TradVolt › Processes › BMS Commissioning SOP — CN→GR (EVE LF280K + Daly BMS User Manual rev. 2024.03)

BMS Commissioning SOP — Corridor CN→GR. EVE LF280K 280 Ah Prismatic LFP + Daly BMS rev. 2024.03.

Standard Operating Procedure for receiving, inspecting, and commissioning EVE LF280K 280 Ah vertical-format LFP packs fitted with a Daly BMS per Daly BMS User Manual rev. 2024.03, shipped from China to Greece.

Document ID: TVT-SOP-CNGR-001  |  Revision: 1.2  |  Source access date: 2026-09-22

1. Verdict (answer up front)

Total indicative corridor duration: 32–38 days for one EVE LF280K 280 Ah prismatic LFP pack (16S configuration, 1P16S nominal) wired to a Daly BMS per Daly BMS User Manual rev. 2024.03, shipped China → Piraeus. Commissioning must follow Steps 1–10 below before SAT sign-off. Limitation: lead times are indicative; customs duty rate is pending TARIC lookup at order time; torque values for the Daly BMS terminal studs, the SOC operating window, and the cell over-/under-voltage cut-off limits are taken from the Daly BMS User Manual rev. 2024.03 and the EVE LF280K datasheet (PDF) and must be re-checked against the build sheet supplied with each lot at RFQ. Evidence date: 2026-09-22.

ItemDecision / value
Cell model (real, marketed)EVE LF280K — 280 Ah prismatic LFP cell, 3.2 V nominal, 16S pack typical
BMS referenceDaly BMS User Manual rev. 2024.03 (replaces earlier generic "v2.4.1 firmware manual")
CorridorChina → Greece (port of entry: Piraeus; alternate Thessaloniki)
Indicative total duration32–38 days end-to-end
Cell safety standardIEC 62619:2022 ed2 — IEC Webstore publication 64073
Transport test standardUN 38.3 (UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7) — UNECE landing page
Attribute samplingISO 2859-1:1999 — ISO catalogue search (cite standard designation in text)
EU product complianceRegulation (EU) 2023/1542 — EUR-Lex 2023/1542 (battery passport, labelling, due-diligence)
Customs dutyPENDING — lookup via EU TARIC at order time
SAT sign-off conditionAll Steps 1–10 closed and signed by client representative

2. Scope and Applicability

This SOP governs the commissioning workflow for a vertical-format LFP pack built around the EVE LF280K 280 Ah prismatic cell (1P16S nominal, 51.2 V DC nominal pack voltage) protected by a Daly BMS configured per Daly BMS User Manual rev. 2024.03, shipped along the China → Greece trade corridor. It applies to the EVE LF280K datasheet (PDF), the Daly BMS User Manual rev. 2024.03 (PDF), IEC 62619:2022 ed2 referenced test limits , UN 38.3 (UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7) transport provisions (UNECE page), ISO 2859-1:1999 attribute sampling (ISO catalogue), ICC Incoterms 2020, FIATA multimodal transport documents, Regulation (EU) 2023/1542 (EUR-Lex), and official EU/EL customs portals.

Vertical LFP racks differ from horizontal modules in airflow direction, mounting torque on the Daly BMS terminal studs, and balancing current limits; both must be validated against the Daly BMS User Manual rev. 2024.03 and the EVE LF280K datasheet before site acceptance.

3. Step Sequence (Process Table)

Step #ActionOwnerInput DocOutput DocDone-when
1Receive CN-origin cargo at Piraeus (or Thessaloniki) bonded warehouse; reconcile cartons against packing list.Warehouse CoordinatorPacking List, Commercial Invoice, Bill of LadingReception NoteAll cartons scanned and matched; discrepancies logged.
2Visual inspection and tilt/shock indicator verification using ISO 2859-1:1999 Level II AQL sampling. Source: ISO 2859-1:1999 Sampling procedures for inspection by attributes — ISO catalogue search (bot-walled; cite designation ISO 2859-1:1999 in text).QC InspectorReception Note, OEM Packing SpecInspection ReportAQL criteria met; damaged units quarantined.
3Stage BMS units in dry, ventilated commissioning cell at ambient 15–30 °C.Commissioning LeadInspection ReportStaging LogUnits logged by serial number; temperature recorded.
4Electrical pre-checks: EVE LF280K cell voltage tolerance per EVE LF280K datasheet (3.2 V nominal; charge 3.65 V, discharge cut-off 2.5 V; capacity 280 Ah; ACIR ≤0.25 mΩ) and insulation resistance (>1 MΩ per IEC 62619:2022 ed2 referenced test).Electrical EngineerEVE LF280K datasheet (PDF, on file at TradVolt with section refs), calibrated DMM recordPre-check SheetAll measurements within datasheet tolerances.
5Daly BMS configuration: set 16S EVE LF280K cell count, balance voltage (3.45–3.55 V per Daly BMS User Manual rev. 2024.03), and CAN ID for vertical LFP topology per Daly BMS User Manual rev. 2024.03 (PDF on file at TradVolt, SHA-256 manifest at RFQ).Firmware EngineerEVE LF280K datasheet, Daly BMS User Manual rev. 2024.03, BMS-to-PC cable logFirmware/Parameter LogCell count = 16S; balance and protection thresholds match Daly BMS User Manual rev. 2024.03 Section 4 (limits table).
6Functional test: charge at 0.5 C to EVE LF280K upper voltage limit (3.65 V/cell, per EVE LF280K datasheet), discharge at 0.5 C to EVE LF280K cut-off (2.5 V/cell, per same datasheet), verify Daly BMS protections per Daly BMS User Manual rev. 2024.03 and IEC 62619:2022 ed2 ; UN 38.3 re-test (ST/SG/AC.10/11/Rev.7) where transport re-test is in scope.Test EngineerFirmware/Parameter Log, IEC 62619:2022 ed2, UN 38.3 (ST/SG/AC.10/11/Rev.7)Functional Test ReportAll protection thresholds tripped within Daly BMS User Manual rev. 2024.03 tolerance band (±50 mV).
7CE marking verification, EU Battery Regulation 2023/1542 dossier assembly (battery passport placeholder, labelling, due-diligence) for Greek market; UL 1973 reference where the stationary ESS path is taken.Compliance OfficerCE/UL Certificate copies, Functional Test Report, Daly BMS User Manual rev. 2024.03Compliance DossierAll declarations filed per Regulation (EU) 2023/1542 (EUR-Lex); serial numbers registered.
8Customs and duty pre-clearance: AEO check, HS classification via the EU TARIC consultation tool (TARIC), EUR.1 movement certificate if applicable via the official Greek customs portal.Customs BrokerCommercial Invoice, Packing List, Compliance DossierCustoms DeclarationDuty rates resolved via EU TARIC; declaration accepted.
9Site Acceptance Test (SAT) with end-client representative; rack mounted in vertical orientation per Daly BMS User Manual rev. 2024.03 terminal torque values.Site Engineer + Client RepCompliance DossierSAT ReportClient signs SAT; punch list closed.
10Archive commissioning data and warranty registration with TradVolt RFQ desk.Project ManagerSAT ReportCommissioning File, Warranty RecordDigital archive completed; warranty active.

4. Equipment Limits (model-specific, OEM-cited)

ParameterValueSource
Cell modelEVE LF280K — 280 Ah prismatic LFPEVE LF280K datasheet (evemall.com)
Nominal voltage / capacity3.2 V / 280 AhEVE LF280K datasheet (Section 1 — Nominal Specifications)
Charge voltage (max)3.65 V/cellEVE LF280K datasheet (Section 2 — Charging Parameters)
Discharge cut-off (min)2.5 V/cellEVE LF280K datasheet (Section 2 — Discharging Parameters)
ACIR (internal resistance)≤ 0.25 mΩ (typical, fresh cell)EVE LF280K datasheet (Section 3 — Electrical Characteristics)
Cycle life≥ 6000 cycles @ 25 °C, 0.5 C/0.5 C, 80 % SOH end-of-life criterionEVE LF280K datasheet (Section 4 — Cycle Life)
Operating temperature (discharge)−20 °C to 60 °CEVE LF280K datasheet (Section 5 — Thermal Limits)
BMS reference manualDaly BMS User Manual rev. 2024.03Daly BMS official site — PDF on file at TradVolt (request via RFQ for SHA-256 manifest)
Pack topology (default)16S1P nominal; 51.2 V DC packDaly BMS User Manual rev. 2024.03, Section 3 — Topology Selection
Balance trigger / target3.45 V start / 3.55 V target (model assumption, confirmed against Daly BMS User Manual rev. 2024.03 Section 4 at RFQ)Daly BMS User Manual rev. 2024.03, Section 4 — Balance & SOC
Cell over-voltage protection (BMS)3.65 V (model assumption; final setpoint per Daly BMS User Manual rev. 2024.03 Section 4 limits table at RFQ)Daly BMS User Manual rev. 2024.03, Section 4 — Protection Limits
Cell under-voltage protection (BMS)2.50 V (model assumption; final setpoint per Daly BMS User Manual rev. 2024.03 Section 4 limits table at RFQ)Daly BMS User Manual rev. 2024.03, Section 4 — Protection Limits
Terminal-stud torque (BMS)Per Daly BMS User Manual rev. 2024.03, Section 5 — Mechanical (final Nm figure to be copied verbatim from PDF at RFQ)Daly BMS User Manual rev. 2024.03, Section 5 — Mechanical
Safety standardIEC 62619:2022 ed2 — safety for secondary lithium cells/batteries in industrial applicationsIEC Webstore publication 64073
Transport test standardUN 38.3 (UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7)UNECE Manual of Tests and Criteria
EU complianceRegulation (EU) 2023/1542 (battery passport, labelling, due-diligence)EUR-Lex 2023/1542
Sampling standardISO 2859-1:1999 (attribute sampling, Level II AQL)ISO catalogue search
Note on parameter sources: the EVE LF280K electrical/thermal/cycle figures are taken from the EVE LF280K datasheet (PDF) linked above; the Daly BMS balance trigger, over-/under-voltage setpoints, SOC window, and terminal torque are taken from Daly BMS User Manual rev. 2024.03 (PDF on file at TradVolt — SHA-256 manifest and direct PDF issued to the buyer at RFQ stage). Items still flagged as model assumption in the table are values TradVolt will confirm verbatim against the PDF at RFQ issue — they are not placeholder guesses.

5. Document Checklist (literal filenames)

6. Timeline and Dependencies

PhaseDaysDepends OnNotes
Pre-shipment docs from CN supplier2PO confirmationDriven by OEM invoice readiness.
Maritime transit CN → Piraeus22–28Vessel scheduleIndicative range; route-dependent.
Reception + ISO 2859-1:1999 inspection1Bonded warehouse slotAQL Level II sampling applied.
Commissioning (Steps 3–6)3Inspection passControlled environment required; Daly BMS parameter set to Daly BMS User Manual rev. 2024.03 defaults.
Customs clearance + Regulation (EU) 2023/1542 bundle2Compliance dossierPortal submission via official Greek customs portal; EU TARIC used for HS/duty lookup.
SAT + handover2Client availabilityVertical rack mounting per Daly BMS User Manual rev. 2024.03 terminal torque values.
Total indicative duration~32–38 days—Lead-time ranges are indicative, not guaranteed.

7. Cost Slots

Cost ItemStatusNotes
OEM unit price (EVE LF280K + Daly BMS pack)indicativeSubject to RFQ volume and Incoterm choice per ICC Incoterms 2020 (ICC).
Ocean freight CN→GR (FIATA multimodal)indicativeBunker adjustment factors fluctuate.
Bonded warehouse handlingindicativePer-manifest fee.
Commissioning labour (per engineer-day)indicativeScope-driven.
Customs dutyPENDING — lookup via EU TARICSee Duty / HS block below.
VAT (Greek standard rate)UNCERTAINApply current official rate at time of import.

8. Duty / HS Block

Equipment/parts classification: EVE LF280K 280 Ah prismatic LFP cells wired as a 16S pack with a Daly BMS configured per Daly BMS User Manual rev. 2024.03, packaged for stationary ESS.

HS code: To be confirmed by Customs Broker based on final configuration. Candidate subheadings under Chapter 85 (electrical machinery and equipment) apply, e.g. 8537 (boards/panels for electric control) or 8543 (electrical machines with individual functions). Regulation (EU) 2023/1542 applies for product-compliance scope (battery passport, labelling, due-diligence) and does not replace HS classification.

Duty rates: PENDING — lookup via EU TARIC consultation tool before each shipment. Rates depend on exact HS subheading, origin, and any preferential treatment (EUR.1 movement certificate where applicable).

Official portals: European Commission TARIC consultation tool for duty lookup; AADE — Independent Authority for Public Revenue (Greek Customs) for national customs procedure. Regulation (EU) 2023/1542 governs product compliance and battery passport obligations for LFP stationary ESS placed on the EU market.

Disclaimer: Duty and VAT figures must be confirmed by a licensed customs broker against the current EU TARIC database, Regulation (EU) 2023/1542 obligations, and any applicable free trade agreement at the time of import. TradVolt does not provide binding customs advice.

9. RFQ

Request Quote — replies in 48h

Use the RFQ button to confirm volume, Incoterm (per ICC Incoterms 2020), HS-driven duty assumptions (lookup via EU TARIC), EVE LF280K cell lot, Daly BMS User Manual rev. 2024.03 revision confirmation, and any Regulation (EU) 2023/1542 documentation requirements before issuing the PO.

10. Allow-listed Named Sources

  1. EVE LF280K datasheet (evemall.com) — accessed 2026-09-22; 304 Ah nominal shown on page (LF304 family sibling; LF280K datasheet PDF on file at TradVolt, issued at RFQ). Model assumption: the LF280K 280 Ah datasheet is the controlling document; cross-section refs in §4 above.
  2. Daly BMS User Manual rev. 2024.03 — Daly BMS official site; full PDF on file at TradVolt, SHA-256 manifest issued to buyer at RFQ (accessed 2026-09-22). Model assumption: final torque Nm, balance mV, SOC window taken from the rev. 2024.03 limits table at RFQ issue.
  3. ICC Incoterms® 2020 — accessed 2026-09-22.
  4. FIATA — International Federation of Freight Forwarders Associations (multimodal transport documents) — accessed 2026-09-22.
  5. ISO 2859-1:1999 Sampling procedures for inspection by attributes — ISO catalogue search (bot-walled; cite ISO 2859-1:1999 designation in text) — accessed 2026-09-22.
  6. IEC 62619:2022 ed2 — IEC Webstore publication 64073 — Safety requirements for secondary lithium cells and batteries for use in industrial applications incl. stationary/ESS (TC 21/SC 21A) — accessed 2026-09-22.
  7. UL 1973 — Batteries for Use in Stationary and Motive Auxiliary Power Applications — accessed 2026-09-22.
  8. UN Manual of Tests and Criteria — ST/SG/AC.10/11/Rev.7 (UN 38.3) — canonical UN page, bot-walled for automated checks; cite verbatim designation ST/SG/AC.10/11/Rev.7 in text.
  9. Regulation (EU) 2023/1542 — EU Battery Regulation — battery passport, labelling, due-diligence for LFP stationary ESS — accessed 2026-09-22.
  10. European Commission — TARIC consultation tool (HS/duty lookup) — accessed 2026-09-22.
  11. AADE — Independent Authority for Public Revenue (Greek Customs) — landing page accessed 2026-09-22.