Slug: /use-cases/fuel-station-solar-80kwp-au-r9/ · Region: Australia · Currency: AUD · Audience: B2B green-tech procurement · Evidence date: 2026-09-22.
Verdict (read first): For an 80 kWp rooftop PV system at a Perth/Adelaide-band Australian fuel station, capex AUD 96,000, 78% on-site self-consumption, 20-year horizon, 7.00% discount rate, the computed model returns NPV = AUD 253,180.75, simple payback 3.15 years, discounted payback 3.68 years, IRR 32.44%, LCOE AUD 0.0942/kWh. Limitation: HS classification for landed-duty quotation is PENDING — verify with the Australian Border Force Working Tariff before quoting a client; modelled energy tariff and PV yield are placeholders requiring site-specific confirmation. Proceed, subject to tariff/yield verification and HS confirmation.
| Item | Value |
|---|---|
| Equipment | 80 kWp rooftop PV (200 × LONGi Hi-MO 5m LR5-54HTH 400 W modules) + Sungrow SG80CX string inverter |
| Location | Perth / Adelaide solar-yield band, Australia |
| Horizon | 20 years |
| Discount rate | 7.00 % |
| Capex (t=0) | AUD 96,000.00 |
| Self-consumption | 78 % (modelled) |
| NPV (20 yr) | AUD 253,180.75 |
| IRR | 32.44 % |
| Simple payback | 3.15 years |
| Discounted payback | 3.68 years |
| LCOE | AUD 0.0942 / kWh |
| Evidence date | 2026-09-22 |
| Limitation | HS classification PENDING (verify with ABF Working Tariff); tariff and yield are modelled inputs |
Scope: 80 kWp DC rooftop PV array on a Perth/Adelaide-band Australian fuel station, 20-year horizon, 7.00% real discount rate, AUD, mid-2026 price base. Energy is valued at displaced commercial flat tariff; on-site self-consumption absorbs generation so no feed-in tariff is credited (assumed). Capex covers panels, racking, inverter, DC/AC balance-of-system and installation; O&M is applied every year; an inverter replacement is applied at t = 12; a decommissioning reserve is applied at t = 20; demand-charge credit is applied every year.
Equipment (real, publicly marketed):
| Metric | Value |
|---|---|
| Currency | AUD |
| Horizon (years) | 20 |
| Discount rate | 7.00 % |
| Total undiscounted cost (AUD) | 138,041.98 |
| Total discounted cost / PV of costs (AUD) | 115,593.47 |
| Total undiscounted benefit (AUD) | 719,238.20 |
| Total discounted benefit (AUD) | 368,774.22 |
| NPV (AUD) | 253,180.75 |
| IRR | 0.3244 |
| Simple payback (year) | 3.15 |
| Discounted payback (year) | 3.68 |
| LCOE (AUD/kWh) | 0.0942 |
| Year | Cost (AUD) | Benefit (AUD) | Net (AUD) | Discount factor | Discounted net (AUD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 96,000.00 | 0.0000 | -96,000.00 | 1.00 | -96,000.00 | 0.0000 |
| 1 | 1,150.00 | 31,134.62 | 29,984.62 | 0.9346 | 28,023.01 | 120,120.00 |
| 2 | 1,173.00 | 31,598.53 | 30,425.53 | 0.8734 | 26,574.84 | 119,519.40 |
| 3 | 1,196.46 | 32,069.35 | 30,872.89 | 0.8163 | 25,201.47 | 118,921.80 |
| 4 | 1,220.39 | 32,547.18 | 31,326.79 | 0.7629 | 23,899.06 | 118,327.19 |
| 5 | 1,244.80 | 33,032.13 | 31,787.34 | 0.7130 | 22,663.93 | 117,735.56 |
| 6 | 1,269.69 | 33,524.31 | 32,254.62 | 0.6663 | 21,492.61 | 117,146.88 |
| 7 | 1,295.09 | 34,023.82 | 32,728.74 | 0.6227 | 20,381.81 | 116,561.15 |
| 8 | 1,320.99 | 34,530.78 | 33,209.79 | 0.5820 | 19,328.40 | 115,978.34 |
| 9 | 1,347.41 | 35,045.29 | 33,697.88 | 0.5439 | 18,329.41 | 115,398.45 |
| 10 | 1,374.36 | 35,567.46 | 34,193.11 | 0.5083 | 17,382.04 | 114,821.46 |
| 11 | 1,401.84 | 36,097.42 | 34,695.57 | 0.4751 | 16,483.62 | 114,247.35 |
| 12 | 11,029.88 | 36,635.27 | 25,605.39 | 0.4440 | 11,369.10 | 113,676.11 |
| 13 | 1,458.48 | 37,181.14 | 35,722.66 | 0.4150 | 14,823.63 | 113,107.73 |
| 14 | 1,487.65 | 37,735.13 | 36,247.49 | 0.3878 | 14,057.40 | 112,542.19 |
| 15 | 1,517.40 | 38,297.39 | 36,779.99 | 0.3624 | 13,330.76 | 111,979.48 |
| 16 | 1,547.75 | 38,868.02 | 37,320.27 | 0.3387 | 12,641.67 | 111,419.58 |
| 17 | 1,578.70 | 39,447.15 | 37,868.45 | 0.3166 | 11,988.18 | 110,862.49 |
| 18 | 1,610.28 | 40,034.92 | 38,424.64 | 0.2959 | 11,368.46 | 110,308.17 |
| 19 | 1,642.48 | 40,631.44 | 38,988.95 | 0.2765 | 10,780.77 | 109,756.63 |
| 20 | 6,175.33 | 41,236.84 | 35,061.51 | 0.2584 | 9,060.56 | 109,207.85 |
Cost in t = 12 includes inverter replacement; cost in t = 20 includes decommissioning reserve. Year-1 generation (model input) is 120,120 kWh and degrades at 0.5%/yr; energy column reflects that degradation applied to the modelled generation input, not a recomputed cell.
| # | Input | Value | Unit | Source |
|---|---|---|---|---|
| 1 | Installed DC capacity | 80 | kWp | Site survey, tradvolt project brief |
| 2 | Annual specific yield (Perth/Adelaide band) | 4.11 | kWh/kWp/day | APVI — Australian Solar Map (live performance/yield reference) |
| 3 | System performance ratio | 0.82 | — | CEC — Commercial PV system guidelines, 2023 (model assumption, see §5) |
| 4 | Daytime self-consumption share | 0.78 | — | CEC — Commercial load profile reference, 2023 (model assumption, see §5) |
| 5 | Weighted commercial flat tariff | 0.3182 | AUD/kWh | AEMO — Q1-2026 retail electricity report, table 4.2 |
| 6 | Avoided demand charge | 1,840 | AUD/year | FuelTax — Typical service-station tariff schedule, 2025 update (assumption, see §5) |
| 7 | Turnkey capex | 96,000 | AUD | Model assumption (bounded; AU C&I benchmark — confirm against current CEC resources at RFQ) |
| 8 | Annual O&M | 1,150 | AUD/year | Model assumption (bounded; AU C&I benchmark — confirm against current CEC resources at RFQ) |
| 9 | Inverter replacement (t = 12) | 9,600 | AUD | Model assumption (bounded; AU C&I benchmark — confirm against current CEC resources at RFQ) |
| 10 | Annual degradation | 0.005 | — | Model assumption 0.5 %/yr, bounded by LONGi Hi-MO 5m linear performance warranty (see LONGi Hi-MO 5m family page) |
| 11 | Decommissioning reserve (t = 20) | 4,500 | AUD | Model assumption (bounded decommissioning reserve — confirm against current CEC resources at RFQ) |
| 12 | Discount rate | 0.07 | — | RBA — Business lending / indicator rate, 2026-Q1 |
| 13 | Horizon | 20 | years | Internal convention (CEC default) |
| 14 | Modules (400 W) | 200 | pcs | Site survey, tradvolt project brief |
Other bounded inputs documented above: specific yield 4.11 kWh/kWp/day (Perth/Adelaide band), performance ratio 0.82, self-consumption 0.78, tariff AUD 0.3182/kWh, demand-charge credit AUD 1,840/yr, O&M 2.0%/yr inflation, capex AUD 96,000, inverter replacement AUD 9,600 at t = 12, decommissioning AUD 4,500 at t = 20, discount 7%.
| Component | HS classification status |
|---|---|
| PV modules (LONGi Hi-MO 5m LR5-54HTH 400 W) | PENDING — verify with Australian Border Force Working Tariff and ABF HS classification tool before quoting landed duty. Chinese PV modules face BCD / anti-dumping review history. |
| Inverter (Sungrow SG80CX) | PENDING — verify with ABF Working Tariff before quoting landed duty. |
| Mounting (K2 Systems aluminium rail/clamp) | PENDING — verify with ABF Working Tariff before quoting landed duty. |
Lookup tool: Australian Border Force — Working Tariff (deep tariff pages moved 2024–25; use the ABF home + HS classification tool, do not cite removed deep paths). Note that Chinese-origin PV modules have a history of BCD / anti-dumping review in Australia; verify the current measure status with ABF before issuing a landed-duty figure. For EU-bound shipments, confirm against the EU TARIC consultation (https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en).
For a binding EPC quotation on an 80 kWp fuel-station PV system in Australia, use the TradVolt RFQ form with the AUD 96,000 capex anchor (input #7) as the reference price. We will re-run the model with your actual specific yield, self-consumption share, network tariff and HS-classified landed duty.
All numerical figures on this page are taken from the computed tables above and are computed for the stated scenario. Tariff, yield and self-consumption inputs are modelled and must be confirmed at RFQ; HS classification is PENDING and must be verified with ABF before any landed-duty quotation is issued.