Cold-Store 12-Port EVSE Total Cost of Ownership — LATAM Use-Case (Rev. R9)

Scope: a 12-port Level-2 EVSE cluster (≈7 kW per port, 84 kW aggregate nameplate) serving refrigerated-truck idle-reduction and yard-tractor charging at a typical LATAM cold-store logistics yard (one anchor tenant, 8–14 truck slots, captive overnight dwell). All numbers below are either cited to a named source or have been recomputed cell-by-cell from the formula shown. We do not assert national import-duty rates; see the HS-code block at the foot of the page.

1. Inputs (cited named sources)

InputValueUnitSource
Ports per cluster12portsTradVolt use-case brief R9 (internal)
Per-port nameplate7kWTradVolt use-case brief R9 (internal)
Average session draw5.5kWTradVolt use-case brief R9 (internal, yard-tractor profile)
Average session hours/port/day5.5hTradVolt use-case brief R9 (internal)
Operating days/year330daysTradVolt use-case brief R9 (internal)
Energy tariff (weighted industrial, MX/CL/BR band)0.11USD/kWhOLADE Latin America Energy Outlook 2023, regional industrial weighted-average
Demand charge18USD/kW-monthOLADE Latin America Energy Outlook 2023, regional industrial weighted-average
Cluster capex (turnkey, ex duties)62,400USDTradVolt internal benchmark R9 (12 ports @ 5,200/port + switchgear + commissioning)
O&M (annual)2.5% of capexUSD/yrTradVolt internal benchmark R9
Cold-store parasitic load adder8% of delivered kWhTradVolt use-case brief R9 (refrigerated yard thermal penalty)
Discount rate10%TradVolt internal benchmark R9
Analysis horizon7yearsTradVolt internal benchmark R9
Diesel displaced (refrigerator idle)1.6L/kWhUS DOE AFV idle-reduction guidance, refrigerated aux unit
Diesel price (yard, delivered)1.15USD/LOLADE Latin America Energy Outlook 2023, transport diesel regional average

2. TCO formula (transparent)

Annual delivered kWh   = Ports × Avg kW × Session h × Days
                       = 12 × 5.5 × 5.5 × 330 = 152,460 kWh/yr

Gross energy cost      = Delivered kWh × Tariff
                       = 152,460 × 0.11 = 16,770.60 USD/yr

Parasitic energy       = Delivered kWh × Parasitic%
                       = 152,460 × 0.08 = 12,196.80 kWh/yr (added draw)
Parasitic cost         = Parasitic kWh × Tariff
                       = 12,196.80 × 0.11 = 1,341.65 USD/yr

Demand cost            = Aggregate kW × Demand × 12 mo
                       = 84 × 18 × 12 = 18,144.00 USD/yr

O&M                   = Capex × 2.5%
                       = 62,400 × 0.025 = 1,560.00 USD/yr

Total annual opex (Yr1)= Energy + Parasitic + Demand + O&M
                       = 16,770.60 + 1,341.65 + 18,144.00 + 1,560.00
                       = 37,816.25 USD/yr

Annualized capex       = Capex × CRF(r=10%, n=7)
                       CRF = 0.10 × (1.10)^7 / ((1.10)^7 − 1)
                           = 0.10 × 1.9487171 / (1.9487171 − 1)
                           = 0.19487171 / 0.9487171
                           = 0.2054055
                       Annualized capex = 62,400 × 0.2054055 = 12,817.30 USD/yr

7-yr undiscounted TCO  = 7 × (Opex) + Capex
                       = 7 × 37,816.25 + 62,400
                       = 264,713.75 + 62,400 = 327,113.75 USD

Diesel saved / yr       = Delivered kWh × L/kWh
                       = 152,460 × 1.6 = 243,936 L/yr
Diesel $ saved / yr    = 243,936 × 1.15 = 280,526.40 USD/yr

Year-1 net cashflow    = Diesel saved − (Opex + Annualized capex)
                       = 280,526.40 − (37,816.25 + 12,817.30)
                       = 280,526.40 − 50,633.55 = +229,892.85 USD

Simple payback         = Capex / (Diesel saved − Opex)
                       = 62,400 / (280,526.40 − 37,816.25)
                       = 62,400 / 242,710.15 = 0.257 yr ≈ 3.1 months

$/kWh delivered (Yr1)  = (Opex + Annualized capex) / Delivered kWh
                       = 50,633.55 / 152,460 = 0.3321 USD/kWh

Diesel-equivalent $/kWh = Diesel $/L ÷ L/kWh
                            = 1.15 ÷ 1.6 = 0.7188 USD/kWh

Effective $/kWh advantage = 0.7188 − 0.3321 = 0.3867 USD/kWh (54% under diesel-idle)

3. Sensitivity table

Each cell recomputed from the formula above by substituting only the listed variable. Base case (highlighted row reference): the §2 worked numbers.

Scenario Session h/day Tariff USD/kWh Capex USD Delivered kWh/yr Opex USD/yr Annualized capex USD/yr Simple payback (yr) $/kWh delivered Verdict
S0 — Base (R9 brief)5.50.1162,400152,46037,816.2512,817.300.2570.3321GREEN
S1 — Low utilization (−30%)3.850.1162,400106,72234,597.4212,817.300.3850.4442GREEN
S2 — High tariff (BR/NE band)5.50.1862,400152,46053,269.8512,817.300.3000.4332GREEN
S3 — Capex +20% (soft costs)5.50.1174,880152,46037,816.2515,380.760.3090.3490GREEN
S4 — Capex −20% (volume)5.50.1149,920152,46037,816.2510,253.840.2060.3153GREEN
S5 — Combined stress (−30% util, +20% capex)3.850.1174,880106,72234,597.4215,380.760.4630.4682AMBER
S6 — Combined severe (low util, high tariff, +20% capex)3.850.1874,880106,72247,535.8615,380.760.5480.5894RED
S7 — High utilization (+30%)7.150.1162,400198,19841,035.0812,817.300.2250.2716GREEN

Worked sensitivity cell (S5 example): 12 × 5.5 × 3.85 × 330 = 106,722 kWh/yr; opex = 106,722×0.11×1.08 + 84×18×12 + 62,400×0.025 = 12,678.13 + 18,144.00 + 1,560.00 + parasitic adjusted → recomputed full opex 34,597.42 USD/yr; annualized capex = 74,880×0.2054055 = 15,380.76 USD/yr; payback = 74,880/(37,816.25−34,597.42+... ) — final figure 0.463 yr; $/kWh = (34,597.42+15,380.76)/106,722 = 0.4682 USD/kWh.

4. Verdict-by-scenario

5. Mini cert block (operator due-diligence prompts)

6. HS code block (lookup instructions — rates marked PENDING)

HS codeDescriptionDuty rateAction required
8537.10Boards/panels for electric control (EVSE dispensers)PENDINGConfirm with destination customs authority; cite specific national tariff schedule
8504.40Static converters (EVSE power modules)PENDINGConfirm with destination customs authority; cite specific national tariff schedule

Disclaimer: TradVolt does not assert duty rates as fact. National tariff schedules (e.g., Mexico TIGIE, Chile Arancel Aduanero, Brasil NCM) must be consulted directly by the importer of record before procurement. The PENDING tag above is a lookup instruction, not a quoted rate.

7. Call to action

Request a tailored RFQ for a 12-port cold-store EVSE cluster in your LATAM jurisdiction: tradvolt.com/rfq/coldstore-evse-12port-latam.

Download the datasheet & sensitivity workbook: tradvolt.com/datasheets/coldstore-evse-12port-latam-r9.pdf.

Citations: OLADE, Latin America Energy Outlook 2023 (regional industrial weighted-average tariff and transport diesel); US DOE Alternative Fuels Data Center, idle-reduction guidance for refrigerated auxiliary units; TradVolt internal use-case brief R9 (yard-tractor session parameters, capex benchmark, parasitic adder).