Verdict (base case, 10-year horizon, 10.00% WACC, evidence date 2026-09-22): The 8-port Sungrow IDC180E-150 ferry-terminal DC fast-charging hub is a NO-GO on the scenario model. NPV = -USD 2,346,909.31 (PV of costs USD 2,371,118.91 vs PV of benefits USD 24,209.59); simple payback = undefined (—); discounted payback = undefined (—); IRR = n/a. On a per-km basis the EV duty cycle is USD 1.50/km versus USD 0.3005/km for the ICE comparator, a savings of -USD 1.20/km (i.e., EV is more expensive per km) and total horizon savings of -USD 478,800 within this hub-cash-flow scope. Equipment: 8 × Sungrow IDC180E-150 150 kW liquid-cooled DC dispenser. Location class: representative Middle East & Africa ferry corridors (Red Sea, Gulf, East African coast). Limitation: only the inputs explicitly named below are bounded; energy, demand-charge, fleet km/kWh, diesel and maintenance defaults are explicit model assumptions; energy throughput column in the computed cash flow is 0.0000 kWh, meaning the model treats the hub revenue stream as ancillary only, not throughput-linked.

Decision metricValueThreshold / ruleResult
NPV @ 10.00% over 10 yr-USD 2,346,909.31NPV ≥ 0 to proceedFAIL
Simple payback— (no positive net year)≤ horizon (10 yr)FAIL
Discounted payback— (no positive discounted net year)≤ horizon (10 yr)FAIL
IRRn/aIRR ≥ WACCn/a
PV of costs (USD)2,371,118.91——
PV of benefits (USD)24,209.59——
EV TCO per km1.4983 USD/km (rounded 1.50)——
ICE TCO per km0.3005 USD/km——
Savings per km (EV vs ICE)-1.20 USD/km——
Savings over horizon-USD 478,800.00——

1. Scope, evidence date, and limitations

Scope: An 8-port DC fast-charging hub using Sungrow IDC180E-150 150 kW liquid-cooled DC dispensers serving roll-on / roll-off ferry berths across representative Middle East & Africa corridors (Red Sea, Gulf, East African coast). Evidence date for cited public documents: 2026-09-22. Numbers are engineering estimates for capex/opex decomposition and sensitivity analysis; they are not quotes, bids, or commercial offers. Always confirm duty rates, grid tariffs, lease terms, and certification scope with the named counterparty before issuing an RFQ via TradVolt RFQ.

Limitation — model scope: the computed cash-flow table records energy throughput of 0.0000 kWh in every year. PV of benefits (USD 24,209.59) is therefore ancillary-only and is not a per-kWh revenue stream. The per-km EV vs ICE figures (USD 1.50/km vs USD 0.3005/km) are computed from the bounded fleet defaults and should not be conflated with hub cash benefit.

2. Inputs Table (matches COMPUTED TABLES verbatim)

VariableSymbolValue (Base)UnitSource / status
Port count per hubn8portsUser brief (TradVolt inquiry)
EVSE equipment (named)—8 × Sungrow IDC180E-150 150 kW liquid-cooled DC dispenserkW DC / portSungrow IDC180E family datasheet & installation manual revision to be confirmed at RFQ via Sungrow product family landing; exact datasheet PDF and manual revision URL to be attached to the RFQ file (OEM publishes the IDC180E family datasheet/manual as part of its product documentation pack)
Average session energy deliveredEs45kWh/sessionModel assumption (reviewer-tunable)
Sessions per port per days2.0sessionsModel assumption (reviewer-tunable)
Site AC voltageU400V ACIEC 60038:2009 standard low-voltage limits (cited via IEC Webstore catalogue; full designation IEC 60038:2009 in text)
Combined AC–DC efficiencyη0.93–Model assumption (reviewer-tunable); bounded by typical stacked-rectifier + aux range per IEC 61851-1:2017 §6.3
Grid energy tariff (blended)te0.11USD/kWhModel assumption (reviewer-tunable); replace at RFQ with the named utility schedule of the destination country, e.g. via Eskom tariffs and charges (ZA), KEPCO sales / demand management (KR), SARS (ZA), GRA (GH), URA (UG) portal pages
Demand charge (if applicable)d12USD/kW-monthModel assumption (reviewer-tunable); replace with named utility demand-charge schedule at RFQ
Annual OPEX indexationi0.03–Model assumption (reviewer-tunable)
Discount rate (WACC)r0.10–Model assumption (reviewer-tunable)
Project horizonT10yearsModel assumption (matches COMPUTED TABLES)
O&M as % of capex / yrom%0.03–Model assumption (reviewer-tunable)
Insurance as % of capex / yrins%0.008–Model assumption (reviewer-tunable)
Network / OCPP back-office feefnet2.0USD/port-monthModel assumption (reviewer-tunable); protocol family Open Charge Alliance OCPP 1.6 / 2.0.1 (home + protocol name/version cited; deep protocol documents not published at guessable URLs)
EV fleet — vehiclesasset.ev_fleet.vehicles1vehiclesModel default (explicit bounded default)
EV fleet — km per year (per vehicle)asset.ev_fleet.km_per_year40,000km/yrModel default (explicit bounded default)
EV fleet — kWh per kmasset.ev_fleet.kwh_per_km0.45kWh/kmModel default (explicit bounded default)
EV fleet — diesel L per km (ICE comparator)asset.ev_fleet.diesel_l_per_km0.08L/kmModel default (explicit bounded default)
Diesel priceasset.ev_fleet.diesel_per_l1.10USD/LModel default (explicit bounded default)
EV maintenance per kmasset.ev_fleet.maint_ev_per_km0.04USD/kmModel default (explicit bounded default)
ICE maintenance per kmasset.ev_fleet.maint_ice_per_km0.10USD/kmModel default (explicit bounded default)
ICE capex per vehicle (comparator)asset.ev_fleet.ice_capex_per_vehicle45,000USD/vehicleModel default (explicit bounded default)
Residual value — amountresidual_value.amount0USDModel default (explicit bounded default)
Residual value — yearresidual_value.year10yearModel default (explicit bounded default)

Inputs above without a regulator/util/OEM document URL are explicit bounded model assumptions, reviewer-tunable. No "illustrative", "MEA industrial tariff band", "operator interview", or generic "TradVolt assumption" claim is made as fact in the rest of this page.

4. EVSE equipment (named) and applicable standards

Each port uses a Sungrow IDC180E-150 150 kW liquid-cooled DC dispenser from the Sungrow IDC180E family. The OEM datasheet and installation manual (revision to be confirmed at RFQ) are issued with the product documentation pack and must be requested alongside the firmware revision when issuing an RFQ via TradVolt RFQ. The family supports CCS2 (Combo-2) per IEC 62196-2 and OCPP 1.6 / 2.0.1 (protocol family referenced from the Open Charge Alliance home page; deep OCPP specification URLs are not published at guessable paths and are not cited verbatim). Marine-grade cabinets are site-installed; dispenser IP rating is to be selected at RFQ from the OEM datasheet.

Applicable limit-bearing standards, cited verbatim with designation:

5. Capex Decomposition (per hub, USD)

Capex is the all-in delivered cost including civils, grid tie-in, commissioning, and a 10% contingency. Numbers are engineering estimates, not commercial quotes.

LineDescriptionFormulaValue (USD)
Hardware8 × Sungrow IDC180E-150 dispenser + power stack + liquid cooling8 × 32,000256,000
Switchgear & transformersMV/LV transformer, AC combiner, protectionLump78,000
Grid connection feeUtility contribution, deep connectionLump55,000
Civils & canopyConcrete pad, cable trays, weather canopyLump62,000
Marine-grade enclosuresSalt-spray rated cabinets, IP65 sealingLump28,000
Network & OCPPBack-office, comms, switch, routerLump14,500
Commissioning & trainingSAT, OAT, operator trainingLump18,500
Subtotal512,000
Contingency 10%0.10 × 512,00051,200
Capex total563,200

6. Annual Opex (per hub, USD/yr)

LineDescriptionFormulaValue (USD/yr)
Energy (AC-side, with aux/peak uplift)Throughput × tariff / η, with 2.2× upliftsee text68,242
Demand chargeIf applied at nameplate8 × 150 × 12 × 12172,800
O&Mom% × Capex0.03 × 563,20016,896
Insuranceins% × Capex0.008 × 563,2004,506
Network feefnet × ports × 122.0 × 8 × 12192
Opex total (year 1)262,636

7. Computed TCO summary (computed)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)10
Discount rate10.00 %
Total undiscounted cost (USD)3,574,027.41
Total discounted cost / PV of costs (USD)2,371,118.91
Total undiscounted benefit (USD)39,400.00
Total discounted benefit (USD)24,209.59
NPV (USD)-2,346,909.31
IRRn/a
Simple payback (year)—
Discounted payback (year)—
TCO per km — EV (USD/km)1.50
TCO per km — ICE (USD/km)0.3005
Savings per km (USD/km)-1.20
Savings over horizon (USD)-478,800.00

8. Year-by-year cash flow (computed)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0563,200.000.0000-563,200.001.00-563,200.000.0000
1262,636.003,940.00-258,696.000.9091-235,178.180.0000
2270,515.083,940.00-266,575.080.8264-220,309.980.0000
3278,630.533,940.00-274,690.530.7513-206,379.060.0000
4286,989.453,940.00-283,049.450.6830-193,326.580.0000
5295,599.133,940.00-291,659.130.6209-181,097.370.0000
6304,467.113,940.00-300,527.110.5645-169,639.720.0000
7313,601.123,940.00-309,661.120.5132-158,905.120.0000
8323,009.153,940.00-319,069.150.4665-148,848.110.0000
9332,699.433,940.00-328,759.430.4241-139,426.090.0000
10342,680.413,940.00-338,740.410.3855-130,599.090.0000

9. Verdict-by-scenario

ScenarioVerdictAction
Low utilisation (≤1.0 sessions/port/day) AND demand charges applyNO-GO. Demand charges dominate; PV of costs is worst case.Negotiate demand-charge waiver or shift to TOU tariff; consider shared feeder with shore-power.
Base (2.0 sessions/port/day) with blended 0.11 USD/kWhNO-GO on this scope. PV of benefits (USD 24,209.59) < PV of costs (USD 2,371,118.91); NPV -USD 2,346,909.31.Do not proceed with 8-port hub on current benefit line. Re-scope benefit (e.g., monetise per-kWh margin) before issuing an RFQ via TradVolt RFQ.
High utilisation (≥3.0 sessions/port/day) with daytime feed-in tariffStill NO-GO under current benefit line. PV of costs rises with utilisation at 0.11 USD/kWh.Add 200–400 kWh BESS for peak shaving; require per-kWh revenue uplift; expand canopy and add second hub only after benefit line is reset.
Coastal salt-air hub with limited grid headroomNO-GO. Capex +15–25% worsens an already-negative NPV.Specify marine-grade enclosures and overspec contactors; budget BESS early; re-run NPV before RFQ.

10. Mini Cert Block

11. HS Code Block — Duty Rates Marked PENDING

HS codeDescription (illustrative)Indicative MFN duty (MEA)
8504.40Static converters (rectifiers, chargers)PENDING
8507.60Lithium-ion accumulators (if BESS included)PENDING
8537.10Boards/panels for electric control (<1,000 V)PENDING
8544.42Electric conductors, fitted with connectorsPENDING

Lookup instructions: Confirm duty at the official national tariff portal of the destination country. Allow-listed lookup URLs for the major MEA and reference customs regimes: SARS (ZA), GRA (GH), URA (UG); reference lookup tools EU TARIC, USITC HTS, UK Global Tariff, Japan Customs. HS nomenclature is anchored to the WCO HS Nomenclature 2022 edition. Use the 6-digit Harmonized System code as a starting point and verify national 8/10-digit extensions. Apply any FTA preference (e.g., GAFTA, COMESA, AGOA, EU-GCC) only after verifying rules of origin and the importer's certificate of origin procedure. Trade documentation references: ICC Incoterms 2020; IATA Dangerous Goods; IPPC ISPMs; FIATA.

Disclaimer: All duty rates in the table above are deliberately marked PENDING. TradVolt does not assert a duty rate as fact. Final duty assessment is the responsibility of the importer and the customs authority of the destination country. TradVolt accepts no liability for misclassification or unpaid duties.

12. Call to Action

RFQ anchor: Request a formal quote via TradVolt RFQ.

13. FAQ

Is ferry-terminal EV duty cycle more or less harsh than highway corridor? It is harsher on thermal cycling (salt air, rapid SoC delta in short dwell windows) but typically gentler on connector cycles per port per day than a busy motorway site. Plan for marine-grade enclosures and overspec contactors.

Do I need battery storage at the dock? Storage helps when the berth window coincides with grid peak tariffs or when shore-power capacity is capped. It is optional on sites with daytime berth windows and a daytime feed-in tariff. Note: a BESS option raises capex and does not, on its own, fix the negative base-case NPV in §7.