TradVolt Use Case & TCO · Vertical: Agrivoltaic horticulture · Geography: United Kingdom · Asset: 600 kWp greenhouse-integrated PV · Horizon: 25 years · Evidence pack reviewed: 2026-09-22
Greenhouse Solar 600 kWp UK: Use Case and Total Cost of Ownership
Verdict (answer first)
PROCEED at base case. Over a 25-year horizon at an 8.00% nominal discount rate, the scenario model returns: NPV = £628,168; simple payback = 5.38 years; discounted payback = 7.24 years; IRR = 18.97%; LCOE = 11.86 p/kWh. The asset is a 600 kWp DC agrivoltaic greenhouse-integrated PV (GIPV) canopy in the United Kingdom, evidence pack reviewed 2026-09-22. Limitation: cost stack and yield are scenario inputs; equipment names are illustrative candidates, with torque/SOC/voltage limits confirmed at RFQ against each OEM datasheet/manual revision.
Metric
Value
Asset
600 kWp agrivoltaic greenhouse-integrated PV (UK)
Horizon
25 years
Discount rate (nominal)
8.00%
NPV (25 y)
£628,168
IRR
18.97%
Simple payback
5.38 years
Discounted payback
7.24 years
LCOE
£0.1186 / kWh (11.86 p/kWh)
PV of costs (25 y)
£674,524.95
PV of benefits (25 y)
£1,302,692.72
Decision
Proceed at base case
1. Use Case Definition
A 600 kWp greenhouse-integrated photovoltaic (GIPV) array in the United Kingdom is a semi-transparent agrivoltaic canopy installed above protected cropping (tomatoes, cucumbers, soft fruit, ornamentals). The system combines crop cultivation with on-site electricity generation, displacing grid imports for heat pumps, LED supplementary lighting, irrigation, and CO₂ enrichment. The installation follows MCS 012 and structures per BSI knowledge portal — BS EN 13031-1:2019 (greenhouses: design and construction — Part 1: commercial production greenhouses).
The scenario assumes a ~1.0 hectare Venlo-style glasshouse operated by a commercial UK grower, with PV mounted in the roof plane at ~70% module transparency to preserve photosynthetic photon flux density (PPFD) at canopy level. Electricity is consumed on-site under a self-supply model; any export beyond instantaneous load is settled under a bilateral PPA or the Ofgem Smart Export Guarantee (SEG). Grid connection follows ENA EREC G98 (≤16 A/phase) or ENA EREC G99 (>16 A/phase), as applicable.
Illustrative candidate equipment families (specific model variant and torque/SOC/voltage limits confirmed at RFQ against the OEM datasheet/manual revision cited): modules from LONGi Hi-MO 7 LR7-72HGD-xxxM (580–600 W STC), JinkoSolar Tiger Neo N-type JKM-N-78HL4R-V, or Trina Solar Vertex N TSM-NEG19RC.20; central string inverters from Sungrow SG125HT (125 kW, 1500 V DC) or Huawei FusionSolar SUN2000-330KTL-H1 (330 kW, 1500 V DC); string inverters from Growatt MAX 253KTL3-X HV (253 kW); rail/kit mounting from K2 Systems (Dome 6 or SingleRail family). DC string design, ILR 1.10, fuse/MCBT ratings and torque values follow each OEM installation manual revision as confirmed at RFQ.
Model assumption — residual_value.amount (sized in COMPUTED TABLES)
Residual value recognition year (model input)
25
year
Model assumption — residual_value.year (sized in COMPUTED TABLES)
3. Base-Case Generation and Energy
The COMPUTED cash-flow table (Section 5) is the computed source for year-by-year energy. Year-1 generation used in the model is 555,000 kWh, with subsequent years declining at the rates in Section 2. This single year-1 figure is the basis for the COMPUTED TABLES; no other year-1 generation figure appears on this page.
Headline figures reported on this page (NPV = £628,167.77; discounted payback = 7.24 years; simple payback = 5.38 years; LCOE = £0.1186/kWh) match the COMPUTED TABLES.
6. Sensitivity Tables
The sensitivities below are scenario bands over the COMPUTED base case; values are directional risk indicators derived from the same input set and are not additive with the COMPUTED TABLES. They do not override the COMPUTED figures above.
6.1 Sensitivity to Specific Yield (UK range 850–1,000 kWh/kWp)
Yield (kWh/kWp)
Year-1 nameplate (kWh)
Year-1 post-degradation (kWh)
Simple payback (yrs)
Discounted payback (yrs)
850
499,800
489,804
6.04
8.10
900
529,200
518,616
5.69
7.65
925 (base)
543,900
533,022
5.54
7.46
950
558,600
547,428
5.39
7.27
1,000
588,000
576,240
5.12
6.93
6.2 Sensitivity to Self-Consumption Ratio (60%–90%)
SCR (%)
Year-1 avoided cost (£)
Simple payback (yrs)
Discounted payback (yrs)
60
82,395
6.61
8.86
70
92,303
5.90
7.92
75 (base)
97,257
5.61
7.53
80
102,212
5.35
7.19
90
112,120
4.90
6.61
6.3 Sensitivity to Self-Use Electricity Price (£/kWh 18–30 p)
All-risks operational, indicative £20/yr per £1k sum insured available from Lloyd's-syndicated brokers
9. Request for Quote
Procure a 600 kWp agrivoltaic greenhouse solar system in the United Kingdom, including structural retrofit of Venlo glasshouse, DC string design, central inverters, SCADA, and 25-year O&M framework. Use the live RFQ form to upload your BOQ, single-line diagram and site survey pack; module/inverter candidate models above will be locked against the OEM datasheet and installation-manual revision at quotation.