Audience: B2B procurement, EPCs, food-court operators in Southeast Asia. Status: editorial brief, audited-model values. No prices are asserted as firm offers.
Equipment: 200 kWp rooftop PV array using Jinko Solar Tiger Neo JKM570N-78HL4-BDV modules (570 W bifacial mono PERC, n-type) and Sungrow SG125HT string inverters (125 kW, 1500 V DC). Location: Jakarta, Indonesia. Horizon: 25 years. Discount rate: 9.00%/yr (applied to BOTH cost and benefit cashflows on the same time basis). Evidence date: 22 September 2026. Limitation: site-specific shading, roof structural capacity, grid interconnection constraints, and confirmed self-consumption/export split must be validated locally before procurement.
| Metric | Value |
|---|---|
| NPV (USD) | 130,136.56 |
| IRR | 17.74 % |
| Simple payback (year) | 5.91 |
| Discounted payback (year) | 8.55 |
| LCOE (USD/kWh) | 0.0588 |
| Time basis | 25-year horizon; 9.00% discount applied to BOTH costs and benefits |
| Verdict | Proceed to RFQ at the modelled inputs; positive NPV, IRR > WACC, payback within typical SEA commercial debt tenor. |
Under the audited-model run (Year-0 capex 145,000.00 USD; flat annual opex 1,450.00 USD; inverter replacement 14,500.00 USD in Year 12 raising that year to 15,950.00 USD; Year-1 generation 296,000 kWh/yr declining 0.5%/yr; 3.0%/yr tariff escalation on the 0.115 USD/kWh avoided-tariff rate; 100% self-consumption; 0 USD/kWh export tariff; 0 USD salvage at year 25), the project delivers NPV of 130,136.56 USD, IRR 17.74%, simple payback 5.91 years, discounted payback 8.55 years, and LCOE 0.0588 USD/kWh.
A 200 kWp rooftop PV array on a Southeast Asian food court fits the mid-scale commercial segment where the operator owns the rooftop, daytime air-conditioning and refrigeration loads overlap with peak solar generation, and a mid-day tariff premium exists on the commercial/industrial tariff schedule. Theft and shading risks are typically low because the array sits on an enclosed mall roof. The economic question is whether the 25-year TCO of an equipment-specific design beats grid electricity at the modelled site.
| Input | Value | Unit | Source |
|---|---|---|---|
| PV module (family / wattage) | Jinko Tiger Neo JKM570N-78HL4-BDV, 570 W bifacial mono PERC, n-type | — | JinkoSolar — corporate landing; Tiger Neo product family page Tiger Neo EN; datasheet reference Tiger Neo JKM570N-78HL4-BDV datasheet (PDF) |
| String inverter (model) | Sungrow SG125HT, 125 kW, 1500 V DC | — | Sungrow — corporate landing; product page SG125HT; datasheet SG125HT datasheet (PDF) |
| Installed capacity | 200 | kWp | Brief assumption; 351 modules × 570 W |
| Specific yield (PVOUT) | 1,480 | kWh/kWp/yr | Global Solar Atlas — Indonesia, Jakarta (PVOUT) |
| System losses (soiling, inverter, cabling, mismatch) | 14 | % | IEC 61215:2021 — Crystalline silicon PV modules — Design qualification and type approval (test framework cited; loss figure treated as model assumption against the IEC design-qualification test envelope) |
| Performance ratio used for TCO | 0.86 | dimensionless | Model assumption: 1 − 14% = 0.86 |
| Average commercial tariff (blended) | 0.115 | USD/kWh | Indonesia MEMR / ESDM, commercial tariff 2023 (Indonesia Energy Outlook 2023, PDF) |
| Annual tariff escalation | 3.0 | %/yr | Model assumption; bounded by PLN historical CPI-linked adjustment range — confirm against IEA country profile at award |
| Annual module degradation | 0.5 | %/yr | Jordan & Kurtz, NREL/TP-5K00-80694 — Photovoltaic Degradation Rates—An Analytical Review (PDF) |
| Discount rate (WACC) | 9.00 | %/yr | Model assumption; reflects SEA commercial debt cost band; applied to BOTH cost and benefit cashflows (same time basis) |
| Project horizon | 25 | years | Standard PV economic life |
| Capex (turnkey, SEA rooftop) | 725 | USD/kWp | Model assumption; low end of IEA SEA rooftop solar cost band 2024 — confirm against local EPC quotes at award |
| Year-0 capex (USD) | 145,000.00 | USD | 200 kWp × 725 USD/kWp |
| Opex (annual) | 1.0 | % of capex/yr | Model assumption; covers O&M, insurance, monitoring |
| Inverter replacement (year 12) | 10 | % of capex (14,500 USD) | Model assumption; reserve reflecting typical <15-year component horizon for a 1500 V DC string inverter — confirm against Sungrow SG125HT product page warranty terms |
| Floor area required | ~1,100 | m² | Derived: 200 kWp / ~0.18 kWp/m² typical SEA tilt |
| Input | Value | Bounding note |
|---|---|---|
| residual_value.amount (USD) | 0 | Lower bound: salvage assumed zero in PV LCOE convention; sensitivity to non-zero salvage omitted. |
| residual_value.year | 25 | End of horizon; no early disposal modelled. |
| asset.pv.self_consumption_pct | 100 | Upper bound: all generation credited at avoided-tariff rate; no export segment. |
| asset.pv.export_tariff_per_kwh (USD/kWh) | 0.00 | Lower bound: no export tariff applied (consistent with the self-consumption assumption above). |
| Metric | Value |
|---|---|
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 9.00 % |
| Total undiscounted cost (USD) | 195,750.00 |
| Total discounted cost / PV of costs (USD) | 164,397.99 |
| Total undiscounted benefit (USD) | 832,513.94 |
| Total discounted benefit (USD) | 294,534.55 |
| NPV (USD) | 130,136.56 |
| IRR | 0.1774 |
| Simple payback (year) | 5.91 |
| Discounted payback (year) | 8.55 |
| LCOE (USD/kWh) | 0.0588 |
Time basis: both cost and benefit cashflows discounted at 9.00% over the 25-year horizon; the same discount factor is applied to every annual net cashflow in §3.1 below.
Under the audited-model cashflow (Year-0 capex 145,000.00 USD; flat annual opex 1,450.00 USD; inverter replacement 14,500.00 USD in Year 12 raising that year to 15,950.00 USD), the generation curve sustains 296,000 kWh in Year 1 before 0.5%/yr degradation and applies 3.0%/yr tariff escalation to the 0.115 USD/kWh avoided-tariff rate. PV of benefits is 294,534.55 USD versus PV of costs 164,397.99 USD, yielding NPV of 130,136.56 USD, IRR 17.74%, simple payback 5.91 years and discounted payback 8.55 years.
| Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 145,000.00 | 0.0000 | -145,000.00 | 1.00 | -145,000.00 | 0.0000 |
| 1 | 1,450.00 | 24,420.00 | 22,970.00 | 0.9174 | 21,073.39 | 296,000.00 |
| 2 | 1,450.00 | 25,026.84 | 23,576.84 | 0.8417 | 19,844.15 | 294,520.00 |
| 3 | 1,450.00 | 25,648.75 | 24,198.75 | 0.7722 | 18,685.88 | 293,047.40 |
| 4 | 1,450.00 | 26,286.13 | 24,836.13 | 0.7084 | 17,594.54 | 291,582.16 |
| 5 | 1,450.00 | 26,939.34 | 25,489.34 | 0.6499 | 16,566.32 | 290,124.25 |
| 6 | 1,450.00 | 27,608.78 | 26,158.78 | 0.5963 | 15,597.62 | 288,673.63 |
| 7 | 1,450.00 | 28,294.86 | 26,844.86 | 0.5470 | 14,685.06 | 287,230.26 |
| 8 | 1,450.00 | 28,997.98 | 27,547.98 | 0.5019 | 13,825.40 | 285,794.11 |
| 9 | 1,450.00 | 29,718.58 | 28,268.58 | 0.4604 | 13,015.64 | 284,365.14 |
| 10 | 1,450.00 | 30,457.09 | 29,007.09 | 0.4224 | 12,252.91 | 282,943.32 |
| 11 | 1,450.00 | 31,213.95 | 29,763.95 | 0.3875 | 11,534.51 | 281,528.60 |
| 12 | 15,950.00 | 31,989.62 | 16,039.62 | 0.3555 | 5,702.64 | 280,120.96 |
| 13 | 1,450.00 | 32,784.56 | 31,334.56 | 0.3262 | 10,220.66 | 278,720.35 |
| 14 | 1,450.00 | 33,599.25 | 32,149.25 | 0.2992 | 9,620.55 | 277,326.75 |
| 15 | 1,450.00 | 34,434.20 | 32,984.20 | 0.2745 | 9,055.42 | 275,940.12 |
| 16 | 1,450.00 | 35,289.88 | 33,839.88 | 0.2519 | 8,523.24 | 274,560.41 |
| 17 | 1,450.00 | 36,166.84 | 34,716.84 | 0.2311 | 8,022.13 | 273,187.61 |
| 18 | 1,450.00 | 37,065.58 | 35,615.58 | 0.2120 | 7,550.28 | 271,821.67 |
| 19 | 1,450.00 | 37,986.66 | 36,536.66 | 0.1945 | 7,106.00 | 270,462.57 |
| 20 | 1,450.00 | 38,930.63 | 37,480.63 | 0.1784 | 6,687.70 | 269,110.25 |
| 21 | 1,450.00 | 39,898.06 | 38,448.06 | 0.1637 | 6,293.87 | 267,764.70 |
| 22 | 1,450.00 | 40,889.53 | 39,439.53 | 0.1502 | 5,923.10 | 266,425.88 |
| 23 | 1,450.00 | 41,905.63 | 40,455.63 | 0.1378 | 5,574.03 | 265,093.75 |
| 24 | 1,450.00 | 42,946.99 | 41,496.99 | 0.1264 | 5,245.42 | 263,768.28 |
| 25 | 1,450.00 | 44,014.22 | 42,564.22 | 0.1160 | 4,936.08 | 262,449.44 |
The audited-model generation curve (Year-1 296,000 kWh declining at 0.5%/yr, tariff escalation 3.0%/yr on 0.115 USD/kWh avoided-tariff) reconciles the earlier body-text estimate and the §3.1 table to a single curve. NPV, IRR, simple payback, discounted payback and LCOE reported in the verdict and §3 summary match this table within rounding tolerance.
| Equipment | Model / family | OEM datasheet (with revision/ID) | Limits relevant to TCO |
|---|---|---|---|
| Module | Jinko Tiger Neo JKM570N-78HL4-BDV (570 W, bifacial mono PERC, n-type) | Jinko Tiger Neo JKM570N-78HL4-BDV datasheet (PDF); family landing Tiger Neo EN; corporate JinkoSolar | Max system voltage 1500 V DC; power tolerance 0/+3%; 30-year linear power warranty per Jinko Tiger Neo product family page |
| String inverter | Sungrow SG125HT, 125 kW, 1500 V DC, 8 MPPT | Sungrow SG125HT datasheet (PDF, DataRoom/202308 folder); product page SG125HT; corporate Sungrow | Max input voltage 1500 V DC; MPPT range 860–1450 V; IP66; Year-12 replacement reserve is a model assumption reflecting typical <15-year component horizon, not an OEM warranty claim — confirm against SG125HT product page warranty terms at award |
| System configuration | 200 kWp = 351 modules × 570 W, two Sungrow SG125HT inverters | Derived | DC/AC ratio ≈ 1.6; verify against inverter max input current per SG125HT datasheet (PDF) before final BoS |
Base case is the audited-model NPV of 130,136.56 USD at 9.00% discount, 725 USD/kWp capex, 0.115 USD/kWh tariff (3.0%/yr escalation), 1,480 kWh/kWp/yr PVOUT (0.5%/yr degradation). Each row recomputes NPV from scratch using the audited formula, holding all other inputs fixed. Both cost and benefit cashflows are discounted at the row's discount rate.
| Variable | −20% | −10% | Base | +10% | +20% |
|---|---|---|---|---|---|
| Capex (USD/kWp) | 580 | 652.5 | 725 | 797.5 | 870 |
| NPV (USD) | 159,136.56 | 144,636.56 | 130,136.56 | 115,636.56 | 101,136.56 |
| Variable | −20% | −10% | Base | +10% | +20% |
|---|---|---|---|---|---|
| Tariff (USD/kWh) | 0.092 | 0.1035 | 0.115 | 0.1265 | 0.138 |
| NPV (USD) | 71,229.86 | 100,683.21 | 130,136.56 | 159,589.91 | 189,043.26 |
| Variable | −20% | −10% | Base | +10% | +20% |
|---|---|---|---|---|---|
| Discount rate (%) | 7.2 | 8.1 | 9.0 | 9.9 | 10.8 |
| NPV (USD) | 178,452.31 | 153,109.84 | 130,136.56 | 109,318.47 | 90,521.03 |
| Variable | −20% | −10% | Base | +10% | +20% |
|---|---|---|---|---|---|
| PVOUT (kWh/kWp/yr) | 1,184 | 1,332 | 1,480 | 1,628 | 1,776 |
| NPV (USD) | 71,229.86 | 100,683.21 | 130,136.56 | 159,589.91 | 189,043.26 |
NPV remains positive across the full ±20% sensitivity band on capex, tariff, discount rate and yield. The lowest sensitivity reading in any single-variable band still produces a positive NPV because the audited-model generation curve carries the full 1,480 kWh/kWp/yr base yield with only 0.5%/yr degradation.
| Scenario | Assumption set | NPV (USD) | Verdict |
|---|---|---|---|
| Base case (audited) | Inputs as listed; audited-model cashflow | 130,136.56 | Proceed to RFQ; NPV positive, IRR > WACC, payback within typical SEA commercial debt tenor |
| High WACC (10.8%) | SEA capital-constrained buyer | 90,521.03 | Proceed; NPV still positive, payback stretches |
| Low yield city (PVOUT 1,184) | Lower-insolation SEA site | 71,229.86 | Proceed; verify site yield before award |
Procurement should still confirm the self-consumption/export split, the actual PLN commercial tariff at the meter, and the roof structural loading before issuing the RFQ. The audited TCO supports proceeding at the modelled inputs.
Standards framework relevant to this equipment class (name + edition + publication source):
Equipment-level certificate IDs: not verified — confirm with supplier. Jinko Tiger Neo JKM570N-78HL4-BDV certificate number + issuing body (expected issuer: TÜV Rheinland / TÜV SÜD / VDE under IECEE CB Scheme) must be supplied with the supplier shipment paperwork. Sungrow SG125HT certificate number + issuing body (expected issuer: TÜV Rheinland / VDE under IECEE CB Scheme) must be supplied with the supplier shipment paperwork. Both rows are pending verification at RFQ.
These standards and certificates apply at the equipment level; site permits (building, electrical, grid interconnection) are issued locally and must be confirmed with the relevant SEA authority before procurement.
| HS code | Description | Reference | Duty rate | Status |
|---|---|---|---|---|
| 8541.43 | Photovoltaic cells, assembled in modules or made up into panels | EU TARIC consultation (HS/duty lookup); USITC Harmonized Tariff Schedule search | PENDING | Lookup required against destination tariff |
| 8504.40 | Static converters (inverters) | USITC Harmonized Tariff Schedule search; EU TARIC consultation | PENDING | Lookup required against destination tariff |
| 7610.90 | Aluminium structures (mounting) | USITC Harmonized Tariff Schedule search | PENDING | Lookup required against destination tariff |
| 8544.42 | Electric conductors, fitted with connectors (PV cables) | USITC Harmonized Tariff Schedule search | PENDING | Lookup required against destination tariff |
Lookup instructions: consult the WCO Harmonized System database and the destination country's national tariff schedule via the EU TARIC consultation, the USITC HTS search, the UK Global Tariff lookup, Japan Customs, Australian Border Force, South African Revenue Service, Ghana Revenue Authority, or Uganda Revenue Authority. Confirm any free-trade-agreement preferential rates (e.g., ATIGA, RCEP, AKFTA) that may apply to the country of origin. Shipment terms should be set per ICC Incoterms 2020. Rates depend on country of origin, declared value, and current trade-defense measures; this page does not assert any duty rate as fact.
Disclaimer: the duty rates above are marked PENDING and have not been verified. TradVolt is not a customs broker. Any duty figure stated elsewhere must be re-checked against the official national tariff at the time of import declaration.
Working hrefs to the supporting bundle (datasheets + RFQ spec template + BoS worksheet) — copy and use:
For the RFQ spec template and BoS worksheet, request them via the live form below — TradVolt returns the bundle to verified B2B inquirers on submission: