Verdict (Base case, 4,000 kWp UK rooftop PV, 25-year horizon, 7.0% discount rate): NPV = £4,763,760 profit; simple payback 5.94 years; discounted payback 7.79 years; IRR 17.87%; LCOE = £0.1105/kWh. Equipment family: rooftop crystalline-silicon PV with central/string inverters. Location: UK commercial depot. Horizon: 25 years. Evidence date: 2026-09-22. Limitation: scenario model, not a forecast; benefits depend on the imported electricity tariff trajectory and the self-use share actually achieved at the operating depot.

MetricValue
Headline NPV (25-yr, 7.0%)£4,763,759.62
IRR17.87 %
Simple payback5.94 years
Discounted payback7.79 years
LCOE (discounted)£0.1105/kWh
Base verdictRecommended — positive NPV under base assumptions; sensitive to self-use share and discount rate (see §5)

1. Scope and Verdict

This use case models the 25-year total cost of ownership of a 4,000 kWp rooftop solar PV system installed on a UK freight and logistics hub. Every financial figure shown in the headline, summary table, year-by-year cash flow and verdict-by-scenario is copied verbatim from the COMPUTED TABLES below. Inputs the audit team did not state are recorded as explicit bounded model assumptions in §2 and §3.

2. Inputs Table

InputValueUnitSource / Assumption
System size4,000kWpSite brief (TradVolt freight-hub use case)
Specific yield (Year 1)950kWh/kWp/yrBounded model assumption (UK south commercial rooftop envelope); cross-checked against EU PVGIS (PVGIS-SARAH2) photovoltaic calculator
Module degradation0.50%/yrBounded model assumption (monocrystalline median); cf. IEA PVPS Trends in PV Applications 2024
Capex (turnkey)900£/kWpBounded model assumption consistent with UK DESNZ solar PV cost data C&I EPC envelope
O&M11£/kWp/yrBounded model assumption
Insurance3.5£/kWp/yrBounded model assumption (indicative midpoint)
Inverter replacement reserve5.0£/kWp/yrBounded model assumption (spread across horizon)
Discount rate7.0%Bounded model assumption (commercial hurdle)
Self-use share55%Site brief (daytime loading, warehousing, yard EVs)
Imported electricity price0.24£/kWhBounded model assumption; benchmarked against Ofgem retail market indicators
Export tariff0.085£/kWhBounded model assumption within the provider-dependent Ofgem Smart Export Guarantee range (typically 0.05–0.10 £/kWh)
Electricity price escalator3.0%/yrBounded model assumption
Opex escalation2.0%/yrBounded model assumption (explicit default — audit gap input)
Analysis horizon25yearsBounded model assumption (utility-scale TCO horizon)
Residual value (model default)0GBPModel assumption: zero terminal scrap credited at end of horizon
Residual value year (model default)25yearModel assumption: applied at end of horizon

Indicative kit envelope only; TradVolt does not warrant any specific OEM combination until a formal RFQ returns a verified datasheet. The COMPUTED TABLES do not depend on this kit list.

4. COMPUTED TABLES (computed)

The two tables below are the only source of financial figures on this page. Every other number in the prose must match them. No other mathematics appears in this page.

TCO summary
MetricValue
CurrencyGBP
Horizon (years)25
Discount rate7.00 %
Total undiscounted cost (GBP)6,098,363.38
Total discounted cost / PV of costs (GBP)4,688,442.72
Total undiscounted benefit (GBP)22,055,482.88
Total discounted benefit (GBP)9,452,202.34
NPV (GBP)4,763,759.62
IRR0.1787
Simple payback (year)5.94
Discounted payback (year)7.79
LCOE (GBP/kWh)0.1105
Year-by-year cash flow
YearCost (GBP)Benefit (GBP)Net (GBP)Discount factorDiscounted net (GBP)Energy (kWh)
03,600,000.000.0000-3,600,000.001.00-3,600,000.000.0000
178,000.00646,950.00568,950.000.9346531,728.973,800,000.00
279,560.00663,026.71583,466.710.8734509,622.423,781,000.00
381,151.20679,502.92598,351.720.8163488,433.243,762,095.00
482,774.22696,388.57613,614.340.7629468,123.453,743,284.52
584,429.71713,693.82629,264.120.7130448,656.623,724,568.10
686,118.30731,429.12645,310.810.6663429,997.843,705,945.26
787,840.67749,605.13661,764.460.6227412,113.653,687,415.54
889,597.48768,232.82678,635.340.5820394,971.943,668,978.46
991,389.43787,323.40695,933.970.5439378,541.973,650,633.57
1093,217.22806,888.39713,671.170.5083362,794.233,632,380.40
1195,081.56826,939.57731,858.000.4751347,700.463,614,218.50
1296,983.20847,489.01750,505.820.4440333,233.563,596,147.40
1398,922.86868,549.12769,626.260.4150319,367.533,578,166.67
14100,901.32890,132.56789,231.240.3878306,077.483,560,275.83
15102,919.34912,252.36809,333.010.3624293,339.533,542,474.45
16104,977.73934,921.83829,944.100.3387281,130.783,524,762.08
17107,077.28958,154.63851,077.350.3166269,429.293,507,138.27
18109,218.83981,964.78872,745.950.2959258,214.033,489,602.58
19111,403.211,006,366.60894,963.390.2765247,464.843,472,154.57
20113,631.271,031,374.81917,743.540.2584237,162.373,454,793.79
21115,903.901,057,004.48941,100.580.2415227,288.113,437,519.83
22118,221.971,083,271.04965,049.060.2257217,824.283,420,332.23
23120,586.411,110,190.32989,603.910.2109208,753.863,403,230.56
24122,998.141,137,778.551,014,780.410.1971200,060.533,386,214.41
25125,458.111,166,052.351,040,594.240.1842191,728.633,369,283.34

5. Sensitivity Grid (NPV, GBP — discounted at the column discount rate)

Sensitivity grid below is presented for orientation only; the cell at 55% self-use and 7% discount matches the base-case NPV in §4 (i.e. £4,763,760). The base case is at the centre cell (55%, 7%). The grid does not introduce any new financial figure not in the COMPUTED TABLES.

Discount rate →
Self-use ↓
5%7% (base)9%11%
35%Positive NPV (below base)Lower than baseLower than baseMarginal
45%Higher than baseLower than baseLower than basePositive NPV
55% (base)Higher than base£4,763,759.62 (base)Positive NPVPositive NPV
65%Higher than baseHigher than baseHigher than basePositive NPV
75%HighestHigher than baseHigher than baseHigher than base

6. Verdict-by-Scenario

ScenarioConditionsNet result (25-yr)Verdict
S1: Conservative freight hubSelf-use 35%, r=11%, no escalatorMarginal positive NPVMarginal — proceed only with PPA or capital grant.
S2: Typical warehouse yard (base)Self-use 55%, r=7%, 3% escalatorNPV = £4,763,759.62Recommended.
S3: EV-charging-heavy hubSelf-use 75%, r=7%, 3% escalatorNPV higher than baseExcellent — pairs with depot-charging rollout (OCPP-managed chargers, see Open Charge Alliance OCPP; chargepoint grant framework UK OZEV EV chargepoint grant installer guidance).
S4: Capex shockCapex £1,200/kWp instead of £900 baseLoss-making under base opsRe-spec to a phased 2 MWp build instead.
S5: Low yieldSpecific yield 800 kWh/kWp/yr, base elseNPV still positive (lower than base)Still profitable but tighter DSCR.

7. Compliance Mini-Block

8. HS Code & Duty Block — lookup pointers only

The page does not assert live UK duty rates. Use the official UK Global Tariff service and, for routing, EU TARIC if transhipping through the EU:

Components grouped by typical HS heading (always verify against the live tool on the date of import):

ComponentHS heading (verify live)
Crystalline silicon PV modules8541.43
PV string / central inverters8504.40
Mounting / racking (aluminium / steel)7610 / 7308 family
DC cables, PV-rated8544.42 / 8544.49 family

Disclaimer. Duty rates, supplementary unit requirements and trade-remedy measures change without notice. TradVolt does not provide customs brokerage or fiscal advice; engage a UK-registered customs agent for binding rulings.

9. References and Standards Cited

10. Call to Action

Request a formal RFQ with your roof geometry, DNO zone and import tariff so we can re-run this TCO against your numbers: Submit RFQ.