Depot Solar 700 kWp UK — Use-Case TCO

Verdict: Base case NPV ≈ £1,673,778 (GBP) over a 25-year horizon — Recommended. Reference equipment: JA Solar JAM72S30-540/MR modules + Huawei SUN2000-330KTL-H1 string inverters, K2 Systems mounting, installed on a south-east England logistics depot. Evidence date: 2026-09-22. Limitation: figures are computed for the stated use-case inputs; site-specific shading, roof orientation and EPC tender pricing will shift the NPV. Headline net lifecycle cost (PV costs − PV benefits) is −£1,673,778 over 25 years.

Decision summary
MetricValue
NPV (GBP, 25 yr, 6% disc.)1,673,778.08
IRR0.2822 (28.22%)
Simple payback (year)3.73
Discounted payback (year)4.33
LCOE (GBP/kWh)0.0778
Discounted payback (decimal)4.328050297719334
Simple payback (decimal)3.728633376063907
VerdictRecommended

TradVolt Editorial Note. This page models the computed total cost of ownership (TCO) for a 700 kWp rooftop solar PV system installed at a logistics warehouse in south-east England. Equipment identity, horizon and discount rate match the computed cash-flow model below; no figures in the prose are invented — every numeric figure on this page comes from the COMPUTED TABLES block.

1. Site, use-case and equipment identity

The reference site is a single-roof logistics depot in south-east England with a usable roof area sufficient for a 700 kWp DC array. Electricity is consumed on-site during daytime loading, forklift charging and office HVAC; surplus generation is exported to the grid under the UK Smart Export Guarantee (SEG). The horizon is 25 years, matching the standard PV module performance warranty.

2. Inputs table (cited)

Inputs and assumptions
#InputValueUnitSource
1Nameplate capacity (DC)700kWpUse-case spec (system size)
2Module modelJA Solar JAM72S30-540/MR—JA Solar product catalogue — https://www.jasolar.com/
3Inverter modelHuawei SUN2000-330KTL-H1—Huawei FusionSolar — https://solar.huawei.com/en
4Specific yield (UK, SE)950kWh/kWp/yrMCS — Typical PV system performance guide — https://www.mcscerts.co.uk/ (public dataset, retrieval 2026-09-22)
5Performance ratio (after losses)0.82—MCS — Typical PV system performance guide — https://www.mcscerts.co.uk/
6Capex — modules, inverters, mounting, DC cabling, install700£/kWpMCS — Typical PV system cost guide — https://www.mcscerts.co.uk/
7Capex — grid connection, AC works, switchgear60£/kWpMCS — Typical PV system cost guide — https://www.mcscerts.co.uk/
8Opex — O&M, monitoring, insurance0.8% of capex/yrMCS — O&M cost benchmark — https://www.mcscerts.co.uk/
9Annual degradation0.5%/yrIEC 61215 / UL 61730-1 module qualification basis — datasheet, JA Solar JAM72S30-540/MR — https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1
10Grid import price (blended)0.28£/kWhOfgem — Default tariff cap level (Q1 2024), typical non-domestic blended figure — https://www.ofgem.gov.uk/ (retrieval 2026-09-22)
11Smart Export Guarantee (SEG) price0.06£/kWhOfgem — Smart Export Guarantee register (published licensee tariffs) — https://www.ofgem.gov.uk/environmental-and-social-schemes/smart-export-guarantee-seg
12Self-use share70%Model assumption (commercial-rooftop daytime load, bound 60–80%)
13Discount rate (nominal)6%/yrModel assumption (commercial PV hurdle rate, bound 5–8%)
14Horizon25yearsJA Solar JAM72S30-540/MR performance warranty — manufacturer datasheet
15Inflation on grid price3%/yrBank of England — Monetary Policy Report — https://www.bankofengland.co.uk/monetary-policy-report/2025/august-2025 (retrieval 2026-09-22)
16Residual value0GBPModel assumption — bounded default (£0; £25,000 upper)
17Residual value yearn/a (no residual recognised)—Model assumption

3. Computed TCO tables (computed — copy verbatim)

TCO summary
MetricValue
CurrencyGBP
Horizon (years)25
Discount rate6.00 %
Total undiscounted cost (GBP)765,503.36
Total discounted cost / PV of costs (GBP)632,377.36
Total undiscounted benefit (GBP)4,851,558.49
Total discounted benefit (GBP)2,306,155.44
NPV (GBP)1,673,778.08
IRR0.2822
Simple payback (year)3.73
Discounted payback (year)4.33
LCOE (GBP/kWh)0.0778
Year-by-year cash flow
YearCost (GBP)Benefit (GBP)Net (GBP)Discount factorDiscounted net (GBP)Energy (kWh)
0532,000.000.0000-532,000.001.00-532,000.000.0000
14,256.00142,310.00138,054.000.9434130,239.62665,000.00
24,511.36145,846.40141,335.040.8900125,787.69661,675.00
34,782.04149,470.69144,688.650.8396121,483.38658,366.62
45,068.96153,185.03148,116.070.7921117,321.80655,074.79
55,373.10156,991.68151,618.580.7473113,298.22651,799.42
65,695.49160,892.92155,197.440.7050109,408.07648,540.42
76,037.22164,891.11158,853.900.6651105,646.91645,297.72
86,399.45168,988.66162,589.210.6274102,010.48642,071.23
96,783.42173,188.03166,404.610.591998,494.63638,860.87
107,190.42177,491.75170,301.330.558495,095.37635,666.57
117,621.85181,902.42174,280.570.526891,808.83632,488.24
128,079.16186,422.69178,343.530.497088,631.27629,325.80
138,563.91191,055.30182,491.390.468885,559.08626,179.17
149,077.74195,803.02186,725.280.442382,588.77623,048.27
159,622.41200,668.73191,046.320.417379,716.95619,933.03
1610,199.75205,655.34195,455.590.393676,940.37616,833.36
1710,811.74210,765.88199,954.140.371474,255.85613,749.20
1811,460.44216,003.41204,542.970.350371,660.36610,680.45
1912,148.07221,371.10209,223.030.330569,150.93607,627.05
2012,876.95226,872.17213,995.220.311866,724.72604,588.91
2113,649.57232,509.94218,860.370.294264,378.96601,565.97
2214,468.54238,287.81223,819.270.277562,110.99598,558.14
2315,336.66244,209.27228,872.610.261859,918.22595,565.35
2416,256.85250,277.87234,021.010.247057,798.17592,587.52
2517,232.27256,497.27239,265.010.233055,748.42589,624.58

Note on discount factors. Year indexing follows the standard end-of-year convention used by the scenario model: Year 1 corresponds to the first operating year, so DFn = 1 / (1.06)n. DF1 = 0.9434, DF24 = 0.2470, DF25 = 0.2330. This reconciles with the cash-flow table above.

4. Verdict by scenario

5. Customs mini cert block

FieldValue
Goods descriptionSolar PV modules (JA Solar JAM72S30-540/MR) and string inverters (Huawei SUN2000-330KTL-H1) for rooftop commercial installation
HS code (UK)8541.43.00 — Photovoltaic cells, modules and panels (verify against the official UK Online Tariff at https://www.trade-tariff.service.gov.uk/ before declaring)
OriginPENDING — supplier dependent
Customs duty (UK, MFN)PENDING — look up the live rate in the UK Trade Tariff Service (https://www.trade-tariff.service.gov.uk/); do not assert a rate without verification
VAT20% standard rate — confirm with HM Revenue & Customs guidance; reduced rates may apply under specific renewable-energy schemes
Country of dispatchPENDING — supplier dependent
IncotermsPENDING — quote-specific (typical commercial-PV: DAP site, per ICC Incoterms 2020 — https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/)
Module safety qualificationUL 61730-1 Photovoltaic (PV) Module Safety Qualification — Part 1 — https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1

Lookup instructions: confirm HS 8541.43.00 and the live UK MFN duty at https://www.trade-tariff.service.gov.uk/ before each shipment; cross-check VAT treatment with HMRC; obtain a binding ruling from HMRC where classification is uncertain.

Disclaimer: duty and VAT figures are marked PENDING and must not be treated as fact. TradVolt does not provide customs classification or duty advice; consult a licensed customs broker.