TradVoltProcesses › Battery Pack Vibration Pre-Shipment Test (CN→IN, EVE LF280K)

Battery Pack Vibration Pre-Shipment Test — CN→IN Corridor, EVE LF280K LFP Pack

Verdict (answer-first): For a 1–3 pack lot of EVE LF280K-family LFP battery packs consigned CN→IN, this SOP delivers a signed pre-shipment vibration test report in a typical end-to-end duration of 2 working days, subject to shaker availability. Pass criterion per IEC 62619 mechanical tests: no fire, no explosion, no electrolyte leak, no enclosure rupture, post-test cell voltage within 2.5–3.65 V/cell and pack voltage within ±1% of nominal. Equipment family: EVE LF280K 3.2 V / 280 Ah prismatic LFP cell, assembled into 48 V / 51.2 V nominal packs (16S configuration), OEM service manual reference: "EVE Energy LF280K User Manual", Rev. 2024-03. Limitation: HS classification 8507.60 and BCD/IGST/SWS rates are PENDING lookup against Indian Customs ICEGATE at booking. Evidence date for all cited sources: 2026-09-21.

ParameterValue / Status
Equipment familyEVE LF280K 3.2 V / 280 Ah prismatic LFP cell in 16S pack (48 V / 51.2 V nominal)
OEM service manual"EVE Energy LF280K User Manual", Rev. 2024-03
Lot size scope1–3 packs (typical); ISO 2859-1 General Inspection Level II default
Typical duration2 working days end-to-end
Pass criterionIEC 62619 mechanical tests + post-test cell voltage 2.5–3.65 V, no leak/explosion/fire
Mount torque (M8 fixture bolts)18 N·m ± 2 N·m (per OEM manual)
Pre-test SOC target50% ± 5%
HS code8507.60 — PENDING (lookup on ICEGATE at booking)
BCD / IGST / SWSPENDING (lookup on ICEGATE at booking)
Evidence date2026-09-21

Scope and applicability

Applies to EVE LF280K-family LFP battery packs assembled in China and consigned to India by sea or air, where the buyer requires third-party evidence of mechanical robustness before goods are loaded. The pack family is built on the EVE LF280K 3.2 V / 280 Ah prismatic cell (datasheet https://www.evebattery.com/en/product/lf280k), configured 16S to deliver a nominal 51.2 V / 280 Ah pack. The applicable OEM service manual reference is the "EVE Energy LF280K User Manual" Rev. 2024-03 (downloaded copy held on the TradVolt job file; OEM page: https://www.evebattery.com/en/product/lf280k). Tests are performed against IEC 62619 mechanical test clauses and ICC Incoterms 2020 governs the CN→IN delivery terms. [Claim | Src: IEC 62619 | URL: https://webstore.iec.ch/publication/60981 | accessed 2026-09-21] [Claim | Src: EVE LF280K product page | URL: https://www.evebattery.com/en/product/lf280k | accessed 2026-09-21] [Claim | Src: ICC Incoterms 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21]

Reference framework

Duty and HS classification block

ItemDetail
HS code (battery packs, LFP, industrial)8507.60 — PENDING — lookup against Indian Customs ICEGATE for the consignment season at booking.
Applicable BCD / IGST / social welfare surchargePENDING — lookup on ICEGATE at the time of shipment; rates are sensitive to budget notifications and exemptions (e.g., Phased Manufacturing Programme lists).
Customs valuation basisCIF value per Incoterms 2020 (CIP/CIF) declared on the Bill of Entry. [Claim | Src: ICC Incoterms 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | accessed 2026-09-21]
Official portalIndian Customs ICEGATE — https://www.icegate.gov.in/
DisclaimerDuty rates and HS classification are PENDING lookup at the time of each booking against the current ICEGATE tariff file. TradVolt does not hardcode duty rates and is not a customs broker; final entries are filed by the importer's CHA.

Step-by-step procedure

Step #ActionOwnerInput docOutput docDone-when
1Receive export booking, PO, and pack list from sellerTradVolt PMBuyer PO, packing list, commercial invoiceBooking confirmation notePO numbers, lot size, and pack model (EVE LF280K 16S) match across all three documents
2Open job file and define test scope; record OEM manual revisionTradVolt PMBooking confirmation, "EVE Energy LF280K User Manual" Rev. 2024-03Job sheet with profile, axis set, and pass criteriaProfile, axis set, M8 mount torque (18 N·m), SOC target (50% ± 5%), and pass criteria recorded on job sheet
3Draw the sample per ISO 2859-1 AQL planTradVolt QALot size, AQL table (General Inspection Level II unless buyer specifies Level I or S-1)Sample selection recordSample count and pack serial numbers logged
4Pre-condition the pack to 50% SOC ± 5% at 25°C ± 2°CLab technician"EVE Energy LF280K User Manual" Rev. 2024-03, pre-conditioning sectionPre-conditioning logPack voltage 51.2 V nominal × 0.5 ≈ 25.6 V pack string within ±1%, SOC verified via BMS log
5Mount the pack on the electrodynamic shaker using OEM fixture; torque M8 bolts to 18 N·m ± 2 N·mLab technicianEVE fixture drawing, calibration certificate of shakerMounting photo set + torque logPack rigidly bolted; reference accelerometer within 5 g tolerance
6Run sweep / random vibration profile per IEC 62619 / UN 38.3 T.1Lab technicianJob sheet profile, IEC 62619, UN 38.3 T.1Raw acceleration data files (.csv)X/Y/Z axes run full duration with no controller abort; PSD curves archived
7Mid-test inspection (interruption point only if standard requires)TradVolt QATest standard checkpoint listMid-test checklistNo new BMS alarms, no leak, no mounting loosening observed
8Post-test electrical and visual checksLab technicianPost-test checklist, "EVE Energy LF280K User Manual" Rev. 2024-03 acceptance limitsPost-test measurement sheetCell voltage 2.5–3.65 V, pack insulation resistance within OEM limits, no enclosure deformation
9Compile report and QA Lead sign-offTradVolt QA LeadRaw data, calibration certs, photosTR-VIB-### report (PDF)Report signed, archived, shared with seller and buyer
10Release lot to forwarder and archive jobTradVolt PMSigned report, FIATA multimodal transport document setRelease note, archived job folderForwarder acknowledges release note; archive path recorded

Document checklist (literal filenames)

Timeline with dependencies

PhaseActivityDepends onIndicative duration
T0PO and pack list receivedindicative 0 days
T0+1Sample selection per ISO 2859-1T0indicative 0.5 day
T0+1Pre-conditioning to 50% SOC ± 5% at 25°CT0, OEM manualindicative 4–8 hours per pack
T0+2Mounting, torque to 18 N·m, accelerometer checkPre-conditioning completeindicative 1 hour per pack
T0+2Vibration run (X/Y/Z per IEC 62619 / UN 38.3 T.1)Mounting complete, shaker availableindicative 3 hours total
T0+3Post-test electrical and visualVibration run completeindicative 1 hour
T0+3Report drafting, QA Lead sign-off, releaseAll measurements loggedindicative 0.5 day
T0+4Handover to forwarder for IN legSigned reportindicative 0.5 day

Total indicative end-to-end duration for a 1–3 pack lot: 2 working days, subject to shaker availability and pre-conditioning time. Cost slots for lab time, calibration, and report issuance are indicative and UNCERTAIN at booking; final numbers are quoted on the RFQ.

Sampling and pass/fail criteria

Sample selection follows ISO 2859-1 General Inspection Level II unless the buyer's specification tightens to Level I or S-1. [Claim | Src: ISO 2859-1 | URL: https://www.iso.org/standard/11437.html | accessed 2026-09-21] Pass criteria follow IEC 62619 mechanical tests (no fire, no explosion, no electrolyte leak, no enclosure rupture, post-test cell voltage within 2.5–3.65 V/cell, pack voltage within ±1% of nominal) and UN 38.3 T.1 vibration profile. [Claim | Src: IEC 62619 | URL: https://webstore.iec.ch/publication/60981 | accessed 2026-09-21] [Claim | Src: UN Manual of Tests and Criteria Rev. 7, §38.3 | URL: https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria | accessed 2026-09-21]

Document checklist

The printable document checklist with sign-off boxes is delivered as part of the RFQ pack and re-issued with the signed report. Request the checklist + quote via the RFQ form.

Request a quote

Send your PO, pack model (EVE LF280K 16S or equivalent), lot size, and the OEM service manual revision. Request Quote — replies in 48h.

Notes and disclaimers

This SOP describes TradVolt's standard procedure for the CN→IN corridor and the EVE LF280K LFP pack family (16S configuration, 51.2 V nominal). Where the buyer specification, OEM service manual revision, or applicable IEC/UL/UN clause deviates, the stricter document governs. [Claim | Src: IEC 62619 | URL: https://webstore.iec.ch/publication/60981 | accessed 2026-09-21] [Claim | Src: UL 1973 | URL: https://www.shopulstandards.com/ProductDetail.aspx?UniqueKey=35575 | accessed 2026-09-21] HS codes, duty rates, and exemption status are PENDING — lookup against the current ICEGATE tariff at booking; TradVolt does not provide customs brokerage and does not guarantee rate outcomes. [Claim | Src: ICEGATE | URL: https://www.icegate.gov.in/ | accessed 2026-09-21] For packs other than the EVE LF280K family, this SOP is treated as a model assumption and a job-specific manual review is performed before quoting.