Vertical: Solar Balance-of-Systems (BoS) · Document type: Process / Standard Operating Procedure · Revision: 2026-Q3
This Standard Operating Procedure defines how TradVolt verifies the cell-balancing function of Battery Management Systems (BMS) integrated with solar Balance-of-Systems equipment shipped from original equipment manufacturers in China to project sites in Luxembourg. The SOP exists to detect balancing faults before energisation on-site, and to provide an auditable evidence file for the customer.
[Claim: Cell-balancing faults detected pre-shipment reduce on-site commissioning risk | Src: IEC 62619 | URL: https://webstore.iec.ch/publication/65959 | Accessed: 2026-09-21]
| Step # | Action | Owner | Input doc | Output doc | Done-when |
|---|---|---|---|---|---|
| 1 | Open inbound shipment, reconcile packing list with commercial invoice and customs paperwork. | Warehouse Lead | Packing list, commercial invoice, CN→LU customs declarations | Goods Received Note (GRN) | GRN signed and quantities match; deviations logged. |
| 2 | Move BMS units to ESD-safe, climate-controlled verification cell (15–25 °C). | Warehouse Lead | GRN | Staging log | Units grounded; staging log entry recorded. |
| 3 | Connect OEM service tool, apply nominal bus voltage, confirm BMS firmware handshake. | BMS Technician | OEM service manual (per model), firmware version sheet | Handshake record | Firmware version and serial number logged; telemetry visible. |
| 4 | Record resting per-cell voltage (mV) after 1 h settling; compute ΔVmax. | BMS Technician | OEM service manual tolerance table | Baseline voltage sheet | ΔVmax ≤ OEM-specified threshold (mV) for each unit. |
| 5 | Apply controlled discharge to lowest-voltage cell using bench supply until ΔV trigger met. | BMS Technician | OEM service manual, bench PSU | Imbalance induction log | ΔV between weakest and strongest cell ≥ trigger threshold. |
| 6 | Enable active balancing and log balancing current (A) and duration (s) until convergence. | BMS Technician | OEM service manual pass criteria | Balancing response log | ΔVmax returns within OEM-specified mV band within stated s. |
| 7 | Capture cell and balancer PCB temperatures (°C) with calibrated thermocouples. | BMS Technician | OEM service manual thermal limits | Thermal log | All readings ≤ OEM thermal limit (°C). |
| 8 | Apply ISO 2859-1 attribute sampling; classify lot Pass / Conditional / Fail. | Quality Engineer | Per-unit logs, AQL sampling plan | Lot classification sheet | AQL decision recorded with sampled n and Ac/Re values. |
| 9 | Compile verification report with serial numbers, photos, and raw CSV logs. | Quality Engineer | All per-unit logs, calibration certificates | Customer Verification Report (PDF) | Report reviewed and counter-signed by QA Manager. |
| 10 | Archive evidence pack and release lot for onward dispatch under DAP Luxembourg. | Documentation Officer | Signed verification report, raw logs | Archived evidence pack in project folder | Files stored with read-only hash; lot marked release-ready. |
[Claim: Attribute sampling per ISO 2859-1 governs lot acceptance decisions | Src: ISO 2859-1 | URL: https://www.iso.org/standard/11418.html | Accessed: 2026-09-21]
The following files must exist in the project folder before the lot is marked released. Filenames are literal.
01_GRN_[ProjectID]_[Date].pdf02_StagingLog_[ProjectID].xlsx03_HandshakeRecord_[ProjectID].csv04_BaselineVoltage_[ProjectID].xlsx05_ImbalanceInduction_[ProjectID].csv06_BalancingResponse_[ProjectID].csv07_ThermalLog_[ProjectID].csv08_AQLClassification_[ProjectID].pdf09_VerificationReport_[ProjectID]_[Rev].pdf10_CalibrationCerts_Bundle_[ProjectID].pdf| Stage | Owner | Duration | Depends on |
|---|---|---|---|
| Pre-shipment QA at CN factory | Supplier QA | 2 days | — |
| Export customs clearance (CN) | Freight forwarder | 1 day | Pre-shipment QA |
| Multimodal transit CN → LU port/airport | Carrier (FIATA-issued MTD) | 7 days (indicative) | Export clearance |
| Import customs clearance (LU) | Customs broker | 1 day | Goods arrival, HS-coded paperwork |
| Inbound BMS verification (this SOP) | TradVolt QA | 2 days | Import clearance |
| DAP Luxembourg delivery to site | Last-mile carrier | 1 day | Verification Pass |
Transit durations are indicative and depend on carrier schedule, port congestion, and customs workload; values are NOT lead-time commitments.
| Cost element | Basis | Value |
|---|---|---|
| Verification labour | Per unit, indicative | UNCERTAIN — request quote |
| AQL re-test (if Conditional) | Per re-tested unit, indicative | UNCERTAIN — request quote |
| Documentation pack | Per lot, indicative | UNCERTAIN — request quote |
| EU import duty | Per HS code, official portal | PENDING — lookup, see §7 |
Equipment class: Lithium-ion battery management systems and stationary lithium battery assemblies intended for solar Balance-of-Systems installations.
Indicative HS code candidates (must be confirmed by a licensed customs broker for the exact shipment):
8507.60 — Lithium-ion accumulators (battery assemblies).8537.10 — Boards/panels for electric control, incl. BMS controllers.Applicable duty / VAT rates: PENDING — lookup at the official EU Customs Trader Portal (TARIC consultation).
Official portal: European Commission — Access2Markets / TARIC — https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en.
HS classification and duty/VAT rates are shipment-specific and must be confirmed by a licensed customs broker against the exact tariff measure in TARIC at the time of import. No rate is hardcoded in this SOP.
[Claim: Official EU tariff measures are published in the TARIC database | Src: European Commission TARIC | URL: https://ec.europa.eu/taxation_customs/dds2/taric/ | Accessed: 2026-09-21]
[Claim: Incoterms DAP designates the seller responsible up to the named place of delivery in the country of import | Src: ICC Incoterms® 2020 | URL: https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ | Accessed: 2026-09-21]
All artefacts listed in §4 are retained for the duration of the warranty period plus statutory minimums applicable in Luxembourg. Raw CSV logs are immutable once signed; corrections are made by appending a delta file, not by editing the original.
Request Quote — replies in 48h Download checklist (PDF)
| Rev | Date | Change |
|---|---|---|
| 2026-Q3 | 2026-09-21 | Initial release, CN→LU corridor. |