Verdict (base case): 700 kWp rooftop PV at a US logistics depot, 25-yr horizon, 7.00% discount — GO. LCOE 0.0808 USD/kWh vs. 0.14 USD/kWh site tariff (−42%); NPV 832,974 USD; simple payback 6.24 yr; discounted payback 8.34 yr; IRR 16.45%. Evidence-date: 2026-09-22. Limitation: capex, yield and tariff use bounded single-point benchmarks from the cited NREL PVWatts location report, AEO table and EIA Electric Power Monthly table; modelled as deterministic — no Monte-Carlo, no financing constraints, no Section 201 / Section 301 / AD-CVD add-on resolution (those are importer-side and must be re-pulled at time of entry).
| Metric | Value |
|---|---|
| LCOE | 0.0808 USD/kWh |
| NPV (25 yr) | 832,974 USD |
| Simple payback | 6.24 yr |
| Discounted payback | 8.34 yr |
| IRR | 16.45% |
| PV of costs (NPC) | 852,972 USD |
| PV of benefits | 1,685,946 USD |
| vs. 0.14 USD/kWh tariff | −42% (favourable) |
Logistics-depot rooftop PV, US site. Worked TCO with formula, sensitivity grid, equipment-family specification and import-classification pointers. Re-published after review with verified computed tables, separated citation block, and re-reconciled sensitivity.
| Component | Family / model class assumed | Datasheet / product URL |
|---|---|---|
| PV modules | LONGi Hi-MO 5 / Hi-MO 6 tier — bifacial monocrystalline PERC / HPBC, 540–560 Wp class, 144-cell half-cut | https://www.longi.com/en/ |
| String inverters | Sungrow SGxxCX / Huawei SUN2000-60KTL-M0 tier — three-phase, 8–12 MPPT, 1,500 V DC topology (here modelled at the project ratio, not 1:1) | https://www.sungrowpower.com/en ; https://solar.huawei.com/en |
| DC optimiser (optional) | SolarEdge P-series or Huawei SUN2000 smart module-controller tier — module-level MPPT | https://solar.huawei.com/en |
| Mounting structure | K2 Systems SingleRail / SolidRail aluminium rail + roof-attach kit for trapezoidal / standing-seam metal roof (typical US logistics-depot roof) | https://k2-systems.com/en/ |
| OEM manual title (limits source) | Mounting structural limits: K2 Systems base planning guide for SingleRail / SolidRail family — torque, ballast and span tables per roof-attach kit revision (confirmed at RFQ). Inverter AC/DC voltage windows and MPPT range: Sungrow / Huawei product datasheet revision current at order date. | |
Final make/model/datasheet-revision and torque/SOC/voltage windows are locked at RFQ submission against the OEM product page above. The model assumes the listed module wattage tier (540–560 Wp), 1,500 V DC string-inverter topology, and aluminium rail racking on metal-deck roof; deviation is a model assumption to be re-priced.
| Metric | Value |
|---|---|
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 7.00 % |
| Total undiscounted cost (USD) | 961,507.39 |
| Total discounted cost / PV of costs (USD) | 852,971.55 |
| Total undiscounted benefit (USD) | 3,868,206.54 |
| Total discounted benefit (USD) | 1,685,945.76 |
| NPV (USD) | 832,974.21 |
| IRR | 0.1645 |
| Simple payback (year) | 6.24 |
| Discounted payback (year) | 8.34 |
| LCOE (USD/kWh) | 0.0808 |
| Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 770,000.00 | 0.0000 | -770,000.00 | 1.00 | -770,000.00 | 0.0000 |
| 1 | 3,850.00 | 120,960.00 | 117,110.00 | 0.9346 | 109,448.60 | 945,000.00 |
| 2 | 3,946.25 | 123,364.08 | 119,417.83 | 0.8734 | 104,304.16 | 940,275.00 |
| 3 | 4,044.91 | 125,815.94 | 121,771.03 | 0.8163 | 99,401.44 | 935,573.62 |
| 4 | 4,146.03 | 128,316.53 | 124,170.50 | 0.7629 | 94,729.08 | 930,895.76 |
| 5 | 4,249.68 | 130,866.82 | 126,617.14 | 0.7130 | 90,276.27 | 926,241.28 |
| 6 | 4,355.92 | 133,467.80 | 129,111.88 | 0.6663 | 86,032.70 | 921,610.07 |
| 7 | 4,464.82 | 136,120.47 | 131,655.66 | 0.6227 | 81,988.53 | 917,002.02 |
| 8 | 4,576.44 | 138,825.87 | 134,249.43 | 0.5820 | 78,134.39 | 912,417.01 |
| 9 | 4,690.85 | 141,585.03 | 136,894.18 | 0.5439 | 74,461.36 | 907,854.93 |
| 10 | 4,808.12 | 144,399.04 | 139,590.91 | 0.5083 | 70,960.94 | 903,315.65 |
| 11 | 4,928.33 | 147,268.97 | 142,340.64 | 0.4751 | 67,625.01 | 898,799.07 |
| 12 | 65,051.53 | 150,195.94 | 85,144.40 | 0.4440 | 37,805.13 | 894,305.08 |
| 13 | 5,177.82 | 153,181.08 | 148,003.26 | 0.4150 | 61,416.09 | 889,833.55 |
| 14 | 5,307.27 | 156,225.56 | 150,918.29 | 0.3878 | 58,528.71 | 885,384.38 |
| 15 | 5,439.95 | 159,330.54 | 153,890.59 | 0.3624 | 55,777.03 | 880,957.46 |
| 16 | 5,575.95 | 162,497.23 | 156,921.29 | 0.3387 | 53,154.67 | 876,552.68 |
| 17 | 5,715.35 | 165,726.87 | 160,011.52 | 0.3166 | 50,655.55 | 872,169.91 |
| 18 | 5,858.23 | 169,020.69 | 163,162.46 | 0.2959 | 48,273.88 | 867,809.06 |
| 19 | 6,004.69 | 172,379.97 | 166,375.29 | 0.2765 | 46,004.15 | 863,470.02 |
| 20 | 6,154.80 | 175,806.03 | 169,651.22 | 0.2584 | 43,841.10 | 859,152.67 |
| 21 | 6,308.67 | 179,300.17 | 172,991.50 | 0.2415 | 41,779.71 | 854,856.90 |
| 22 | 6,466.39 | 182,863.76 | 176,397.37 | 0.2257 | 39,815.21 | 850,582.62 |
| 23 | 6,628.05 | 186,498.18 | 179,870.13 | 0.2109 | 37,943.04 | 846,329.71 |
| 24 | 6,793.75 | 190,204.83 | 183,411.08 | 0.1971 | 36,158.87 | 842,098.06 |
| 25 | 6,963.59 | 193,985.15 | 187,021.56 | 0.1842 | 34,458.57 | 837,887.57 |
| Parameter | Value |
|---|---|
| Installed capacity | 700 kWp (DC) |
| Module wattage tier assumed | 540–560 Wp (LONGi Hi-MO family class) |
| Inverter topology / kW class assumed | 1,500 V DC, three-phase string, 8–12 MPPT (Sungrow SGxxCX / Huawei SUN2000-60KTL-M0 class) |
| Racking type assumed | Aluminium rail on metal-deck roof (K2 Systems SingleRail / SolidRail family) |
| Annual specific yield | 1,350 kWh/kWp/yr |
| Annual generation (year 1) | 945,000 kWh/yr |
| Module degradation | 0.5%/yr linear |
| System lifetime | 25 yr |
| Turnkey capex | 1.10 USD/Wp |
| Total capex (year 0) | 770,000 USD |
| Fixed O&M (year 1) | 3,850 USD/yr (= 0.5% of capex) |
| O&M escalator | 2.5%/yr |
| Inverter replacement | 60,000 USD in year 12 (one-off) |
| Site retail tariff (blended) | 0.14 USD/kWh (year 1) |
| Tariff escalator | 2.5%/yr |
| Self-consumption share | 85% |
| Exported energy value | 0.06 USD/kWh (flat) |
| Discount rate (WACC, nominal) | 7.00% |
| Bounded model defaults — present as explicit assumptions, not sourced facts | |
| Residual_value.amount | 0 USD (no terminal salvage assumed) |
| Residual_value.year | n/a (terminal year 25 has no residual) |
| Factual claim | Source row | URL |
|---|---|---|
| Annual specific yield 1,350 kWh/kWp/yr for the US logistics-depot location | NREL PVWatts location report (typical-meteorological-year, fixed-tilt, logistics-rooftop class) | https://www.nrel.gov/pvwatts |
| Turnkey capex benchmark 1.10 USD/Wp for US commercial rooftop Q4 2025 | Wood Mackenzie US solar market outlook — Q4 2025 capex benchmark (commercial rooftop segment) | https://www.woodmac.com/research/products/power-and-renewables/us-solar-market-outlook/ |
| Site blended retail tariff 0.14 USD/kWh (US commercial 2024 average) | EIA, Electric Power Monthly, Table 5.6.A — Average Price of Electricity to Ultimate Customers by End-Use Sector, Commercial | https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=table_5_06_a |
| Tariff escalator 2.5%/yr (long-run US commercial price growth) | EIA Annual Energy Outlook 2025, Table: Electricity prices by sector, commercial, reference case | https://www.eia.gov/outlooks/aeo/ |
| Exported energy value 0.06 USD/kWh (typical small-PV export credit / avoided cost) | EIA, Electric Power Monthly, Table: Average Price of Electricity to Ultimate Customers — used as proxy reference for avoided-cost banding | https://www.eia.gov/electricity/monthly/ |
| Fixed O&M assumption 0.5% of capex | NREL Annual Technology Baseline (ATB) — Commercial PV, fixed O&M cost | https://atb.nrel.gov/electricity/2024/commercial_pv |
| Module degradation 0.5%/yr linear | NREL Annual Technology Baseline (ATB) — Commercial PV, degradation | https://atb.nrel.gov/electricity/2024/commercial_pv |
| Inverter replacement 60,000 USD in year 12 (≈0.08 USD/Wp of initial capex) | Bounded model assumption anchored to a typical 0.08–0.10 USD/Wp string-inverter swap for the equipment class above; OEM warranty length stated in the datasheet at RFQ | https://www.sungrowpower.com/en ; https://solar.huawei.com/en |
| Discount rate 7.00% nominal | Project brief — TradVolt commercial-PV WACC benchmark | https://tradvolt.com/ |
| Self-consumption share 85% | Project brief — daytime logistics loading profile | https://tradvolt.com/ |
| HS / HTS classification lookup tool | USITC Harmonized Tariff Schedule — official lookup | https://hts.usitc.gov/ |
| EU TARIC lookup (for cross-reference) | European Commission TARIC consultation | https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en |
| UK Global Tariff lookup (for cross-reference) | UK Trade Tariff | https://www.trade-tariff.service.gov.uk/ |
| Incoterms 2020 (for delivery-term reading of the RFQ) | ICC Incoterms 2020 | https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/ |
| US import compliance reference | US Customs and Border Protection | https://www.cbp.gov/ |
| UL 61730-1 PV module safety qualification | UL Standards — UL 61730-1 | https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1 |
| IEEE 1547 interconnection (US) | IEEE Standards Association catalogue (search IEEE 1547-2018) | https://standards.ieee.org/ieee/1547/5912/ |
| NFPA 70 / NEC 690 PV installation code | NFPA 70 — National Electrical Code | https://www.nfpa.org/codes-and-standards/nfpa-70-standard-development/70 |
| IEC 62446 commissioning documentation | IEC Webstore — search by designation IEC 62446 (cite designation + edition in any procurement document; do not invent publication ID) | https://webstore.iec.ch/ |
| ISPM 15 wood packaging (relevant only if crating uses solid wood) | IPPC ISPM standards list | https://www.ippc.int/en/core-activities/standards-setting/ispms/ |
| IATA DGR (relevant only if lithium / battery storage is co-shipped) | IATA Dangerous Goods Regulations | https://www.iata.org/en/programs/cargo/dgr/ |
Each cell is recomputed against the same closed-form in §3 (Capex → NPC linearly; Yield → Gen_t and Bil t; Tariff → Bil t). LCOE is reported to 4 decimals.
| Scenario | Capex USD/Wp | Yield kWh/kWp | Tariff USD/kWh | LCOE (USD/kWh) | Net_NPV (kUSD) | Discounted payback (yr) |
|---|---|---|---|---|---|---|
| Base | 1.10 | 1,350 | 0.14 | 0.0808 | 833 | 8.34 |
| Capex −20% | 0.88 | 1,350 | 0.14 | 0.0674 | 986 | 6.93 |
| Capex +20% | 1.32 | 1,350 | 0.14 | 0.0970 | 679 | 9.97 |
| Yield −15% | 1.10 | 1,148 | 0.14 | 0.0951 | 510 | 11.40 |
| Yield +15% | 1.10 | 1,553 | 0.14 | 0.0703 | 1,156 | 7.20 |
| Tariff −20% | 1.10 | 1,350 | 0.112 | 0.0808 | 496 | 11.10 |
| Tariff +20% | 1.10 | 1,350 | 0.168 | 0.0808 | 1,170 | 7.05 |
| Worst composite (−capex, −yield, −tariff) | 0.88 | 1,148 | 0.112 | 0.0792 | 275 | 12.90 |
| Best composite (+capex savings, +yield, +tariff) | 0.88 | 1,553 | 0.168 | 0.0561 | 1,756 | 5.55 |
Reconciliation note (R11): the Capex ±20% rows in the prior draft used a stale Net_NPV that did not reconcile with the base NPC and NPV_Savings within 2%. The two rows above are recomputed against the base formula and now reconcile: Capex −20% lifts Net_NPV by ~153 kUSD (NPC drops by 154 kUSD, discounted benefit unchanged at 1,685,946 USD) and Capex +20% drops Net_NPV by ~154 kUSD (NPC rises by 154 kUSD).
| Component | Possible HTS heading | Indicative heading text | Duty rate | Lookup URL |
|---|---|---|---|---|
| Crystalline silicon PV modules | 8541.43 | Photosensitive semiconductor devices, incl. photovoltaic cells & modules | PENDING — verify at the USITC HTS lookup | https://hts.usitc.gov/ |
| String / central inverters | 8504.40 | Static converters, other | PENDING — verify at the USITC HTS lookup | https://hts.usitc.gov/ |
| Mounting structures (aluminium / steel) | 7610 / 7308 | Aluminium structures / iron-steel structures | PENDING — verify at the USITC HTS lookup | https://hts.usitc.gov/ |
| DC / AC cables, PV-rated | 8544.60 | Other electric conductors, >1,000 V | PENDING — verify at the USITC HTS lookup | https://hts.usitc.gov/ |
Lookup instructions: Open the official USITC Harmonized Tariff Schedule at https://hts.usitc.gov/, enter the 6-digit heading above, then expand to the 10-digit statistical breakout for the duty rate, any Section 301 / Section 232 add-ons, and applicable Free Trade Agreement preference programs. Rates change; always re-pull at the time of entry. Section 201 safeguard and AD/CVD findings can apply depending on country of origin. Cross-reference for non-US destinations: EU TARIC · UK Global Tariff.
Disclaimer: No duty rate is asserted as fact on this page. Classification is the importer's responsibility under 19 CFR §141. Consult a licensed customs broker for binding rulings via CBP's e-Rulings programme (https://www.cbp.gov/).
Deliverables are returned through the RFQ pipeline; no separate datasheet PDF is published on this page.
Numbers above are derived from the stated inputs against the formula in §3 and the cited documents in §5. Refresh the EIA Electric Power Monthly table, the AEO table, and the USITC HTS lookup before any procurement decision. No "No.1", review stars or third-party-verified-supplier claim is made on this page; the OEM product pages above are the source of make/model confirmation and datasheet revision. Reviewed by muse-ba.