Standard Operating Procedure for the verification of anti-islanding behaviour on TradVolt vertical LFP battery systems prior to on-site commissioning, applicable to shipments moving on the China → Philippines (CN→PH) corridor.
Decision. Pass criterion: inverter must disconnect within ≤ 2.00 s per IEC 62116:2014 at all five load points (25 / 50 / 75 / 100 / 125 % of rated output), with insulation ≥ 1 MΩ between DC+/DC− and PE and DC bus voltage within ±3 % of nominal before energising. Equipment: TradVolt TV-LFP-215K LFP cabinet paired with Sungrow SG125HT 125 kW three-phase string inverter. Location: buyer site, Manila area, Philippines. Horizon: pre-commissioning on arrival under Incoterms 2020 CIF Manila. Evidence date: 2026-09-21. Limitation: IEC 62116 procedure limits (DC bus 1500 V max, SOC 30–80 %, torque 8 N·m on DC connector per OEM manual) apply only to the Sungrow SG125HT Rev. 1.4 service manual; other inverter models in the TradVolt catalogue require a separate SOP revision.
| Item | Value / Reference |
|---|---|
| TradVolt LFP cabinet in scope | TV-LFP-215K (215 kWh, 51.2 V DC modules) |
| Inverter in scope | Sungrow SG125HT (125 kW, 1500 V DC, 3-phase, 8 MPPT) — Sungrow string inverter range |
| OEM service manual | Sungrow SG125HT Service Manual, Rev. 1.4 (2025-08) — exact rev confirmed at RFQ |
| DC bus limit (per OEM manual) | ≤ 1500 V DC (Sungrow SG125HT maximum input voltage) |
| SOC window (per OEM manual) | 30 %–80 % during the test sequence |
| DC connector torque (per OEM manual) | 8 N·m on the PV/DC connector |
| Test method | IEC 62116:2014, load points 25 / 50 / 75 / 100 / 125 % |
| Max disconnection time | ≤ 2.00 s at every load point |
| Insulation (pre-energising) | ≥ 1 MΩ, DC+ to PE and DC− to PE |
| DC bus deviation | within ±3 % of nominal |
| Visual sampling | ISO 2859-1 normal inspection, AQL 1.0 (major) / 2.5 (minor) |
| Incoterms 2020 | CIF Manila (default; overridden per contract) |
| Executed by | TradVolt Service Engineer (Lead) with Commissioning Supervisor counter-signature |
This SOP defines the procedure, acceptance criteria, documentation set, and trade-compliance references required to perform the anti-islanding protection test on TradVolt LFP battery systems installed in commercial and industrial sites on the CN→PH corridor.
| Claim | Source (full designation) | URL | Accessed |
|---|---|---|---|
| The anti-islanding test method for inverter-based resources is described in IEC 62116:2014 (Edition 2.0), including the requirement that the inverter ceases to energise the utility within 2 s of grid loss under specified load conditions. Use the IEC Webstore catalogue query — direct publication IDs are not guessable. | IEC 62116:2014, Utility-interface test procedures for inverter-based resources interconnected with low-voltage distribution networks | https://webstore.iec.ch/en/products/?q=62116 | 2026-09-21 |
| The LFP battery cabinets covered by this SOP carry CE marking under the applicable EU directives; product conformity is verified through the manufacturer's Declaration of Conformity shipped with each cabinet. EU Battery Regulation (EU) 2023/1542 governs battery placement on the EU market. | Regulation (EU) 2023/1542 — EU Battery Regulation | https://eur-lex.europa.eu/eli/reg/2023/1542/oj | 2026-09-21 |
| UL 1973 is the standard for batteries used in stationary and motive auxiliary power applications; UL 9540 is the system-level energy-storage standard. Together they form the basis for system-level listing referenced for inverter functional-safety tests. | UL 1973, Batteries for Use in Stationary and Motive Auxiliary Power Applications | https://www.shopulstandards.com/ProductDetail.aspx?productid=UL1973 | 2026-09-21 |
| UL 9540 is the standard for energy storage system safety; inverter anti-islanding is one of the functional-safety tests referenced for system-level listing. | UL 9540, Standard for Energy Storage Systems and Equipment | https://www.ul.com/services/energy-storage-system-testing-and-certification | 2026-09-21 |
| Sampling of received equipment for visual defects follows ISO 2859-1 normal inspection, AQL 1.0 for major and 2.5 for minor defects unless contractually amended. | ISO 2859-1:1999, Sampling procedures by attributes — Part 1 | https://www.iso.org/search.html?q=2859 | 2026-09-21 |
| Shipments from CN to PH are tendered under Incoterms 2020; the buyer- or seller-side obligation (commonly FOB, CFR, or CIF Manila) is recorded per contract and not redefined by TradVolt. | ICC Incoterms 2020 (ICC Publication No. 723E) | https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | 2026-09-21 |
| Multimodal handover in Manila is documented through the FIATA multimodal transport waybill framework; transport documents are provided by the nominated freight forwarder. | FIATA Multimodal Transport Waybill (MTWB) documentation framework | https://fiata.org/ | 2026-09-21 |
| Customs declarations on the Philippines side are filed through the Bureau of Customs Client Portal; tariff lines and duties are quoted by the licensed customs broker, not by TradVolt. | Philippines Bureau of Customs — e2m Customs Client Portal | https://clientportal.customs.gov.ph/ | 2026-09-21 |
| HS nomenclature used to classify LFP cabinets and static converters on import follows the WCO Harmonized Commodity Description and Coding System, 2022 edition. | WCO HS Nomenclature 2022 edition | https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition | 2026-09-21 |
| Lithium-ion cells used inside the cabinet are type-tested under the UN Recommendations on the Transport of Dangerous Goods, Manual of Tests and Criteria (UN 38.3). | UN Recommendations on the Transport of Dangerous Goods, Manual of Tests and Criteria (UN 38.3, ST/SG/AC.10/11/Rev.7) | https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria | 2026-09-21 |
| Role | Responsibility |
|---|---|
| Service Engineer (Lead) | Executes the test, signs the report, owns the checklist. |
| Commissioning Supervisor | Authorises energising, issues LOTO keys, reviews results, counter-signs. |
| Safety Officer | Confirms the safe work zone and PPE compliance. |
| Document Controller | Files the signed report and checklist in the project folder. |
| Forwarder / Customs Broker | Provides Incoterms-aligned transport docs and PH customs filing. |
| Step # | Action | Owner | Input doc | Output doc | Done-when |
|---|---|---|---|---|---|
| 1 | Confirm scope, work order, and pre-conditions (weather window, isolation permit issued). | Service Engineer (Lead) | WO-XXX, ISO-45001 JSA | Pre-condition checklist signed | All 6 pre-condition items ticked. |
| 2 | Review the inverter section of the OEM service manual — Sungrow SG125HT Service Manual Rev. 1.4 — for the exact model in scope; record page numbers. | Service Engineer (Lead) | Sungrow SG125HT Service Manual Rev. 1.4 | Manual page references logged | Manual page numbers recorded. |
| 3 | Prepare and calibrate the test instruments: AC source, RLC load, power analyser with valid calibration sticker. | Service Engineer (Lead) | Calibration register | Instrument readiness form | Sticker dates valid, warm-up complete. |
| 4 | Perform pre-test safety walk: PPE, LOTO applied, emergency stop tested, signage posted. | Safety Officer | Site Safety Plan | Safety walk card | All hazards closed or guarded. |
| 5 | Verify initial electrical state: DC open-circuit voltage within ±3 % of nominal; insulation resistance ≥ 1 MΩ between DC+ and PE and between DC− and PE. Confirm DC bus ≤ 1500 V per Sungrow SG125HT Rev. 1.4. | Service Engineer (Lead) | Battery commissioning sheet | Initial measurements log | Values recorded with units. |
| 6 | Execute the anti-islanding test per IEC 62116:2014: apply R, RL, RC, and RLC loads at 25 %, 50 %, 75 %, 100 %, 125 % of rated inverter output. Hold the cabinet SOC within 30 %–80 % per OEM manual. | Service Engineer (Lead) | IEC 62116:2014 test matrix | Trip-time data sheet | All 5 load points per phase captured. |
| 7 | Record trip times from each waveform capture with timestamp and load point. | Service Engineer (Lead) | Power analyser export | Trip-time data sheet | Maximum trip time ≤ 2.00 s. |
| 8 | Determine pass/fail against IEC 62116:2014 acceptance criteria; flag any anomaly. | Commissioning Supervisor | Trip-time data sheet | Pass/fail record | Supervisor counter-signature present. |
| 9 | Restore normal operating mode, clear LOTO, return the inverter to inverter-on-grid. | Service Engineer (Lead) | LOTO register | Restoration sign-off | LOTO padlock removed by owner. |
| 10 | Issue the final test report and archive it in the project folder; update the asset register. | Document Controller | Pass/fail record, waveforms | SOP-LFP-AIT-07 Report (PDF) | Report SHA-256 logged. |
| Item | Specification | Quantity |
|---|---|---|
| AC source (grid simulator) | Programmable, 0–300 V AC, ≥ 10 kVA | 1 |
| RLC load bank | 5 kW min, switched R/L/C steps | 1 |
| Power analyser | Class A, ≥ 1 kHz sampling | 1 |
| Insulation tester | 1000 V DC, ≥ 1 GΩ range | 1 |
| Torque wrench (DC connector) | 8 N·m calibrated (per Sungrow SG125HT Rev. 1.4) | 1 |
| PPE kit | Insulating gloves, arc-rated face shield, hearing protection | 1 set per person |
WO-XXX_Anti-Islanding_Test_Request.pdfPre-Condition_Checklist_LFP-AIT-07.pdfManual_Reference_Log_Sungrow_SG125HT_Rev1-4.pdfInstrument_Readiness_Form.pdfSafety_Walk_Card.pdfInitial_Measurements_Log.xlsxTrip-Time_Data_Sheet.xlsxPass_Fail_Record.pdfRestoration_Sign-Off.pdfSOP-LFP-AIT-07_Test_Report_v3.2.pdf| Phase | Activity | Dependency | Indicative duration | Slot |
|---|---|---|---|---|
| 1 | Factory acceptance (CN) — IEC 62116 bench report bundled with shipment | OEM test bench availability | Model assumption — confirmed per PO | Indicative |
| 2 | Export clearance (CN) — commercial invoice, packing list, certificate of origin | Forwarder appointment | Indicative 2–4 working days | Indicative |
| 3 | Sea transit CN→PH (e.g. Shanghai / Shenzhen → Manila) | Carrier schedule | Indicative 7–12 days | Indicative |
| 4 | Philippines customs clearance — broker filing via the Bureau of Customs Client Portal | Broker engagement | Indicative 3–7 working days | Indicative |
| 5 | Inland haulage and site delivery | Site readiness | Indicative 1–3 days | Indicative |
| 6 | On-site anti-islanding test (this SOP) — TradVolt Service Engineer (Lead) with Supervisor counter-sign | Energising window | Indicative 4–6 hours | Indicative |
| 7 | Report sign-off, asset register update, handover | Document Controller | Indicative 1 working day | Indicative |
All durations above are indicative and depend on the contractually agreed Incoterms 2020 point of delivery, carrier schedule, broker engagement and site readiness. TradVolt does not warrant transit or clearance lead-times.
The Philippines tariff follows the WCO Harmonized Commodity Description and Coding System (2022 edition) as transposed into the PH AHTN 2026. Final classification, valuation, duty and VAT are determined by the licensed PH customs broker and the Bureau of Customs at the moment of filing via the Bureau of Customs Client Portal. Lookup tool: WCO HS Nomenclature 2022 edition.
| Item | HS code (PH AHTN 2026, indicative class) | Duty rate | VAT | Source for verification |
|---|---|---|---|---|
| LFP battery cabinet (incl. BMS and integrated inverter/charger) | 8507.60 — Lithium-ion accumulators (PH AHTN 2026, exact sub-line PENDING — broker lookup against Section IV Ch. 85) | PENDING — broker lookup against PH AHTN 2026 / Section IV Ch. 85 | PENDING — broker lookup (PH VAT default 12 %, confirm at filing) | Philippines Bureau of Customs — Client Portal + WCO HS 2022 |
| Spare inverter modules and replacement PCBs (e.g. Sungrow SG125HT spares) | 8504.40 — Static converters (PH AHTN 2026, exact sub-line PENDING — broker lookup) | PENDING — broker lookup against PH AHTN 2026 / Section IV Ch. 85 | PENDING — broker lookup | Philippines Bureau of Customs — Client Portal |
| Test instruments (returned/re-imported service tools) | 9030 — Oscilloscopes, spectrum analysers (PH AHTN 2026, exact sub-line PENDING — broker lookup) | PENDING — broker lookup against PH AHTN 2026 | PENDING — broker lookup | Philippines Bureau of Customs — Client Portal |
Disclaimer: HS classifications and duty/VAT rates above are placeholders pending confirmation against the Philippines AHTN 2026 and the live Bureau of Customs tariff table. Final classification, valuation, duty and VAT are determined by the licensed PH customs broker and the Bureau of Customs at the moment of filing. TradVolt does not provide legal tariff advice.
/projects/<site-id>/commissioning/ait/.For scheduling the anti-islanding test on a CN→PH corridor project on a TradVolt TV-LFP-215K paired with a Sungrow SG125HT (or another cabinet/inverter pairing within the TradVolt catalogue), submit an RFQ and our service team will reply within 48 hours.