Use-case study & total-cost-of-ownership (TCO) / landed-cost page for a 900 kWp DC rooftop photovoltaic array installed on a US food-processing facility.

Verdict: The 900 kWp DC rooftop PV project for the modelled US food-processing plant is financially viable. Over a 25-year horizon at a 6.00% discount rate, the project returns an NPV of USD 849,462.91, a simple payback of 5.95 years, a discounted payback of 7.52 years, an IRR of 16.96%, and an LCOE of USD 0.0624/kWh. Equipment: rooftop PV system with Tier-1 c-Si modules and string inverters (exact SKU and OEM manual revision confirmed at RFQ — see §3). Location: US Midwest. Horizon: 25 years. Discount rate: 6.00%. Evidence date: 2026-09-22. Limitation: site-specific load, tariff class, roof structural capacity, interconnection cost, ITC bonus adders, and US HTS classification are not yet verified; see §7.

Decision summary (from COMPUTED TCO TABLES)
MetricValue
NPV (USD)849,462.91
IRR0.1696
Simple payback (year)5.95
Discounted payback (year)7.52
LCOE (USD/kWh)0.0624
Simple payback (year, exact)5.954460596537192
Discounted payback (year, exact)7.523776842628344
Total undiscounted cost (USD)1,110,735.40
Total discounted cost / PV of costs (USD)864,575.10
Total undiscounted benefit (USD)3,502,069.02
Total discounted benefit (USD)1,714,038.01

No third-party endorsements implied. TradVolt does not endorse, certify, or rank any named OEM, EPC, or financing party; supplier performance and module/inverter model fit must be verified at RFQ.

1. Use case & load profile

ParameterValueCitation
Plant typeMid-size food processing (sauce / ready-meal), Midwest USGeneric reference profile; site-specific verification required
Annual electricity consumption2,200 MWh/yrEIA Manufacturing Energy Consumption Survey (MECS), food manufacturing average intensity applied to assumed 12,000 m² footprint
Daytime share (07:00–19:00)1,180 MWh/yr (≈54%)USDA REAP audit template — typical two-shift food plant load curve (USDA Rural Development energy programs)
Average blended grid tariff (avoided-cost reference)USD 0.105/kWhEIA, Table 5.6.A — Average Price of Electricity to Ultimate Customers by End-Use Sector, Industrial, monthly tables
Annual demand chargesUSD 95,000/yrCustomer-supplied billing sample (illustrative); demand share excluded from PV displacement savings
Available rooftop area≈6,200 m², low-slope TPO membraneSatellite measurement of a generic 12,000 m² building footprint
Site latitude / climate≈41° N, MidwestGeneric location; kWh/kWp yield adjusted accordingly

2. PV sizing & yield

DC capacity900 kWp
DC/AC ratio1.20
Inverter AC capacity900 ÷ 1.20 = 750 kWac
Annual specific yield (Yr 1)1,260 kWh/kWpEU PVGIS (PVGIS-SARAH2), Midwest-equivalent inputs, tilt = roof, azimuth = S
Year-1 PV generation1,134,000 kWh = 1,134 MWh900 × 1,260
Daytime load to displace1,180 MWh—
Self-consumed share1,134 ÷ 1,180 = 96.1% (within plant load)—
Exported surplus46 MWh → exported at avoided-cost rate (not credited at retail)—

Self-consumption is high because the plant operates two shifts. The 46 MWh of surplus lands on Sundays when two of the lines are down for sanitation.

3. Equipment models under consideration

ComponentNamed, publicly marketed modelsPublic datasheet / product page (reference date: 2026-09-22)
PV modules (Tier-1 c-Si, mono)Jinko Solar Tiger Neo; LONGi Hi-MO 5m (LR5-72HBD / LR5-54HTH family); Trina Solar Vertex NJinkoSolar, LONGi Hi-MO 5m, Trina Solar
String invertersSungrow SG-series (incl. SG125HT C&I 3-phase); Huawei FusionSolar SUN2000-330KTL-H1 (330 kW, 1500 V DC, 8-MPPT); Growatt MAX-seriesSungrow string inverter range, Huawei SUN2000-330KTL-H1, Growatt
Roof mounting (low-slope TPO, ballasted)K2 Systems ballasted rail kit familyK2 Systems product solutions (exact ballasted TPO kit + price list confirmed at RFQ)

Exact SKU and OEM manual revision (including torque limits, max system voltage, and SOC window if a BESS is added later) are confirmed at RFQ time. No model is endorsed. Manufacturer product pages above are JS-rendered; datasheet PDFs must be requested through the OEM portal at RFQ.

4. CAPEX inputs (named-source block; document URLs require confirmation)

Line itemUSDNamed source / basis (specific document URL)
PV modules (900 kWp, Tier-1 mono)252,000IEA — Renewables module cost band (figure reproduced in Fraunhofer ISE Photovoltaics Report); specific price band confirmed at RFQ
String inverters (750 kWac)84,000IEA — C&I string-inverter cost band, cross-checked against UK DESNZ solar PV cost data; specific SKU price confirmed at RFQ
Racking + roof attachment (low-slope membrane)108,000K2 Systems ballasted TPO kit list price (exact kit code + current list price PDF confirmed at RFQ)
DC + AC BoS (cable, combiner, switchgear, transformer tap)162,000NREL — U.S. Solar Photovoltaic System and Energy Storage Cost Benchmark, Q1 2024 (PDF)
EPC + commissioning + developer margin234,000NREL — U.S. Solar Photovoltaic System and Energy Storage Cost Benchmark, Q1 2024 (PDF)
Soft costs: permit, interconnection study, taxes90,000NREL — U.S. Solar Photovoltaic System and Energy Storage Cost Benchmark, Q1 2024 (PDF), soft-cost breakdown
Gross CAPEX930,000Sum of above (modelled input)
Net CAPEX after 30% ITC651,000930,000 × (1 − 0.30) — IRC §48 base credit statute: 26 U.S. Code §48 — Energy credit (Cornell Legal Information Institute); bonus adders PENDING verification

IRC §48 base credit (30%) is applied. Bonus adders (energy community, domestic content, low-income) are PENDING verification by the project tax advisor and are not included in the headline CAPEX. Adders, if eligible, can reduce net CAPEX further.

5. Annual OpEx & inverter replacement (inputs to COMPUTED TABLES)

Year-1 O&M (preventive + monitoring + module washing)USD 11,000/yr (≈ USD 12/kWp-yr)C&I PV O&M rule of thumb (basis PENDING — see Sources table §11 row 5)
Annual escalation on O&M2.5%U.S. BLS labor-cost index, applied as model assumption (see Sources table §11 row 6)
Inverter replacement, Year 15USD 84,000Vendor quote basis PENDING — see Sources table §11 row 7 (replacement equal to original inverter CAPEX line, no degradation applied)
Module degradation0.5%/yr linearNREL module degradation meta-analysis, median for c-Si (basis cited via NREL benchmark report above)

6. COMPUTED TCO TABLES (verbatim — computed)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate6.00 %
Total undiscounted cost (USD)1,110,735.40
Total discounted cost / PV of costs (USD)864,575.10
Total undiscounted benefit (USD)3,502,069.02
Total discounted benefit (USD)1,714,038.01
NPV (USD)849,462.91
IRR0.1696
Simple payback (year)5.95
Discounted payback (year)7.52
LCOE (USD/kWh)0.0624
Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0651,000.000.0000-651,000.001.00-651,000.000.0000
111,000.00116,637.57105,637.570.943499,658.081,134,000.00
211,275.00118,375.47107,100.470.890095,319.041,128,330.00
311,556.88120,139.26108,582.390.839691,167.871,122,688.35
411,845.80121,929.34110,083.540.792187,196.481,117,074.91
512,141.94123,746.09111,604.140.747383,397.111,111,489.53
612,445.49125,589.90113,144.410.705079,762.351,105,932.09
712,756.63127,461.19114,704.570.665176,285.091,100,402.43
813,075.54129,360.36116,284.820.627472,958.541,094,900.41
913,402.43131,287.83117,885.400.591969,776.191,089,425.91
1013,737.49133,244.02119,506.530.558466,731.821,083,978.78
1114,080.93135,229.36121,148.430.526863,819.481,078,558.89
1214,432.95137,244.28122,811.320.497061,033.461,073,166.09
1314,793.78139,289.22124,495.440.468858,368.321,067,800.26
1415,163.62141,364.63126,201.000.442355,818.831,062,461.26
1599,542.71143,470.9643,928.250.417318,329.721,057,148.96
1615,931.28145,608.68129,677.400.393651,047.021,051,863.21
1716,329.56147,778.24131,448.680.371448,815.361,046,603.89
1816,737.80149,980.14133,242.340.350346,680.631,041,370.88
1917,156.25152,214.84135,058.600.330544,638.621,036,164.02
2017,585.15154,482.85136,897.690.311842,685.351,030,983.20
2118,024.78156,784.64138,759.860.294240,816.961,025,828.28
2218,475.40159,120.73140,645.330.277539,029.801,020,699.14
2318,937.29161,491.63142,554.340.261837,320.341,015,595.65
2419,410.72163,897.86144,487.140.247035,685.221,010,517.67
2519,895.99166,339.93146,443.950.233034,121.241,005,465.08

6.1 Year-1 benefit split (reproducibility of the USD 116,637.57 figure)

Benefit componentkWhRate (USD/kWh)USD
Self-consumed PV (avoided grid purchase)1,088,0000.105 (blended industrial avoided cost)114,240.00
Exported surplus (avoided-cost credit, not retail)46,0000.0521 (export tariff — model assumption, see §7)2,397.57
Year-1 benefit total1,134,000—116,637.57

Splits stated to make the Year-1 benefit reproducible from the stated inputs. The export rate (0.0521 USD/kWh) is an explicit bounded model assumption, not a sourced fact (see §7 row "Export tariff").

7. Assumptions & limits

Inputs (matched to COMPUTED TABLES, exact): Explicit bounded defaults the draft did not state (model assumptions, never sourced facts): Limits / PENDING items:

8. HS code & duty-rate block

Lookup instructions (do not assert duty rates as fact):
  1. For the modules, start at US HTS heading 8541.40 (photovoltaic cells, arranged in modules or panels) via the USITC Harmonized Tariff Schedule search.
  2. For string inverters, start at US HTS 8504.40 (static converters) — confirm whether the specific inverter SKU is classified as a "static converter" or a "photovoltaic inverter" sub-line, via the USITC HTS search.
  3. Confirm country of origin for each SKU; duty rate is origin-dependent.
  4. Check Section 201 / 301 / AD-CVD overlays (US has applied these to certain solar origins historically; status changes). See US Customs and Border Protection and US International Trade Administration.
  5. Confirm with USITC HTS and CBP CROSS rulings, then with a licensed customs broker before shipment.
Duty rates: PENDING verification — never assert as fact.

9. Mini certifications & standards block

10. RFQ CTA

Request a single RFQ for a 900 kWp US food-plant array

RFQ is routed through the TradVolt RFQ form only.

11. Sources & citations

#ClaimCitationStatus
1Year-1 PV generation = 1,134 MWh (900 kWp × 1,260 kWh/kWp)EU PVGIS (PVGIS-SARAH2)Sourced
2Blended industrial avoided-cost tariff = 0.105 USD/kWhEIA Table 5.6.A — Average Price of Electricity to Ultimate Customers, IndustrialSourced
3Daytime load share ≈54% for two-shift food plantUSDA REAP audit template (programme entry: USDA Rural Development energy programs)Sourced (programme page); specific REAP audit template PDF confirmed at RFQ
4Module / inverter / racking cost bandsIEA; cross-checked against Fraunhofer ISE Photovoltaics Report and UK DESNZ solar PV cost data; K2 Systems list price confirmed at RFQSourced (band level)
5O&M = 12 USD/kWp-yr basisC&I PV O&M rule of thumb (no specific citation at this granularity)PENDING — model assumption, to be replaced by EPC contract quote
6O&M escalation = 2.5%/yrU.S. BLS labor-cost index assumption (general program: BLS Consumer Price Index; specific escalation series confirmed at RFQ)PENDING — model assumption
7Inverter replacement at Year 15 = 84,000 USDVendor quote basis PENDING (model currently assumes replacement = original inverter CAPEX line)PENDING
8Export surplus credit basis = 0.0521 USD/kWh (Year-1)asset.pv.export_tariff_per_kwh model default (no public source at this specificity)Model assumption (bounded default)
9Tariff escalation = 0%/yr real over horizonasset.pv.tariff_escalation_pct model defaultModel assumption (bounded default)
1030% ITC base credit applied to gross CAPEX26 U.S. Code §48 — Energy credit (Cornell LII)Sourced (statute)
11Module safety qualificationUL 61730-1 (UL Product iQ); IEC 61215 catalogue query: IEC Webstore (full designation at RFQ)Sourced
12BoS / EPC / soft-cost benchmarksNREL — U.S. Solar Photovoltaic System and Energy Storage Cost Benchmark, Q1 2024 (PDF)Sourced
13HS classification lookup path (modules / inverters)USITC Harmonized Tariff Schedule search; US Customs and Border Protection; US International Trade AdministrationSourced (lookup tools)

12. Disclaimer

This page is an engineering and financial illustration for a generic US food-processing site. It is not a quote, an offer, or a tariff classification. Site-specific factors — actual load shape, roof structural capacity, interconnection cost, tariff class, demand charges, ITC bonus adders, and HS classification — must be verified before any commitment. All duty rates are PENDING verification; never rely on this page for customs decisions. TradVolt does not provide tax, legal, or customs advice. No third-party endorsements are implied by the citation of any source, OEM, or standard.