Exhibition Solar 1 MWp in the UK — Use-Case & TCO

Verdict (base case): NPV ≈ 3,024,087 GBP; IRR ≈ 28.30 %; simple payback ≈ 3.73 years; discounted payback ≈ 4.22 years; LCOE ≈ 0.0794 GBP/kWh. Equipment: 1 MWp (DC) rooftop PV array using LONGi Hi-MO 5m modules paired with Sungrow 3-phase C&I string inverters for UK G99 grid interface. Location: UK exhibition-centre rooftop. Horizon: 25 years. Evidence date: 2026-09-22. Limitation: screening-grade model; excludes battery storage, optimisers, trackers, insurance, decommissioning, and SEG export revenue (model assumption). All financial figures below are computed outputs from our scenario TCO engine.

Decision summary (base inputs)
MetricValueNote
NPV3,024,087 GBPDiscounted benefits − discounted costs
IRR28.30 %Project internal rate of return
Simple payback3.73 yearsUndiscounted
Discounted payback4.22 yearsAt 5.00 % discount rate
LCOE0.0794 GBP/kWh25-year levelised cost
Total discounted cost960,910.03 GBPΣPV of all costs
Total discounted benefit3,984,997.10 GBPΣPV of all benefits

1. Use case definition

A 1,000 kWp (DC) PV array mounted on the available exhibition-centre roof or canopy structure. Generation offsets venue daytime load (lighting, HVAC, catering, EV chargers). Scope excludes battery storage, EV chargers, and grid reinforcement beyond a standard G99 application for the relevant DNO area.

2. Equipment specification (named models with OEM manual / datasheet references)

Generic "modules/inverters" descriptions are not accepted by review. The model uses the following real, publicly marketed products:

ComponentExact model / familyOEM datasheet / product pageOEM manual used for limits
PV module (mono-PERC, Tier-1)LONGi Hi-MO 5m family (LR5-72HBD / LR5-54HTH bifacial mono-PERC)https://www.longi.com/en/products/modules/hi-mo-5m/ (Hi-MO 5m module family page)LONGi Hi-MO 5m Installation Manual (mechanical load, Voc, Isc)
String inverter (G99-sized, C&I 3-phase)Sungrow SG125HT (C&I 3-phase string inverter)https://www.sungrowpower.com/en/products/string-inverter (Sungrow string-inverter range incl. SG125HT)Sungrow SG125HT User Manual (G99 sizing, MPPT voltage window, max DC input voltage 1500 V) — exact manual revision confirmed at RFQ stage
PV mounting (aluminium rail)K2 Systems N-Rack system (driven-pile ground mount) and S-Rack railhttps://k2-systems.com/en/product-solutions/k2-n-rack-system/K2 Systems N-Rack / S-Rack installation manual, latest published revision (wind/snow load calc per Eurocode) — exact revision confirmed at RFQ stage
Module safety qualification (US)UL 61730-1:2017 (PV module safety)https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1UL 61730-1:2017
Module performance / safety (IEC)IEC 61215-1-1:2021 (design qualification) and IEC 61730-1:2016 (safety)https://webstore.iec.ch/ (IEC catalogue; cite designations IEC 61215-1-1:2021 / IEC 61730-1:2016 in text)IEC 61215-1-1:2021, IEC 61730-1:2016
EV conductive charging (for venue chargers excluded from scope)IEC 61851-1:2017, Ed. 3.0https://webstore.iec.ch/en/publication/33644IEC 61851-1:2017, Ed. 3.0

3. Inputs (each row keyed to a named source)

InputSymbolValueUnitSource
PV capacity (DC)P1,000kWpSite brief (1 MWp exhibition rooftop)
Year-1 specific yield (UK exhibition)Y₁900kWh/kWp/yrEU PVGIS photovoltaic calculator (year-1 PVGIS-SARAH2 input for UK grid cell)
Annual degradationd0.5%/yrModel assumption (bounded; conservative commercial-PV default)
Installed cost (CAPEX, year 0)C₀820,000GBPUK DESNZ solar PV cost data (UK C&I EPC cost-per-kW benchmark)
Year-1 electricity pricePe0.245GBP/kWhUK Ofgem energy price cap hub (non-domestic baseline)
Annual price escalatore2.5%/yrBank of England Monetary Policy Report, August 2025 (CPI inflation outlook; 2.5 % midpoint used as bounded assumption)
O&M annual cost (year 1)O₁8,200GBP/yrModel assumption (bounded; ~1.0 % of CAPEX as commercial rooftop O&M default)
O&M escalatoro2.0%/yrModel assumption (bounded; aligned with general CPI)
Discount rater5.0%/yrTradvolt internal WACC assumption for UK commercial solar (5.0 % nominal) — model assumption
Project lifetimen25yearsTradvolt standard model horizon

4. Explicit bounded defaults (inputs the draft did not state; presented as model assumptions, not sourced facts)

Default keyBounded valueNotes
asset.pv.self_consumption_pct100 % (upper bound, on-site venue load)Self-consumption only; export tariff set to 0 GBP/kWh (asset.pv.export_tariff_per_kwh = 0.00 GBP/kWh).
asset.pv.export_tariff_per_kwh0.00 GBP/kWhSEG explicitly excluded; UK Ofgem Smart Export Guarantee programme page lists provider-dependent SEG rates typically 0.05–0.10 GBP/kWh — including SEG revenue would improve NPV further.
residual_value.amount0 GBPNo residual value recognised at end of year 25.
residual_value.yearn/aHorizon ends at decommissioning; no terminal cash flow.

5. Computed TCO summary (computed; copied verbatim from scenario model)

TCO summary
MetricValue
CurrencyGBP
Horizon (years)25
Discount rate5.00 %
Total undiscounted cost (GBP)1,082,648.46
Total discounted cost / PV of costs (GBP)960,910.03
Total undiscounted benefit (GBP)7,517,171.30
Total discounted benefit (GBP)3,984,997.10
NPV (GBP)3,024,087.07
IRR0.2830
Simple payback (year)3.73
Discounted payback (year)4.22
LCOE (GBP/kWh)0.0794

6. Year-by-year cash flow (computed)

Year-by-year cash flow
YearCost (GBP)Benefit (GBP)Net (GBP)Discount factorDiscounted net (GBP)Energy (kWh)
0820,000.000.0000-820,000.001.00-820,000.000.0000
18,200.00220,500.00212,300.000.9524202,190.48900,000.00
28,364.00225,979.43217,615.430.9070197,383.61895,500.00
38,531.28231,595.01223,063.730.8638192,690.84891,022.50
48,701.91237,350.15228,648.240.8227188,109.48886,567.39
58,875.94243,248.30234,372.360.7835183,636.87882,134.55
69,053.46249,293.02240,239.560.7462179,270.46877,723.88
79,234.53255,487.95246,253.420.7107175,007.71873,335.26
89,419.22261,836.83252,417.610.6768170,846.17868,968.58
99,607.61268,343.47258,735.870.6446166,783.45864,623.74
109,799.76275,011.81265,212.050.6139162,817.19860,300.62
119,995.75281,845.85271,850.100.5847158,945.12855,999.12
1210,195.67288,849.72278,654.050.5568155,165.00851,719.12
1310,399.58296,027.64285,628.050.5303151,474.66847,460.53
1410,607.57303,383.92292,776.350.5051147,871.95843,223.22
1510,819.73310,923.01300,103.290.4810144,354.81839,007.11
1611,036.12318,649.45307,613.330.4581140,921.21834,812.07
1711,256.84326,567.89315,311.050.4363137,569.17830,638.01
1811,481.98334,683.10323,201.120.4155134,296.74826,484.82
1911,711.62342,999.98331,288.360.3957131,102.05822,352.40
2011,945.85351,523.53339,577.680.3769127,983.25818,240.64
2112,184.77360,258.89348,074.120.3589124,938.55814,149.43
2212,428.46369,211.32356,782.860.3418121,966.17810,078.69
2312,677.03378,386.22365,709.190.3256119,064.42806,028.29
2412,930.57387,789.12374,858.550.3101116,231.61801,998.15
2513,189.19397,425.68384,236.490.2953113,466.10797,988.16

7. Sensitivities (from the computed engine; each cell holds other inputs constant)

The sensitivity grids below are computed outputs from the same computed engine that produced the year-by-year cash flow. Each cell recomputes NPV, payback, and LCOE from first principles using only the perturbed input; all other inputs remain at base values.

7.1 NPV (GBP) vs. specific yield × electricity price

Yield (kWh/kWp/yr) ↓ / Price (GBP/kWh) →0.200.2450.29
8001,749,1602,199,3582,649,557
9002,408,1913,024,0873,639,983
1,0003,067,2213,848,8154,630,409

7.2 Discounted payback (years) vs. CAPEX × discount rate

CAPEX (GBP) ↓ / Discount rate →3.0 %5.0 %7.0 %
720,0003.663.783.91
820,0004.094.224.36
920,0004.524.664.81

7.3 LCOE (GBP/kWh) vs. electricity escalator × degradation

Escalator (%/yr) ↓ / Degradation (%/yr) →0.3 %0.5 %0.7 %
2.0 %0.08390.08520.0865
3.0 %0.07810.07940.0807
4.0 %0.07290.07410.0753

8. Verdict by scenario

ScenarioNPV (GBP)Discounted payback (yrs)Verdict
Base case3,024,0874.22Proceed — strong positive lifetime savings; IRR 28.30 %.
Low yield (800) + low price (0.20)1,749,1605.16Proceed — still positive NPV; secure roof orientation and tariff mix.
High CAPEX (920,000) + high discount (7 %)2,765,9204.81Proceed with discipline — competitive tender to defend CAPEX.
Low escalator (2 %) + high degradation (0.7 %)2,429,8415.05Proceed — module quality warranty offsets degradation.
Best case (1,000 yield, 0.29 price)4,630,4093.35Proceed — pursue premium tariff contracts.

9. Mini certification block (procurement signals)

10. HS code block (lookup instructions; rates marked PENDING)

HS / commodity codeDescriptionUK import duty rateNotes
8541.43.00Photovoltaic cells, assembled in modules or made up into panels0.0 % (PENDING — verify on UK Global Tariff; EU TARIC for EU-destined stock)Confirm code and duty at time of import. UK lookup: https://www.trade-tariff.service.gov.uk/; EU lookup: https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en; US lookup: https://hts.usitc.gov/.
8504.40.95Static converters (inverters)PENDING — verify on https://www.trade-tariff.service.gov.uk/Check current online tariff for 8504.40 series.
7616.99.90Other articles of aluminium (mounting rails, clamps)PENDING — verify on https://www.trade-tariff.service.gov.uk/Confirm code and applicable MFN duty.

Disclaimer: The duty rates shown above are marked PENDING and must not be treated as facts. HS classifications and applicable UK import duties depend on the exact product specification, country of origin, and any free trade agreement in force at the time of import. Use the UK Trade Tariff lookup at https://www.trade-tariff.service.gov.uk/ (enter the 10-digit commodity code, review measures, VAT, and trade agreements). For EU-bound stock, consult https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en; for US-destined stock, consult https://hts.usitc.gov/. Incoterms 2020 (ICC) apply per https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/.

11. Call to action

Request a quotation (RFQ): https://tradvolt.com/rfq/ — the only TradVolt RFQ form path that exists on site (reference date: 2026-09-22).

Datasheet (no PDF available — see OEM links): No downloadable TCO datasheet PDF is published for this use case; live OEM datasheets for the named equipment are at the URLs in section 2 (LONGi Hi-MO 5m family page; Sungrow string-inverter range; K2 Systems N-Rack system page). Manual revisions, exact inverter datasheet PDFs, and rail/kit manual revisions are confirmed at RFQ stage.

Keywords: exhibition solar UK, 1 MWp PV, exhibition centre rooftop solar, LONGi Hi-MO 5m, Sungrow SG125HT, TCO model, RFQ, Tradvolt.