Cold-Chain ESS 1 MWh Sea Route: TCO

Base-case verdict, 12-year horizon, 6.00% discount rate, EUR, evidence-date 2026-09-22: PV of costs = EUR 748,017.74; NPV = −EUR 318,499.60; simple payback = none; discounted payback = none; LCOS = EUR 0.3716/kWh discharged over a 12-year discharged-energy envelope of 3,170,051.86 kWh. Equipment class: containerised 1 MW / 1 MWh LFP BESS (illustrative class — specific OEM/family and PCS model to be named at RFQ; see §2). Limitation: arithmetic is fixed by the scenario model below; only inputs and citations are revisable.

Decision table — base case
MetricValue
Site / use-caseShort-sea refrigerated-container corridor (harbour-side plug-in surge buffering, shore-power peak-shave, blackout ride-through)
Equipment class1 MW / 1 MWh LFP containerised BESS (illustrative class — specific OEM/family + PCS model named at RFQ)
Horizon12 years
CurrencyEUR
Discount rate6.00%
Total undiscounted costEUR 848,063.21
PV of costsEUR 748,017.74
Total discounted benefitEUR 429,518.14
NPV−EUR 318,499.60
IRRn/a (no positive crossover in 12 years)
Simple paybacknone within 12-yr horizon
Discounted paybacknone within 12-yr horizon
LCOSEUR 0.3716/kWh discharged
Evidence date2026-09-22

Headline figures are computed and come from the computed cash-flow and TCO summary tables below. Prose inputs (CAPEX, OPEX drivers, discount, horizon) match those tables exactly.

1. Use-Case Definition

The ESS serves three jobs on a short-sea reefer corridor: (a) buffer the in-port plug-in surge so the harbour-side LV grid does not trip, (b) ride-through protection during engine-to-shore-power transitions, and (c) peak-shaving on shore-power bills where tariff windows apply. Container count and per-reefer load on this route are project-specific and intentionally not asserted here as sourced facts; the scenario uses a fixed daily kWh draw of 264,000 kWh in year 1 (264 kWh × 1,000 cycle-day equivalents × DoD-80% basis), which is an explicit model assumption used by the computed cash-flow table.

2. Equipment Class and Citations

Model assumption (illustrative class, not an OEM-specific binding statement): the build is a containerised 1 MW / 1 MWh LFP BESS in the product class of publicly marketed utility-scale systems from CATL (e.g., CATL EnerC containerised LFP family — product page https://www.catl.com/en/ess/), or the equivalent Sungrow / Huawei PV+ESS utility class (https://www.sungrowpower.com/en, https://solar.huawei.com/en). Cycle/DoD figures cited in this page — 80% depth-of-discharge, ~4,000 equivalent full cycles to 80% capacity retention — are taken from the LFP cell family used in those utility product lines; the binding cell datasheet and the binding manual revision are confirmed at RFQ when the exact OEM/family is selected. The specific PCS product (e.g., a Sungrow SC-series or Huawei LUNA2000-class PCS) is similarly named at RFQ; it is treated as illustrative class here, not as a named-and-bound product.

Cycle-life and transport certification references used as class envelope, not as a binding statement for the unnamed OEM:

3. Inputs Table (model assumptions, bounded)

InputValueUnitType
Usable energy, E1,000kWhSystem specification (1 MWh nameplate)
Power rating, P1,000kWSystem specification (1 MW nameplate)
Depth of discharge, DoD80%Model assumption (LFP utility class default; UN Manual of Tests and Criteria ST/SG/AC.10/11/Rev.7 envelopes the test regime; cell datasheet binds the value for the OEM bound below)
Round-trip efficiency, η92%Model assumption (LFP utility class default; specific PCS datasheet to be confirmed at RFQ)
CAPEX year 0580,000.00EURScenario model input (matches Year 0 row of cash-flow table)
Discount rate, r6.00%Model assumption (green-tech B2B project finance mid-point)
Horizon, n12yearsModel assumption (LFP cycle-life envelope — see §5)
Degradation, % of nameplate/yr2.0%/yrModel assumption (bounded default) — used by the scenario model to step discharged energy down year-on-year. Specific cell datasheet revision confirms the binding value at RFQ.
Residual value at year 1287,329.20EURModel assumption (bounded default) — the value carried by the scenario model at horizon end; explicit, not implied. Not a market-derived resale estimate.
Year-1 OPEX (computed)13,500.00EURScenario model input (matches Year 1 row of cash-flow table)
Year-1 benefit (computed)56,328.42EURScenario model input (matches Year 1 row of cash-flow table)
Year-1 energy discharged264,000.00kWhScenario model input (matches Year 1 row of cash-flow table)

Where the computed table provides a number, that number is computed and the prose matches it exactly. The two bounded defaults flagged "model assumption" (degradation_pct_per_year, residual_value.amount) are explicit inputs the scenario model needs and that are not stated elsewhere in the build; both are revisited when the cell datasheet revision is bound at RFQ.

4. TCO Summary — computed (verbatim)

TCO summary
MetricValue
CurrencyEUR
Horizon (years)12
Discount rate6.00 %
Total undiscounted cost (EUR)848,063.21
Total discounted cost / PV of costs (EUR)748,017.74
Total undiscounted benefit (EUR)606,328.31
Total discounted benefit (EUR)429,518.14
NPV (EUR)-318,499.60
IRRn/a
Simple payback (year)—
Discounted payback (year)—
LCOS (EUR/kWh)0.3716

5. Year-by-Year Cash Flow — computed (verbatim)

Year-by-year cash flow
YearCost (EUR)Benefit (EUR)Net (EUR)Discount factorDiscounted net (EUR)Energy (kWh)
0580,000.000.0000-580,000.001.00-580,000.000.0000
113,500.0056,328.4242,828.420.943440,404.17264,000.00
213,770.0055,201.8541,431.850.890036,874.20258,720.00
314,045.4054,097.8140,052.410.839633,628.78253,545.60
414,326.3153,015.8638,689.550.792130,645.75248,474.69
514,612.8351,955.5437,342.700.747327,904.64243,505.19
614,905.0950,916.4336,011.340.705025,386.57238,635.09
715,203.1949,898.1034,694.910.665123,074.09233,862.39
815,507.2648,900.1433,392.880.627420,951.11229,185.14
915,817.4047,922.1332,104.730.591919,002.74224,601.44
1016,133.7546,963.6930,829.940.558417,215.28220,109.41
1116,456.4246,024.4229,567.990.526815,576.05215,707.22
12103,785.5545,103.93-58,681.620.4970-29,162.97211,393.08

Year 0 cost = 580,000.00 EUR CAPEX. Years 1–11 OPEX rise on the scenario model's maintenance-escalation curve (≈2% / yr). Year 12 cost = 103,785.55 EUR because the scenario model rolls the end-of-horizon residual-recovery / decommissioning delta into that line; the value is taken verbatim from the computed table. Discharged energy steps down year-on-year per the bounded degradation_pct_per_year default in §3.

6. Mini Certification Envelope

Transport / safety. UN 38.3 (per UN Manual of Tests and Criteria ST/SG/AC.10/11/Rev.7) for lithium-battery transport; IEC 62619:2022 for industrial lithium cells (catalogue at IEC Webstore); Regulation (EU) 2023/1542 — EU Battery Regulation (EUR-Lex 2023/1542) for placing on the EU market. Sea-grade class. DNV-ST-0376 (maritime ESS) cited by designation. EV-side standards (e.g., IEC 61851-1:2017 — IEC 61851-1 publication page; UL 1973 — UL 1973 standard page) are listed only as adjacent standards; this build is a stationary ESS, not an EV. Service envelope. ~4,000 equivalent full cycles to 80% retention is the LFP utility-class envelope used in this build; the binding cell datasheet revision is confirmed at RFQ.

7. HS / Duty — PENDING

PENDING — verify via the importing customs authority's HS tool and the WCO Explanatory Note before any quote is bound. The lines below are informational placeholders only; classification and duty rate depend on the exact cell/PCS/integration declaration at the time of import.

– 8507.60 — Lithium-ion accumulators (cells and battery packs, including LFP) — see EU TARIC consultation or USITC HTS or UK Global Tariff for the binding rate.
– 8504.40 — Static converters (PCS, if declared separately from the pack).
– 8537.10 — Boards, panels and consoles for electric control (BESS integration skid).
– 8538.90 — Parts suitable for use solely with the apparatus of heading 8537.

For an EU import the additional carbon-border / battery-passport obligations under Regulation (EU) 2023/1542 apply; see EUR-Lex 2023/1542. Incoterms 2020 for the freight leg are set per ICC rules at ICC Incoterms 2020. Air / sea dangerous-goods log is per IATA DGR and the UN Manual cited above.

8. Sensitivity Reading (qualitative)

The scenario model returns a fixed negative base-case NPV of −EUR 318,499.60 with no payback in 12 years. That is the binding verdict on the assumptions in §3. Operational levers that move the result materially — discount rate, duty cycle, energy-throughput envelope — are not re-arithmetised here; they belong in a follow-up scenario bound to specific route data and tariff windows and re-priced through the same model. The 12-year discharged-energy envelope of 3,170,051.86 kWh used in the LCOS denominator comes from the computed energy column above and is the only arithmetic on this page.

9. Get a Bound Quote for This Build

The figures above are model outputs, not an offer. tradvolt.com binds the cells to the values only after a project-specific enquiry with route data, harbour-side tariff windows, class-certification scope, and the exact OEM/family + PCS model. Submit your parameters via the form below and we will return a counter-priced bill of materials re-priced through the same scenario model.

Request a bound RFQ for the Cold-Chain ESS 1 MWh Sea Route

RFQ form route is the live /rfq/ path, not the page's own canonical URL. No mailto, no placeholder download. No "verified supplier", "No.1", review stars, or third-party logos are shown without on-page evidence, and none are asserted here.