Guides › CN→ZA Corridor › BMS-CAN Termination Maintenance Guide · R14

BMS-CAN Bus Termination — Maintenance Process Guide for the CN→ZA Corridor

This guide confirms that BMS-CAN bus termination on a Daly Smart BMS 16S 100A LiFePO4 unit (model family: Daly Smart BMS, 16S variant) follows a 10-step bench/field procedure taking approximately 4 hours, with the 120 Ω termination resistor specified in §3.4 of the Daly Smart BMS 16S 100A user manual (OEM manual revision 2024-03). All South African customs duty and VAT rates for HS 8507.10 (lead-acid) / 8507.60 (lithium-ion) BMS-containing assemblies are PENDING and must be verified against the current SARS Tariff schedule before shipment, and no certificate is claimed for this guide — IEC 62619:2022 ed2 and UN Manual of Tests and Criteria ST/SG/AC.10/11/Rev.7 (UN 38.3) are referenced as applicable transport/safety frameworks only, with no certificate ID asserted. The walkthrough is scoped to termination only; balancing, cell monitoring, and firmware flashing are out of scope.

ItemDecision / valueSource / status
Verdict (corridor task)10-step maintenance SOP, ~4 hours bench timeThis guide, R14
EquipmentDaly Smart BMS 16S 100A LiFePO4 (model family: Daly Smart BMS, 16S variant, 120 Ω termination)Daly Smart BMS 16S 100A product page
Location / horizonChina → South Africa trade corridor; bench activity pre-shipment or field-maintenance on commissioningThis guide
Evidence dateVerified 2026-09-22Evidence pack
Termination resistor120 Ω at each physical end of the CAN trunkDaly Smart BMS 16S 100A user manual §3.4 (OEM rev 2024-03)
SA customs duty ratePENDINGSARS Tariff schedule
SA VAT ratePENDINGSARS VAT schedule
Certification claimNo certificate claimed for this guide; IEC 62619:2022 ed2 / UN 38.3 referenced as applicable frameworks onlyDisclaimer in §3 below

Status: R14 draft. Factual claims are tagged in the footer against named sources (Daly Smart BMS 16S 100A user manual OEM rev 2024-03, IEC Webstore entry IEC 62619:2022 ed2, UN Manual of Tests and Criteria ST/SG/AC.10/11/Rev.7, and SARS Tariff schedule). Where a rate, fee, or duty figure could not be sourced from a named authority, the cell is marked PENDING and the lookup link is given.

1. Step-sequence table

Step#ActionOwnerInput docOutput docDone-when
1Confirm corridor scope and shipment HS classificationTrade-ops clerkCommercial invoice draft; packing listShipment-classification sheetHS code confirmed (likely 8507.60 for lithium-ion BMS-containing packs) and shipment tagged "BMS-containing" in the corridor folder.
2Pull Daly Smart BMS 16S 100A user manual (OEM rev 2024-03) for termination resistor value and jumper locationBench technicianBMS model code from invoiceDaly user-manual excerpt (PDF)120 Ω per §3.4 recorded with page reference.
3Verify BMS certification status on issuing body register (if a certificate ID exists)Compliance officerCertificate ID from BOM (if present)Cert-lookup screenshotEither certificate ID resolves as active on the named cert-body register, OR the row is left blank and a disclaimer is recorded that no certificate is claimed for this guide.
4Prepare ESD-safe bench and isolate packBench technicianESD checklistWorkspace-readiness entryPack isolated, PPE confirmed, workspace ID logged.
5Measure existing CAN bus resistance end-to-endBench technicianCalibrated multimeter; Daly Smart BMS 16S 100A user manual §3.4 (OEM rev 2024-03)Resistance-meeting log entryMeasured value recorded against 120 Ω ± tolerance per Daly spec.
6Replace or re-seat the termination resistor if out of toleranceBench technicianDaly-specified part number from §3.4Parts-replacement entryNew resistance reading matches 120 Ω ± tolerance.
7Re-power BMS and capture CAN traffic traceBench technicianCAN analyser; Daly Smart BMS 16S 100A user manual §3.4 (OEM rev 2024-03)CAN-trace capture fileTrace shows no error frames and recessive/dominant voltages within Daly-specified window.
8Update maintenance log and link to shipment master fileBench technicianAll preceding entriesSigned maintenance logLog entry linked to shipment file, technician sign-off present.
9Stage ZA-side customs and importer-of-record documentsTrade-ops clerkMaintenance log, cert-lookup (if any), invoice, packing listZA-entry document packDocument pack complete and handed to the ZA importer of record.
10Close ticket internally or raise an RFQ for follow-up partsProcurement leadMaintenance log, Daly user-manual excerptRFQ ticket or closure noteEither ticket closed with sign-off, or RFQ issued via TradVolt with attachments.

2. Document checklist (literal filenames)

3. Certification disclaimer

No certificate is claimed for this guide. IEC 62619:2022 ed2 (Secondary lithium cells and batteries for use in industrial applications — Safety requirements, International Electrotechnical Commission, TC 21/SC 21A) and the UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 (UN 38.3 lithium-battery transport provisions) are referenced as the applicable transport/safety frameworks that may apply to a BMS-containing lithium battery pack on the CN→ZA corridor. No certificate ID, issuing body, or expiry date is asserted here. If a specific Daly Smart BMS 16S 100A unit is being shipped under a named certificate, the certificate ID, issuer, and revision must be confirmed against the IEC Webstore entry for IEC 62619:2022 ed2 and the UN Manual of Tests and Criteria by the importer of record before shipment.

4. Timeline table (indicative)

PhaseActivityIndicative durationNotes
Day 0Corridor scope and HS confirmation~1 hourTrade-ops clerk turnaround
Day 0–1Daly Smart BMS 16S 100A user manual retrieval and cert lookup (if any)~2 hoursDependent on cert-body register response
Day 1Bench preparation and ESD setup~30 minutesPer ESD checklist
Day 1Resistance measurement and possible re-termination~45 minutesIncludes warm-up of calibrated meter
Day 1CAN trace capture and validation~30 minutesDepends on analyser warm-up
Day 1–2Maintenance log sign-off and ZA document pack assembly~2 hoursFinal QA before hand-off
Day 2+RFQ issuance or ticket closure~30 minutesProcurement lead action

Total indicative duration: approximately 4 hours of active bench/field time, spread over Day 0–Day 2 as above. This is a model assumption; actual duration depends on Daly BMS model variant, analyser warm-up, and cert-body register response time.

5. Cost table (indicative slots — no hard prices)

Cost lineIndicative basisSource / lookupStatus
Bench technician labourIndicativeUNCERTAIN — internal rate cardPENDING
ESD consumables (strap, mat, wrist)IndicativeUNCERTAIN — supplier quotePENDING
Termination resistor (Daly-specified)IndicativeDaly Smart BMS 16S 100A user manual §3.4 (OEM rev 2024-03) — spare-parts list to be confirmed at benchPENDING
CAN analyser session (if external)IndicativeUNCERTAIN — third-party lab ratePENDING
South African import duty on BMS unitsIndicativeLook up the current rate for HS 8507.60 (lithium-ion) or HS 8507.10 (lead-acid) on the SARS Tariff schedule.PENDING
VAT on importationIndicativeConfirm the current VAT rate on the SARS VAT schedule.PENDING

Disclaimer: The cost slots above are indicative placeholders only. No hard prices are stated because sourced, current figures from the relevant authority were not embedded in the page at the time of writing. Customs duty and VAT in particular must be confirmed against the current SARS Tariff schedule and the current SARS VAT schedule applicable at the time of entry. TradVolt is not a customs broker and does not provide duty advice.

6. CTAs

Need a bench team or replacement parts?
Open an RFQ on TradVolt and attach the maintenance log + Daly Smart BMS 16S 100A user-manual excerpt (OEM rev 2024-03).
Request a Quote (RFQ) Download 10-Step SOP (ZIP)

7. Frequently Asked Questions

1. Why does the CAN bus need a 120 Ω termination on both ends?

CAN bus signalling relies on a defined impedance at each end of the trunk to suppress reflection on the differential CAN-H / CAN-L pair. The typically specified value is 120 Ω at each physical end. For the Daly Smart BMS 16S 100A unit, the 120 Ω value and the physical location of the termination jumper/resistor pack are specified in §3.4 of the Daly Smart BMS 16S 100A user manual (OEM revision 2024-03). If only one end is terminated, or if the resistor drifts out of tolerance, the bus will show error frames and the BMS will drop off the network.

2. Is BMS-CAN termination a maintenance task or a pre-shipment task?

It can be either. On the CN→ZA corridor it is commonly performed as a pre-shipment bench activity on a representative unit, and again as a field-maintenance check on arrival or during commissioning at the ZA site. This guide treats both as the same procedure with the same evidence trail.

3. What certificate do I need to ship a BMS-equipped battery pack into South Africa?

This guide does not claim any certificate. The applicable transport/safety frameworks that may apply to a BMS-containing lithium battery pack are IEC 62619:2022 ed2 (Secondary lithium cells and batteries for use in industrial applications — Safety requirements, TC 21/SC 21A) and the UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7 (UN 38.3 provisions for lithium batteries). The exact requirement depends on cell chemistry, pack capacity, and end-use, and must be confirmed by the importer of record against the IEC Webstore entry for IEC 62619:2022 ed2 and the UN Manual of Tests and Criteria. SABS / NRCS letters may also apply for specific ZA-side use cases and must be confirmed separately.

4. Can I use a non-Daly termination resistor?

Only the Daly-specified part listed in §3.4 of the Daly Smart BMS 16S 100A user manual (OEM rev 2024-03) should be used. Substituting a different resistor value, tolerance, or footprint changes the bus impedance and can cause intermittent faults that are difficult to trace at the bench.

5. Where do I find the official SARS import-duty rate for a BMS unit?

Use the SARS customs tariff portal with the correct HS code — likely HS 8507.60 for a lithium-ion BMS-containing pack, or HS 8507.10 for a lead-acid assembly. The exact duty figure must be confirmed against the current SARS Tariff schedule applicable at the time of entry; this guide marks that figure as PENDING because a sourced current rate was not embedded in the page.