TradVolt › TCO › Cemetery Solar 50 kWp ZA

Cemetery Solar 50 kWp in ZA — Use Case & TCO

Verdict (mid scenario, ZAR, 25-year horizon, 8.00% discount): NPV = −166,816 ZAR; IRR = 6.15%; simple payback = 13.18 years; discounted payback = not reached; LCOE = 1.5542 ZAR/kWh. Equipment: JinkoSolar Tiger Neo N-type 580 W modules and Sungrow SG50CX string inverters on K2 Systems SingleRail ground-mount. Location: inland South Africa (illustrative municipal site). Evidence date: 2026-01-15. Limitation: the COMPUTED TABLES below are computed for this scenario; real outcome depends on tariff trajectory, actual yield, capex band and module/inverter choice. The page previously showed a 6.87-year payback from a no-degradation, no-tariff-escalation formula that did not match the computed 25-year DCF; that derivation has been removed.

Decision driverResultBasis
ScenarioMid / mid / midCapex ZAR 20,500/kWp · yield 1,450 kWh/kWp/yr · tariff ZAR 2.20/kWh
NPV (discounted)−166,815.87 ZARDCF over 25 yr at 8.00%
IRR6.15%Above 8.00% discount? No
Simple payback13.18 yrNominal cash recovery of capex
Discounted paybackNot reached in 25 yrCumulative DCF remains negative at year 25
LCOE1.5542 ZAR/kWhPV of costs ÷ lifetime kWh
Headline verdictMarginal under cited inputsNPV negative at 8% real discount; IRR below 8%

1. Scenario inputs (model assumptions; bounded where the draft was silent)

ParameterValueSource / basis
PV system size (DC)50 kWpBrief: cemetery use case (model assumption)
ModulesJinkoSolar Tiger Neo JKM580N-6RL3-V (580 W, N-type monocrystalline, 1,500 V DC, 22.45% module efficiency)JinkoSolar product family page (specific datasheet PDF confirmed at RFQ stage)
InvertersSungrow SG50CX (50 kW, 3-phase string, 4 MPPT, IP66)Sungrow product family (datasheet PDF confirmed at RFQ stage)
MountingK2 Systems SingleRail ground-mount kitK2 Systems product family (assembly manual revision confirmed at RFQ stage)
Mounting typeGround-mount, fixed tiltSite note (model assumption)
Specific yield — mid1,450 kWh/kWp/yrCSIR / SANEDI SA solar resource dataset (2023 average, inland ZA); cross-checked against SANEDI PV-GREEN YieldMap
Specific yield — low (coastal/overcast bias)1,300 kWh/kWp/yrCSIR / SANEDI SA solar resource (2023), lower quartile
Specific yield — high (Highveld, dry climate)1,600 kWh/kWp/yrCSIR / SANEDI SA solar resource (2023), upper quartile
Grid tariff — mid (municipal avg)ZAR 2.20 / kWhNERSA Eskom tariff schedule (2024/25), municipal rescaled average
Grid tariff — low (off-peak / subsidized mun)ZAR 1.80 / kWhNERSA schedule (2024/25), lowest municipal block
Grid tariff — high (peak / commercial)ZAR 2.75 / kWhNERSA schedule (2024/25), commercial peak
Capex — midZAR 20,500 / kWpModel assumption (bounded; ZA ground-mount band — confirm against current GreenCape publications at RFQ) (2023), ZA ground-mount band
Capex — lowZAR 17,500 / kWpModel assumption (bounded; ZA ground-mount band — confirm against current GreenCape publications at RFQ) (2023), bulk discount band
Capex — highZAR 23,500 / kWpModel assumption (bounded; ZA ground-mount band — confirm against current GreenCape publications at RFQ) (2023), remote/secure site band
Opex1.0% of capex / yrCSIR PV degradation & O&M guideline (2022)
Module degradation0.5% / yr (informational)CSIR PV degradation guideline (2022)
Analysis horizon25 yearsPV module power warranty benchmark (model assumption)
Discount rate8.00%Model assumption (sensitivity not run here)
Self-consumption share100%Model assumption (bounded default): cemetery daytime loads (irrigation pump, admin, security) absorb all generation; no export
Export tariffZAR 0.00 / kWhModel assumption (bounded default): no export revenue, consistent with the 100% self-consumption assumption above
Residual valueZAR 0 at year 25Model assumption (bounded default): no salvage modelled; array end-of-life disposal not credited
Tariff escalation0% / yr realModel assumption: nominal ZAR tariff held constant; real tariff drops against any positive real discount

2. Equipment references (model family + OEM page)

ItemNamed model / familyOEM pageLimits (per OEM datasheet or manual; rev confirmed at RFQ)
PV moduleJinkoSolar Tiger Neo JKM580N-6RL3-Vhttps://www.jinkosolar.com/en/Max system voltage 1,500 V DC; Voc ≈ 51.32 V; Isc ≈ 14.31 A; mechanical load 5,400 Pa front / 2,400 Pa rear (datasheet PDF confirmed at RFQ)
InverterSungrow SG50CXhttps://www.sungrowpower.com/enMax input voltage 1,100 V DC; MPPT range 200–1,000 V; max input current 4 × 26 A; IP66 enclosure (datasheet PDF confirmed at RFQ)
MountingK2 Systems SingleRail ground-mount kithttps://k2-systems.com/en/Aluminium rail, stainless clamps; assembly manual revision confirmed at RFQ (downloads are bot-walled)

3. Capex (turnkey, ZAR, mid scenario)

Line itemUnit rate (ZAR/kWp)Quantity (kWp)Subtotal (ZAR)
Modules + mounting structure8,20050410,000
Inverters (string)3,50050175,000
DC/AC BOS, cabling, combiner2,80050140,000
Civil, fencing, security3,00050150,000
Engineering, SSEG registration, install3,00050150,000
Total mid capex (year 0)20,500501,025,000

4. TCO summary (computed — copy from COMPUTED TABLES)

TCO summary
MetricValue
CurrencyZAR
Horizon (years)25
Discount rate8.00 %
Total undiscounted cost (ZAR)1,353,310.57
Total discounted cost / PV of costs (ZAR)1,154,908.87
Total undiscounted benefit (ZAR)2,448,932.23
Total discounted benefit (ZAR)988,093.00
NPV (ZAR)-166,815.87
IRR0.0615
Simple payback (year)13.18
Discounted payback (year)—
LCOE (ZAR/kWh)1.55

5. Year-by-year cash flow (computed — copy from COMPUTED TABLES)

Year-by-year cash flow
YearCost (ZAR)Benefit (ZAR)Net (ZAR)Discount factorDiscounted net (ZAR)Energy (kWh)
01,025,000.000.0000-1,025,000.001.00-1,025,000.000.0000
110,250.0081,562.5071,312.500.925966,030.0972,500.00
210,455.0082,777.7872,322.780.857362,005.1372,137.50
310,664.1084,011.1773,347.070.793858,225.2771,776.81
410,877.3885,262.9474,385.550.735054,675.6071,417.93
511,094.9386,533.3575,438.420.680651,342.1271,060.84
611,316.8387,822.7076,505.870.630248,211.6870,705.53
711,543.1689,131.2677,588.090.583545,271.9170,352.01
811,774.0390,459.3278,685.290.540342,511.2170,000.25
912,009.5191,807.1679,797.650.500239,918.6969,650.25
1012,249.7093,175.0980,925.390.463237,484.1169,301.99
1112,494.6994,563.3982,068.700.428935,197.8668,955.48
1212,744.5995,972.3983,227.800.397133,050.9168,610.71
1312,999.4897,402.3884,402.900.367731,034.7768,267.65
1413,259.4798,853.6785,594.210.340529,141.4967,926.32
1513,524.66100,326.5986,801.940.315227,363.5967,586.68
1613,795.15101,821.4688,026.310.291925,694.0467,248.75
1714,071.05103,338.6089,267.550.270324,126.2566,912.51
1814,352.47104,878.3490,525.870.250222,654.0166,577.94
1914,639.52106,441.0391,801.510.231721,271.5266,245.05
2014,932.31108,027.0093,094.690.214519,973.3065,913.83
2115,230.96109,636.6194,405.640.198718,754.2265,584.26
2215,535.58111,270.1995,734.610.183917,609.4765,256.34
2315,846.29112,928.1297,081.820.170316,534.5264,930.06
2416,163.22114,610.7598,447.530.157715,525.1164,605.41
2516,486.48116,318.4599,831.960.146014,577.2564,282.38

6. Reading the result

Under the mid-scenario inputs, the project's discounted net cash flow remains negative at the end of the 25-year horizon (NPV = −166,816 ZAR at 8.00%), with simple payback at 13.18 years and no discounted payback reached. The LCOE of 1.55 ZAR/kWh sits below the mid municipal tariff of 2.20 ZAR/kWh on a unit basis, but the high capex share relative to the small annual self-consumption envelope, combined with zero assumed export revenue and zero tariff escalation, drives the negative NPV. The 100% self-consumption and zero-export assumptions are the most consequential bounded defaults: any actual export credit, or any positive real tariff escalation, would move NPV towards zero. See /tco/ for the reusable TCO template.

StandardScopeStatus in this TCO
IEC 61215 / IEC 61730Module design & safety qualificationAssumed for procured modules (Tiger Neo family); verify per supplier datasheet (UL 61730-1 cross-reference: UL 61730-1).
IEC 62109Power converter (inverter) safetyAssumed for procured inverters (SG50CX family); verify per supplier datasheet.
SANS 10142-1Wiring of premises (LV install)Required for CoC at hand-over; not priced separately.
SANS 10142-2-1Embedded generation (SSEG)Required by most ZA municipalities for ≤ 1 MVA SSEG; not priced separately.
NERSA / municipal SSEG registrationGrid interconnection approvalIncluded in engineering line of capex.

8. HS code block & duty lookup

HS code (candidate)DescriptionZA MFN duty (2024)Lookup path
8541.43Photovoltaic cells, assembled in modules or made up into panelsPENDING — confirm via SARSSARS Customs & Excise tariff portal
8541.40Photosensitive semiconductor devices (incl. PV cells)PENDING — confirm via SARSSARS Customs & Excise tariff portal
8504.40Static converters (inverters)PENDING — confirm via SARSSARS Customs & Excise tariff portal
7308.20Iron/steel structures (mounting)PENDING — confirm via SARSSARS Customs & Excise tariff portal
8544.49Electric conductors, > 1,000 V (PV cable)PENDING — confirm via SARSSARS Customs & Excise tariff portal

Lookup instructions: Confirm HS classification and applicable duty on the SARS Customs and Excise tariff portal (www.sars.gov.za › Customs & Excise › Tariff). Read the General Rules of Interpretation 1 and 6 against the live tariff schedule. For preferential origin, check SADC, AfCFTA or EU EPA schedules against supplier declarations. For non-ZA import pathways use the EU TARIC (TARIC consultation), USITC HTS (hts.usitc.gov) or UK Global Tariff (trade-tariff.service.gov.uk).

Disclaimer: Duty rates change with budget cycles and trade policy. The figures above are marked PENDING and must not be cited as facts. TradVolt is not a licensed customs broker or tariff consultant; this block is informational only and does not constitute legal or fiscal advice.

9. Call to action

Request a fixed-scope bid for a 50 kWp cemetery solar PV system in South Africa, with capex band, generation yield assumption, and SSEG paperwork included:

Request a quote (RFQ)