnetic compatibility (EMC) — Part 6-2: Generic standards — Immunity for industrial environments — https://webstore.iec.ch/publication/25942 ; IEC 61000-6-4:2018 — Part 6-4: Emission standard for industrial environments — https://webstore.iec.ch/publication/61251IECConfirm test report number + issuer + validity on OEM certificate PDF
EU market access (only if re-exporting to EU/EEA)CE marking under applicable directives (e.g. Low Voltage 2014/35/EU, EMC 2014/30/EU, RED 2014/53/EU)EUR-Lex — Directive 2014/35/EU (Low Voltage): https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32014L0035 ; Directive 2014/30/EU (EMC): https://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:32014L0030European Commission (CE framework)Albania is not an EU member — confirm local conformity rules; CE is required only if re-exporting to the EU/EEA market
Safety (US/Canada market option)UL 2202 / UL 2231 (where applicable)UL Standards — UL 2202 (EV charging system equipment) and UL 2231 (personnel protection systems) record pages: https://www.shopulstandards.com/ProductDetail.aspx?productId=UL2202 ; https://www.shopulstandards.com/ProductDetail.aspx?productId=UL2231-1UL Solutions (UL Standards)Only if exporting onward to US/CA
North America energy compliance (US/CA option)DOE 10 CFR § 430 (energy conservation program) / NRCan (where applicable)US Code of Federal Regulations — 10 CFR Part 430 (Energy Conservation Program for Consumer Products), record page: https://www.ecfr.gov/current/title-10/chapter-II/subchapter-D/part-430US DOE / NRCanOnly if exporting onward to US/CA

6. Duty-stack framework — Albania import

Required header: HS national line | Program | As-of: 2026-09-21 | SoT: PENDING — broker-confirmed lookup
HS national line Program As-of: 2026-09-21 SoT: PENDING — broker-confirmed lookup
PENDING — broker-confirmed 8-digit Albanian Customs tariff line for the SKU procured (typical candidate families: 8504.40 static converters, 8543.70 other machines with individual functions — confirm on the national tariff portal)Customs dutyPENDING — lookupPENDING
Same HS lineVAT at import (Albanian standard rate)PENDING — lookupPENDING
Same HS lineExcise (if applicable to the SKU)PENDING — lookupPENDING
Same HS lineAny preferential rate under FTA / diagonal cumulationPENDING — lookupPENDING
Claim: Albanian import duty and VAT rates for EVSE must be looked up on the Albanian Customs (Drejtoria e Përgjithshme e Doganave) national tariff portal at the time of import declaration, against the 8-digit national line that the broker confirms for the exact SKU.
Src: Albanian Customs — Drejtoria e Përgjithshme e Doganave — national tariff portal (homepage entry to the tariff lookup application).
URL: https://dogana.gov.al/
Accessed: 2026-09-21 · PENDING — broker-confirmed lookup at time of import.
Claim: For an EVSE cross-referenced to Chinese origin, the EU TARIC nomenclature records candidate HS subheadings under Chapter 85 (electrical machinery).
Src: European Commission — TARIC / customs nomenclature consultation page (reference index for HS subheading look-up used as a sanity check on Albanian national nomenclature).
URL: https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp
Accessed: 2026-09-21.

Use the 8-digit national line that the broker confirms for your exact SKU; do not transpose rates across product families (static converter vs charging station vs equipment with specific functions).

7. Logistics claims — sourced

Claim: Ocean transit time from main Chinese load ports (Shanghai, Ningbo-Zhoushan, Shekou) to the Port of Durrës on Far East → Mediterranean services is in the 30–40 day planning window for a single FCL; specific transit time is service- and routing-dependent.
Src: Container transit time reference — UNCTAD Review of Maritime Transport, latest public edition landing page (used as a trade-lane reference index).
URL: https://unctad.org/webflyer/review-maritime-transport-2024
Accessed: 2026-09-21 · Planning reference only — bindable transit time is forwarder schedule-specific.
Claim: Marine cargo insurance (Institute Cargo Clauses A — "all risks") on a single FCL of industrial electrical equipment is typically bindable at ~0.3–0.5 % of insured cargo value for a point-to-point CN → AL voyage; the bindable rate is policy- and underwriter-specific.
Src: Institute Cargo Clauses A (Lloyd's Market Association / LMA Joint Cargo Committee) publication record — LMA/JCC standard wording for ICC-A.
URL: https://www.lmalloyds.com/LMA/Content/LMA_Standard_Wording/LMA_JCC_Wording.aspx
Accessed: 2026-09-21 · Planning reference only — bindable rate is underwriter quote-specific.

8. Frequently asked questions

8.1 What is the right HS code for a 240 kW DC charger into Albania?

HS classification depends on the exact product family (static converter vs charging station vs equipment with specific functions). Confirm the 8-digit national line on the Albanian Customs tariff portal before declaring the import — see §6.

8.2 Is CE marking mandatory in Albania?

Albania is not an EU member state. CE marking is a precondition for placing equipment on the EU/EEA market; for the Albanian market, verify conformity requirements with the relevant Albanian authority before any purchase order. Always request the OEM's full conformity dossier (see §5).

8.3 What is a realistic payback for a highway-hub 240 kW DC charger in Albania?

The computed payback in §2 is 0.0 years under the bounded default set (zero modelled CapEx/OpEx, flat USD 54,400 annual benefit, 8 % discount, 10-year horizon). This is a planning scaffold; replace every input with a live RFQ (CapEx + OpEx), a DSO tariff letter (energy cost and capacity charge), a site study (utilization), and a signed lease or concession. Re-run the scenario TCO model.

8.4 Which Incoterm should I select on the RFQ?

DAP Durrës and CIP Tirana are both common for EVSE shipments; DDP site is workable only if the supplier has an Albanian entity or appointed indirect representative handling import clearance. Confirm with your broker and forwarder. Incoterms 2020 definitions are published by the International Chamber of Commerce — https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ (reference index, accessed 2026-09-21).

8.5 Lead time from a Chinese OEM?

Lead times depend on production slot, certification package, and shipping mode (sea FCL vs air for spares). Request a written lead-time confirmation as part of the RFQ response — do not rely on indicative figures.

8.6 What site-side work is not included in the OEM scope?

MV transformer, low-voltage switchgear, cable runs to the charger skid, earthing, canopy, lighting, signage, and any grid-side protection requested by the DSO are typically outside the OEM delivery. Confirm the division of scope in writing.

8.7 Which real Chinese OEM is the worked example?

The worked-example OEM is Sungrow Power Supply Co., Ltd. (Anhui, PRC); the referenced product family is the IDC180E / IDC240E-class public DC fast charger public product page — https://en.sungrowpower.com/product/IDC180E (accessed 2026-09-21). The exact SKU and certificate set must be confirmed against the OEM datasheet at RFQ.


9. Get a real number — RFQ

Request Quote — replies in 48h Spec & Datasheet (RFQ-gated PDF)

© Tradvolt — B2B import & TCO reference for green-tech exports from China. This page is a planning scaffold; all numeric cells marked PENDING must be replaced with live quotes and official customs lookups before any commercial decision. Computed §2 tables are the output of the computed Tradvolt TCO model against the bounded default set in §3 and are computed as published.