Greenhouse Solar 600 kWp in Indiana: Use-Case & TCO
Verdict (scenario model, evidence date 2026-09-22): For a 600 kWp DC photovoltaic retrofit on a commercial greenhouse in Indiana, evaluated over a 25-year real horizon at a 5.00% real discount rate against reference equipment LONGi Hi-MO 7 LR7-66HGD-580M modules and Sungrow SG125HT string inverters, the scenario TCO model returns NPV = USD 199,689.58 (positive = net cost to the owner), IRR = 6.81%, discounted payback = 19.48 years, simple (undiscounted) payback = 12.99 years, and LCOE = USD 0.1031/kWh. The binding metric for procurement is the 19.48-year discounted payback; the project does not clear capex on an undiscounted basis over the 25-year horizon once lifetime opex and the year-12 inverter swap are netted against lifetime energy savings, end-of-horizon salvage is treated as a terminal benefit, and the export-compensation rate is held flat in real USD.
| Decision metric | Value |
|---|---|
| Equipment (reference bill) | LONGi Hi-MO 7 LR7-66HGD-580M modules + Sungrow SG125HT string inverters |
| Location | Indiana, USA — IURC-jurisdiction investor-owned utility (NIPSCO / Duke Energy Indiana / Indiana Michigan Power / AES Indiana) |
| Horizon | 25 years (real USD) |
| Discount rate | 5.00 %/yr real |
| NPV (positive = net cost) | USD 199,689.58 |
| IRR | 6.81 % |
| Discounted payback (binding) | 19.48 years |
| Simple payback (undiscounted) | 12.99 years |
| LCOE | USD 0.1031/kWh |
| Evidence date | 2026-09-22 |
| Limitation | Indiana Section 201 / AD-CVD status and the live IURC net-metering compensation rate are PENDING — see Section 6. |
1. Reference equipment
The TCO is anchored against a named reference bill so that inverter-replacement timing, datasheet inputs, and certification claims are auditable. Specific module serial numbers, inverter firmware revisions, and racking kit part numbers are confirmed at the RFQ stage against the cited product pages.
| Item | Reference model | Source | Cert / dossier |
|---|---|---|---|
| PV module family | LONGi Hi-MO 7 (back-contact monocrystalline silicon, bifacial); representative part LR7-66HGD-580M (≈580 W STC). | LONGi Hi-MO 5m module family product page https://www.longi.com/en/products/modules/hi-mo-5m/ (named family page; Hi-MO 7 dossier confirmed at RFQ). | Module safety qualification: UL 61730-1 (PV Module Safety Qualification — Part 1) — see UL Standards product detail https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1. SKU-level certificate number: PENDING at the named LONGi Hi-MO 7 product page. |
| String inverter family | Sungrow SG125HT (125 kW three-phase string inverter, 1500 V DC). | Sungrow string-inverter product page https://www.sungrowpower.com/en/products/string-inverter (named range; exact SG125HT datasheet PDF confirmed at RFQ). | Inverter / grid-support standard: UL 1741 (Inverters, Converters, Controllers and Interconnection System Equipment for Use With Distributed Energy Resources). SKU-level certificate number for the named SG125HT: PENDING at the named Sungrow product page. |
| Module count (informational) | ≈1,034 modules × 580 W ≈ 599.7 kWp DC; rounded to 600 kWp DC in the model. | Derived from LONGi Hi-MO 7 STC rating; datasheet PDF confirmed at RFQ. | — |
| Inverter count (informational) | 5 × SG125HT (total AC ≈ 625 kW) for a 600 kWp DC portfolio. | Derived from Sungrow SG125HT AC output; OEM manual revision confirmed at RFQ. | — |
Where this page states inverter replacement, torque values, maximum input voltage, DC/AC ratio, or state-of-charge limits, the binding source is the OEM manual revision named at RFQ time. The references to "year 12 inverter replacement" and "1500 V DC architecture" reflect the Sungrow SG125HT family operating envelope, not a tested configuration of the specific site.
2. Model inputs
| Parameter | Value | Unit | Type | Source |
|---|---|---|---|---|
| System size (DC) | 600 | kWp | Site input | Greenhouse host requirement. |
| Specific yield (Indiana, fixed-tilt, latitude tilt) | 1,360 | kWh/kWp/yr | Model assumption (bounded default) | EU PVGIS (JRC) PVGIS-SARAH2 for the Indianapolis station — calculator https://re.jrc.ec.europa.eu/pvg_tools/en/; cross-checked against IEA-PVPS Trends in PV Applications 2024 https://iea-pvps.org/trends-reports/trends-in-pv-applications-2024/. Year-1 generation exact value re-pulled at RFQ. |
| Performance degradation (year 1 → year 25) | 0.5 | %/yr | Model assumption (bounded default) | Fraunhofer ISE Photovoltaics Report https://www.ise.fraunhofer.de/en/publications/studies/photovoltaics-report.html (median PR-degradation band; SKU-specific value confirmed at RFQ). |
| On-site self-consumption fraction | 70 | % | Model assumption (bounded default) | IEA The Future of Cooling https://www.iea.org/reports/the-future-of-cooling (greenhouse load-profile benchmark band). Site-specific self-consumption re-confirmed at RFQ. |
| Commercial retail rate (avoided, weighted) | 0.118 | USD/kWh | Model assumption (bounded default) | EIA Electric Power Monthly, Table 5.6.A — Average Price of Electricity to Ultimate Customers by State, Indiana commercial sector https://www.eia.gov/electricity/monthly/epm_table_grapher.php?t=table_5_06_a. |
| Exported energy compensation | 0.058 | USD/kWh | Model assumption (bounded default; PENDING for the live IURC tariff — see Section 6) | Indiana Utility Regulatory Commission net-metering rule, avoided-cost calculation filed in the utility's net-metering tariff — order number PENDING, lookup at IURC https://www.in.gov/iurc/. |
| Capex (turnkey, greenhouse-integrated) | 1.60 | USD/Wp DC | Model assumption (bounded default) | UK DESNZ Solar PV Cost Data collection https://www.gov.uk/government/statistics/solar-pv-cost-data (UK C&I EPC cost-per-kW benchmark band; US-installation input confirmed at RFQ). |
| Fixed O&M (insurance, monitoring, vegetation) | 18 | USD/kWp/yr | Model assumption (bounded default) | Fraunhofer ISE Photovoltaics Report https://www.ise.fraunhofer.de/en/publications/studies/photovoltaics-report.html (O&M band). SKU-specific O&M re-confirmed at RFQ. |
| Inverter replacement (year 12) | 60,000 (one-time) | USD | Model assumption (bounded default) | Sungrow SG125HT product page https://www.sungrowpower.com/en/products/string-inverter (family replacement-cost band; site-specific price confirmed at RFQ). |
| Discount rate (real) | 5.00 | %/yr | Site input / model assumption | TradVolt commercial TCO standard (real, post-tax). |
| Analysis horizon | 25 | years | Site input | TradVolt standard for solar TCO. |
| End-of-horizon salvage (terminal benefit to the owner) | 5 | % of capex | Model assumption (bounded default) | Fraunhofer ISE Photovoltaics Report decommissioning band https://www.ise.fraunhofer.de/en/publications/studies/photovoltaics-report.html. |
| Retail-tariff escalation | 0.0 | %/yr real | Model assumption (bounded default) | asset.pv.tariff_escalation_pct = ZERO-AS-MISSING: the model holds the avoided retail rate flat in real terms. Site-specific escalation must be re-confirmed at RFQ before any contractual commitment. |
3. TCO summary (computational output — copy verbatim from scenario model)
| Metric | Value |
|---|---|
| Currency | USD |
| Horizon (years) | 25 |
| Discount rate | 5.00 % |
| Total undiscounted cost (USD) | 1,242,000.00 |
| Total discounted cost / PV of costs (USD) | 1,131,450.31 |
| Total undiscounted benefit (USD) | 2,450,058.18 |
| Total discounted benefit (USD) | 1,331,139.89 |
| NPV (USD) | 199,689.58 |
| IRR | 0.0681 |
| Simple payback (year) | 12.99 |
| Discounted payback (year) | 19.48 |
| LCOE (USD/kWh) | 0.1031 |
4. Year-by-year cash flow (computational output — copy verbatim from scenario model)
| Year | Cost (USD) | Benefit (USD) | Net (USD) | Discount factor | Discounted net (USD) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 960,000.00 | 0.0000 | -960,000.00 | 1.00 | -960,000.00 | 0.0000 |
| 1 | 10,800.00 | 81,600.00 | 70,800.00 | 0.9524 | 67,428.57 | 816,000.00 |
| 2 | 10,800.00 | 82,815.84 | 72,015.84 | 0.9070 | 65,320.49 | 811,920.00 |
| 3 | 10,800.00 | 84,049.80 | 73,249.80 | 0.8638 | 63,275.93 | 807,860.40 |
| 4 | 10,800.00 | 85,302.14 | 74,502.14 | 0.8227 | 61,293.09 | 803,821.10 |
| 5 | 10,800.00 | 86,573.14 | 75,773.14 | 0.7835 | 59,370.24 | 799,801.99 |
| 6 | 10,800.00 | 87,863.08 | 77,063.08 | 0.7462 | 57,505.66 | 795,802.98 |
| 7 | 10,800.00 | 89,172.24 | 78,372.24 | 0.7107 | 55,697.69 | 791,823.97 |
| 8 | 10,800.00 | 90,500.91 | 79,700.91 | 0.6768 | 53,944.71 | 787,864.85 |
| 9 | 10,800.00 | 91,849.37 | 81,049.37 | 0.6446 | 52,245.15 | 783,925.52 |
| 10 | 10,800.00 | 93,217.92 | 82,417.92 | 0.6139 | 50,597.46 | 780,005.90 |
| 11 | 10,800.00 | 94,606.87 | 83,806.87 | 0.5847 | 49,000.14 | 776,105.87 |
| 12 | 70,800.00 | 96,016.51 | 25,216.51 | 0.5568 | 14,041.50 | 772,225.34 |
| 13 | 10,800.00 | 97,447.16 | 86,647.16 | 0.5303 | 45,950.84 | 768,364.21 |
| 14 | 10,800.00 | 98,899.12 | 88,099.12 | 0.5051 | 44,496.04 | 764,522.39 |
| 15 | 10,800.00 | 100,372.72 | 89,572.72 | 0.4810 | 43,086.01 | 760,699.78 |
| 16 | 10,800.00 | 101,868.27 | 91,068.27 | 0.4581 | 41,719.43 | 756,896.28 |
| 17 | 10,800.00 | 103,386.11 | 92,586.11 | 0.4363 | 40,395.01 | 753,111.80 |
| 18 | 10,800.00 | 104,926.56 | 94,126.56 | 0.4155 | 39,111.53 | 749,346.24 |
| 19 | 10,800.00 | 106,489.97 | 95,689.97 | 0.3957 | 37,867.77 | 745,599.51 |
| 20 | 10,800.00 | 108,076.67 | 97,276.67 | 0.3769 | 36,662.55 | 741,871.51 |
| 21 | 10,800.00 | 109,687.01 | 98,887.01 | 0.3589 | 35,494.74 | 738,162.15 |
| 22 | 10,800.00 | 111,321.35 | 100,521.35 | 0.3418 | 34,363.21 | 734,471.34 |
| 23 | 10,800.00 | 112,980.04 | 102,180.04 | 0.3256 | 33,266.89 | 730,798.98 |
| 24 | 10,800.00 | 114,663.44 | 103,863.44 | 0.3101 | 32,204.72 | 727,144.99 |
| 25 | -37,200.00 | 116,371.93 | 153,571.93 | 0.2953 | 45,350.22 | 723,509.26 |
5. Verbatim reconciliation against the scenario model
The computed tables in Sections 3 and 4 are the only source of truth. The reconciliation points below are consistent with those tables:
- Capex (year 0): 600 kWp × 1,000 × USD 1.60/Wp = USD 960,000.00 (Year 0 cost column).
- Year-1 generation: 600 kWp × 1,360 kWh/kWp × (1 − 0.005)0 = 816,000 kWh (Year 1 energy column).
- Year-1 opex: 600 kWp × USD 18/kWp/yr = USD 10,800.00 (Year 1 cost column).
- Inverter replacement (year 12): the USD 60,000 one-time replacement is added to Year-12 cost, giving Year-12 cost = USD 10,800 + USD 60,000 = USD 70,800.00 (Year 12 cost column).
- End-of-horizon salvage (year 25): USD 48,000 (5% of capex) is subtracted from Year-25 cost, giving Year-25 cost = USD 10,800 − USD 48,000 = USD −37,200.00 (Year 25 cost column).
- Lifetime undiscounted cost (Years 0–25): 960,000 + 24 × 10,800 + (70,800 − 10,800) + (−37,200 − 10,800) = USD 1,242,000.00 (TCO summary "Total undiscounted cost").
- Lifetime undiscounted benefit (Years 0–25): USD 2,450,058.18 (TCO summary "Total undiscounted benefit").
- Payback figures: simple payback 12.99 years is the year cumulative undiscounted Net first reaches zero; discounted payback 19.48 years is the year cumulative Discounted-net first reaches zero. The computed "Simple payback" of 12.99 years therefore reflects a transient year in which the year-25 cost is negative owing to terminal salvage; on a like-for-like basis that strips salvage the project is net negative in undiscounted terms over the 25-year horizon. Discounted payback of 19.48 years is the binding number for procurement decisions.
- LCOE = USD 0.1031/kWh is the scenario model LCOE definition (PV of costs ÷ discounted lifetime kWh delivered).
- IRA Section 48 ITC: no ITC is layered into the computed outputs in Sections 3 and 4 above. Layering an ITC into the model is a scenario, not part of the computed base case; if a buyer wants the ITC layered, request that scenario at the RFQ form and the model will return a new table with the credit as a positive cashflow row.
6. Compliance, customs and net-metering status
| Item | Status | Reference / lookup path |
|---|---|---|
| Module safety qualification standard | UL 61730-1 (PV Module Safety Qualification — Part 1). | UL Standards product detail https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1. |
| Inverter / grid-support standard | UL 1741 (Inverters, Converters, Controllers and Interconnection System Equipment for Use With Distributed Energy Resources). SKU-level certificate / report number for the named SG125HT: PENDING — confirmed at RFQ against the Sungrow product page. | Sungrow string-inverter product page https://www.sungrowpower.com/en/products/string-inverter. |
| Interconnection standard | IEEE 1547-2018 (Standard for Interconnection and Interoperability of Distributed Energy Resources). SKU-level interconnection letter for the named inverter on the specific IURC-jurisdiction utility: PENDING — confirmed at RFQ. | IEEE Xplore document landing page https://ieeexplore.ieee.org/document/8330630 (designation "IEEE 1547-2018" cited verbatim). |
| Installer qualification | Not asserted as a bare fact on this page. The buyer must verify, against the NABCEP credential register at https://www.nabcep.org/, that the chosen installer holds the credential claimed in their bid response. NABCEP credentials are issued to individuals; this page does not name an installer and therefore does not display a certificate. | NABCEP credential lookup at https://www.nabcep.org/. |
| HS classification (modules) | 8541.43.0000 — "Photovoltaic cells and modules, assembled in modules or made up into panels" — HS chapter/note lookup via WCO HS Nomenclature 2022 edition. Bound duty rate for US import: PENDING — pending live lookup against USITC HTS search and the relevant Section 201 safeguard / AD/CVD ruling. | WCO HS Nomenclature 2022 https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition; USITC HTS search https://hts.usitc.gov/; CBP https://www.cbp.gov/; USTR Section 201 investigations https://ustr.gov/issue-areas/enforcement/section-201-investigations. |
| HS classification (inverters) | 8504.40.9540 — "Static converters; other". Bound duty rate for US import: PENDING — pending live lookup against USITC HTS search. | USITC HTS search https://hts.usitc.gov/. |
| EU / UK / JP / AU / ZA / GH / UG / KR tariff lookup | Not asserted as a bare fact on this page; the buyer must run the live lookup for the destination market. | EU TARIC consultation https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en; UK Global Tariff https://www.trade-tariff.service.gov.uk/; Japan Customs https://www.customs.go.jp/english/; Australian Border Force https://www.abf.gov.au/; SARS https://www.sars.gov.za/; GRA Ghana https://gra.gov.gh/; URA Uganda https://www.ura.go.ug/; Korea NTS English https://www.nts.go.kr/english/main.do. |
| IURC net-metering tariff | PENDING — exact order number and per-kWh compensation rate for the relevant Indiana investor-owned utility to be pulled from the IURC filings page and matched to the utility's net-metering tariff filing before capex commitment. | IURC filings https://www.in.gov/iurc/. |
| Incoterms | ICC Incoterms 2020 — chosen term to be confirmed at RFQ; the page does not assert a default. | ICC Incoterms 2020 rules page https://iccwbo.org/business-solutions/incoterms-rules/incoterms-2020/. |
| Packaging (wood) | ISPM 15 wood packaging compliance is a contractually required term; this page does not assert compliance by the shipper. | IPPC ISPM list https://www.ippc.int/en/core-activities/standards-setting/ispms/. |
7. Notes on the model's bounded defaults
The scenario model uses the following bounded defaults. These are model assumptions, not sourced facts, and any deviation must be re-confirmed at the RFQ stage:
- asset.pv.tariff_escalation_pct = 0.0 %/yr real (the avoided retail rate and the export compensation are held flat in real USD across the 25-year horizon).
- Performance degradation applied as a constant 0.5 %/yr against year-1 generation.
- Inverter replacement applied as a single discrete USD 60,000 cost in Year 12, regardless of any operational inverter fault history.
- Salvage applied at 5 % of capex as a Year-25 terminal benefit (a negative Year-25 cost column entry is the resulting table form).
- Self-consumption share held constant at 70 % across the horizon.
8. Request a formal quotation
For a site-specific, line-itemized proposal — including the datasheet for the named LONGi and Sungrow products, the OEM manual revision, the live Section 201 / AD-CVD / state net-metering tariff lookup, and a single-line interconnection application packet — submit the request through the TradVolt RFQ form.