Process SOP · LFP Vertical

Warranty Claim Documentation SOP — China → Pakistan Corridor

A standard operating procedure for TradVolt customers handling warranty claims on lithium iron phosphate (LFP) battery equipment and components moving between the People's Republic of China and the Islamic Republic of Pakistan.

Verdict: Following this SOP returns a verified warranty claim with RMA and replacement delivered to a Pakistani site in 26–34 business days via sea (Karachi port) or 16–20 business days overland via the Khunjerab/Sost corridor (subject to weather and customs operating windows). Air freight for time-critical cells is indicative at 7–10 business days but is UNCERTAIN and corridor-conditional. Equipment covered: EVE LF304 prismatic LFP cells (304 Ah / 3.2 V) inside Pylontech US5000 battery modules (48 V / 4.8 kWh) paired with Huawei LUNA2000-215 residential storage or Sungrow PowerTitan2.0 utility cabinets; evidence date 2026-09-22; limitation — all transit times are indicative and depend on Khunjerab weather, Karachi port congestion and OEM RMA response.

ModeOrigin → DestinationIndicative transitLimitation
Sea (LCL/FCL)Shanghai/Qingdao → Karachi18–25 days port-to-portplus 3–4 days customs + last-mile
Overland (CPEC)Kashgar/Wah → Khunjerab → Sost → destination10–14 days door-to-doorwinter closure Nov–Apr
AirPVG/CKG → ISB/KHI3–5 days airport-to-airportUN 38.3 mandatory; surcharge applies

1. Scope and Applicability

This SOP applies to warranty claim events on LFP equipment where the original shipment or the replacement unit crosses the China–Pakistan trade corridor. The corridor includes CPEC overland routes via Khunjerab/Sost, sea transit via Karachi/Qingdao/Shanghai, and multimodal combinations. Named equipment coverage below; substitute models are out of scope unless explicitly added.

1.1 Named equipment under this SOP

1.2 OEM service manual governing SoC, torque and voltage limits

Field technicians, OEM service partners, freight forwarders, and the nominated customs broker each have explicit ownership steps defined in Section 4. Reference to any other TradVolt-supplied model (e.g. BYD MC Cube, Deye BOS-G, GoodWe ET G2) is treated as a separate SOP and is out of scope here.

2. Regulatory References

3. Pre-Conditions

Before opening a claim, the customer confirms that the unit is within the warranty window recorded on the OEM certificate, that the failure mode is not listed in the warranty exclusions (e.g., water immersion beyond IP66 rating, casing fracture from impact, operation outside the OEM published SoC and temperature window), and that the unit has not been opened by a non-authorised party. The relevant OEM service manuals are the Pylontech US5000 Service Manual (rev. 2026-06-23), the Huawei LUNA2000-215 Installation & Commissioning Manual and the Sungrow PowerTitan2.0 O&M Manual, each as cited in §1.2.

Safety: LFP modules must be SoC-discharged to the OEM-specified transport state (US5000: 30–50%; PowerTitan2.0: ≤30%; LUNA2000-215: per installer manual) before any handling, and packaged per the UN Manual of Tests and Criteria, 7th revised edition (ST/SG/AC.10/11/Rev.7), §38.3, where the equipment is shipped by air. Air transport additionally requires the IATA DGR Section II / IB lithium battery handling marks. [Claim | Src: UN Manual of Tests and Criteria | URL: https://unece.org/transport/dangerous-goods/un-manual-tests-and-criteria | accessed 2026-09-22] [Claim | Src: IATA DGR | URL: https://www.iata.org/en/programs/cargo/dgr/ | accessed 2026-09-22]

4. Step-by-Step Procedure

Step #ActionOwnerInput docOutput docDone-when
1Verify warranty eligibility against OEM certificate, batch code and serial number; cross-check against the Pylontech US5000, Huawei LUNA2000-215 or Sungrow PowerTitan2.0 service manuals as applicable.TradVolt Service CoordinatorOEM warranty certificate; sales invoiceEligibility memoEligibility memo signed and dated.
2Capture on-site failure evidence: photographs, BMS logs, fault codes, multimeter readings.Field TechnicianFailed unit on siteEvidence pack (EV-01)EV-01 uploaded to claim folder.
3Issue internal Warranty Claim Form (WCF-01) referencing the EV-01 pack.TradVolt Service CoordinatorEV-01; sales invoiceWCF-01WCF-01 countersigned by customer.
4Submit WCF-01 + EV-01 to the OEM (Pylontech / Huawei / Sungrow as applicable) and obtain a Return Material Authorisation (RMA) number.TradVolt Service CoordinatorWCF-01, EV-01OEM RMA confirmationRMA code logged in claim folder.
5Decide replacement vs. repair; raise purchase order for replacement part or repair service.TradVolt Commercial ManagerOEM RMA confirmationPO and OEM dispatch planPO issued and OEM confirms dispatch slot.
6Prepare commercial documents per ICC Incoterms 2020 (commonly DAP Karachi, CIP Lahore).Freight ForwarderPO; OEM dispatch planCommercial invoice, packing list, CN export declaration draftCommercial invoice approved.
7Inspect the OEM-shipped replacement unit on arrival at the CN consolidation point using an ISO 2859-1:1999 AQL plan (Level II, AQL 1.0 for functional; 2.5 for cosmetic).QC InspectorReplaced unit at consolidation hubInspection report (IR-01)IR-01 signed; defects within AQL or rejected.
8File the export declaration via the China Customs portal and obtain the export release.CN Customs BrokerCommercial invoice, packing list, RMA letterExport declaration receiptCustoms release obtained.
9Pre-lodge the import Goods Declaration on the Pakistan Single Window with the broker; attach RMA letter, OEM commercial invoice and packing list.PK Customs BrokerExport release, transport documentPSW Goods Declaration referenceGD reference number recorded.
10Transport the unit along the agreed corridor (Karachi sea + road; Khunjerab overland; or multimodal) with tracking enabled.CarrierTransport documentTracking events feedPOD received at destination.
11Receive the unit at customer site; reconcile serial numbers; sign delivery acceptance.Field TechnicianPOD, delivery noteDelivery acceptance (DA-01)DA-01 filed; OEM warranty clock continues.
12Archive the full document set and close the claim ticket in the TradVolt portal.TradVolt Service CoordinatorComplete claim folderClosed claim recordCustomer notified; ticket marked closed.

5. Document Checklist

Every claim folder must contain the following files with literal filenames. The customer portal validates filenames on upload.

  • 01_WCF-01_WarrantyClaimForm.pdf
  • 02_EV-01_EvidencePack.zip
  • 03_RMA_Confirmation.pdf
  • 04_PO_Replacement.pdf
  • 05_CommercialInvoice.pdf
  • 06_PackingList.pdf
  • 07_ExportDeclaration.pdf
  • 08_IR-01_InspectionReport.pdf
  • 09_PSW_GoodsDeclaration.pdf
  • 10_TransportDocument.pdf
  • 11_POD_DeliveryReceipt.pdf
  • 12_DA-01_DeliveryAcceptance.pdf

6. Indicative Timeline

PhaseActivityIndicative durationDependency
VerificationSteps 1–42 business daysCustomer evidence supplied
DecisionStep 51 business dayRMA issued
DocumentationSteps 6–92–3 business daysPO confirmed; OEM dispatch slot
TransitStep 10Sea CN→PK: 18–25 days; Overland via Khunjerab: 10–14 days; Air: 3–5 days (lead times are UNCERTAIN and corridor-conditional)Export release
ClosureSteps 11–121 business dayPOD received

Transit durations above are indicative only and depend on carrier schedule, customs clearance, weather at Khunjerab pass, and port congestion. TradVolt does not warrant lead times.

7. Indicative Cost Slots

Cost elementBasisStatus
OEM replacement partPer OEM RMA quoteindicative
CN-side handling & inspectionPer TradVolt rate cardindicative
Export declaration feeChina customs scheduleindicative
Freight (sea / road / air)Per mode and weightUNCERTAIN — request quote
PK customs duties & taxesSee Section 8PENDING — lookup
PK broker feePer broker tariffindicative

8. Duty / HS Code Block

Harmonised System classification for LFP equipment and replacement parts in this corridor must be confirmed against the latest Pakistan Customs Tariff and the China Export Tariff before each filing. The codes and rates below are indicative placeholders only; the WCO HS Nomenclature 2022 edition and USITC HTS search are the cross-reference points for classification work.

ItemIndicative HS code (WCO HS 2022 / Pakistan PCT — verify)Duty rate
Lithium iron phosphate cells (e.g. EVE LF304)8507.60 (verify against Pakistan PCT)PENDING — lookup
Battery management modules / BMS8537.10 (verify against Pakistan PCT)PENDING — lookup
Power conversion / inverter spare parts8504.40 (verify against Pakistan PCT)PENDING — lookup
Cabinets and racks for batteries9403.20 or 8538 (verify against Pakistan PCT)PENDING — lookup

computed classification / duty lookup portals:

Disclaimer: HS classifications and statutory rates above are not computed. Rates, additional regulatory duties, sales tax, withholding tax, and any exemption under Pakistan's EOUS or renewable-energy regime must be confirmed by a licensed customs broker or tax advisor before filing. TradVolt accepts no liability for misclassification.

9. Request a Quote (RFQ)

Submit the WCF-01 and evidence pack via the TradVolt RFQ form to receive a verified quotation within 48 business hours.