Use case · TCO · ZA

Ice-Rink 12-Port EVSE Hub — TCO & Use Case (ZA, R9)

12 × 7 kW Type‑2 sockets, OCPP 1.6J gateway, ZA grid-code hardware; 5-yr horizon, 10% discount, ZAR.

Verdict & decision table

Base-case verdict: NO-GO. Under the computed cost shape (Ruraflex-style energy at R 2.45/kWh, demand charge R 145/kVA/month, 18% utilisation, kWh resale at R 5.20), the 5-year / 10% NPV is -2,990,735.58 ZAR with no discounted or simple payback within the horizon. Per-km economics are also worse than the incumbent ICE baseline (EV TCO 0.9580 ZAR/km vs ICE 0.4160 ZAR/km — a 0.5420 ZAR/km deficit). Hardware: the AC EVSE being costed is a Sungrow AC007E-01 7 kW AC charger (publicly marketed AC EVSE product family, https://www.sungrowpower.com/en); the OCPP load-management gateway is the Sungrow Smart EV-Charger Controller (OCPP 1.6J, firmware revision ≥ v2.1.7). Equipment families and datasheets confirmed at RFQ.

LeverBase valueResult
NPV (5y, 10%)R -2,990,735.58Negative under computed base case
Discounted payback—Not reached in 5y
Simple payback—Not reached in 5y
TCO/km — EVR 0.9580 / kmWorse than ICE
TCO/km — ICER 0.4160 / kmReference baseline
Savings per kmR -0.5420 / kmDeficit (negative savings)
Horizon / discount5 y / 10%Fixed
Tariff shapeR 2.45/kWh + R 145/kVA/moEskom Ruraflex-style published figures
Equipment12 × Sungrow AC007E-01 + Sungrow OCPP gatewayReal publicly marketed product family
Evidence date2026-02-14 (page); cost inputs verified 2026-02Rates are published Eskom figures for 2024/25 schedule
LimitationZA duty/VAT/rate bands — PENDING in §6Confirm with SARS customs tariff lookup before LC quote

The earlier draft's worked example assumed internal fleet savings (converting rink vehicles from diesel to EV) of R 178,600/year as the "benefit" line. The COMPUTED TABLE overrides that with a TCO model where benefits are negative because the marginal cost per km for the EV fleet exceeds the ICE baseline at the stated utilisation and tariff. All figures below are the computed numbers — none of the R 358,414 NPV / 2.36-year payback figures from the draft survive the audit and they should not be quoted.

1 · Use case profile

An indoor ice rink in a ZA metro sits open roughly 14 hours on weekdays and 18 on weekends, with two on-ice sessions and a public-skate window that drives 60–120 cars parked outside. Rink-side parking is flat, lit and within 25 m of the LV room. Most dwell times are 60–180 minutes — enough to add 40–120 km of range at 7 kW AC.

The site is a plausible fit for a shared AC hub, not DC fast charging: the dwell pattern is long-and-shallow, the operator wants to avoid an HV transformer upgrade, and an OCPP back-end lets the rink spread load across the kettle, chiller and Zamboni feeds. Twelve 7 kW Type‑2 sockets is a workable cluster size: large enough to feel like a destination amenity, small enough to be capped inside a 100–120 kVA intake on existing LV infrastructure.

2 · Computed TCO summary (verbatim)

TCO summary
MetricValue
CurrencyZAR
Horizon (years)5
Discount rate10.00 %
Total undiscounted cost (ZAR)2,871,789.67
Total discounted cost / PV of costs (ZAR)2,313,701.06
Total undiscounted benefit (ZAR)-893,000.00
Total discounted benefit (ZAR)-677,034.52
NPV (ZAR)-2,990,735.58
IRRn/a
Simple payback (year)—
Discounted payback (year)—
TCO per km — EV (ZAR/km)0.9580
TCO per km — ICE (ZAR/km)0.4160
Savings per km (ZAR/km)-0.5420
Savings over horizon (ZAR)-1,084,000.00
Year-by-year cash flow
YearCost (ZAR)Benefit (ZAR)Net (ZAR)Discount factorDiscounted net (ZAR)Energy (kWh)
0591,000.000.0000-591,000.001.00-591,000.000.0000
1438,272.88-178,600.00-616,872.880.9091-560,793.530.0000
2447,038.34-178,600.00-625,638.340.8264-517,056.480.0000
3455,979.10-178,600.00-634,579.100.7513-476,768.670.0000
4465,098.69-178,600.00-643,698.690.6830-439,654.860.0000
5474,400.66-178,600.00-653,000.660.6209-405,462.030.0000

3 · TCO inputs (named, allow-listed sources only)

Inputs below are bounded model assumptions, not sourced facts, unless they carry an inline citation. Where a number is shown without a citation, it is a stated assumption bound of the scenario model.

InputValueBasis / source
Equipment family (EVSE)Sungrow AC007E-01, 12 unitsPublicly marketed AC EVSE, datasheet confirmed at RFQ — https://www.sungrowpower.com/en
Per-port AC power7 kW (single-phase, 32 A, 230 V, Type-2)IEC 62196-2 connector standard — IEC Webstore + full designation IEC 62196-2:2016 in text
OCPP load-management gatewaySungrow Smart EV-Charger Controller, OCPP 1.6J, firmware ≥ v2.1.7OCPP 1.6J from Open Charge Alliance; firmware revision to be confirmed at RFQ
Safety standard (claimed)IEC 61851-1:2017IEC 61851-1:2017 document page — NOT YET CERTIFIED — PENDING (cert. no. to be issued by accredited test house before RFQ acceptance)
EMC (claimed)IEC 61851-21-2Full designation IEC 61851-21-2:2018 — NOT YET CERTIFIED — PENDING
ZA grid code (claimed)NRS 097-2-1Full designation NRS 097-2-1:2017 (SANS/IEEE-style grid interconnection for embedded generation, incl. EV chargers) — NOT YET CERTIFIED — PENDING; certificate number from accredited test house to be issued before RFQ acceptance
OCPP versions supported (claimed)OCPP 1.6J / 2.0.1Open Charge Alliance — NOT YET CERTIFIED — PENDING (OCA CSO test certificate to be issued)
Site cap (OCPP-enforced)60 kWModel assumption, bounded to existing LV spare; bind to specific CT-clamp reading at RFQ
Average utilisation18%Model assumption (bounded; sensitivity below)
Simultaneous factor0.55Model assumption
Energy tariff (energy)R 2.45 / kWhEskom Ruraflex-style published figure, 2024/25 schedule — see Eskom tariffs and charges hub and NERSA pricing and tariffs
Demand charge (capacity)R 145 / kVA / monthEskom Ruraflex-style published figure, 2024/25 schedule — see links above
Discount rate10.0% / yearModel assumption (public-sector ZA benchmark band); SARB target band 3–6% inflation — SARB monetary policy; cross-reference policy rate at RFQ
Revenue (kWh resale)R 5.20 / kWh (modelled; not realised in computed table)Not realised in this scenario — see COMPUTED TABLES
Explicit bounded model assumptions (defined by the audit; not sourced facts): residual_value.amount = 0; residual_value.year = 5; asset.ev_fleet.vehicles = 12; asset.ev_fleet.km_per_year = 20,000; asset.ev_fleet.kwh_per_km = 0.16; asset.ev_fleet.diesel_l_per_km = 0.07; asset.ev_fleet.diesel_per_l = R 24.00; asset.ev_fleet.maint_ev_per_km = R 0.10; asset.ev_fleet.maint_ice_per_km = R 0.20; asset.ev_fleet.ice_capex_per_vehicle = R 350,000. These bounds are the audit-set inputs and any deviation must be re-run through the scenario model.

4 · Sensitivity (computed row only)

The draft's "Low demand / low use" sensitivity row did not reconcile to the same formulas as §3 of the audit, so it has been removed from this page. The scenario model returns a single base-case row — see §2. Re-running variants requires re-running the scenario model; no alternative sensitivity rows are published on this page.

PENDING — ZA customs duty / VAT / HS rate. HS classifications below are stated without a ZA duty rate or VAT band. Confirm via the SARS customs tariff lookup and current VAT schedules before issuing any landed-cost quote. Treat all ZA duty/VAT cells as 0.0% with the explicit "PENDING" flag.

5 · Verdict by scenario (summary)

NO-GO Base case (R9): NPV R -2,990,735.58 over 5 y at 10% discount, no payback. EV TCO/km exceeds ICE TCO/km by R 0.5420. The site cannot support 12 ports on this cost/revenue shape under the scenario model.

CONDITIONAL Higher utilisation (sensitivity, not shown): Would need a re-run of the scenario model; this page does not publish an unverified alternative row.

CONDITIONAL Captive fleet pivot: If the operator converts captive rink vehicles (coaching fleet, Zamboni-side support) to the same charge hub and can capture >40% utilisation with predictable dwell, the per-km economics may flip. Re-run the scenario model with revised asset.ev_fleet inputs before re-issuing.

6 · Mini certification & HS classification (status flagged)

ItemDetailStatus
Product classShared AC EV charging hub, 12 × Type-2 sockets—
EVSE modelSungrow AC007E-01 (7 kW, single-phase, 32 A, 230 V AC) × 12Datasheet confirmed at RFQ — https://www.sungrowpower.com/en
Load-management gatewaySungrow Smart EV-Charger Controller (OCPP 1.6J, firmware ≥ v2.1.7)Confirm firmware revision at RFQ
Output per port7 kW (single-phase, 32 A, 230 V AC)—
Connector standardIEC 62196-2 Type-2 (designation IEC 62196-2:2016)Designation only — certificate not yet issued
Protocol (claimed)OCPP 1.6J / 2.0.1NOT YET CERTIFIED — PENDING (OCA test certificate to be issued)
Ingress protection (claimed)IP54 (pedestal), IP65 (socket shroud)NOT YET CERTIFIED — PENDING
Safety standard (claimed)IEC 61851-1:2017IEC 61851-1:2017 — NOT YET CERTIFIED — PENDING (cert. no. TBC)
EMC (claimed)IEC 61851-21-2:2018NOT YET CERTIFIED — PENDING
ZA grid code (claimed)NRS 097-2-1:2017NOT YET CERTIFIED — PENDING (cert. no. TBC)
HS code (EVSE)8504.40.90PENDING — ZA duty rate TBC via SARS lookup
HS code (cable assemblies)8544.42.90PENDING
HS code (load-mgmt gateway)8517.62.90PENDING
Cross-check: WCO HS 2022 editionHeadings 8504, 8544, 8517 — see WCO HS Nomenclature 2022 editionLookup tool
Cross-check: EU TARIC (EU import)If re-export to EU — EU TARIC consultationLookup tool
Cross-check: USITC HTS (US import)If re-export to US — USITC HTS searchLookup tool

7 · RFQ anchor & downloadable spec

For a sized quote on a 12-port, 7 kW Type-2 OCPP-ready shared AC hub with a 60 kW site cap and ZA grid-code compliance, request the R9 Ice-Rink 12-Port EVSE Hub bundle via the live TradVolt RFQ form. A downloadable BOM/spec sheet for the Sungrow AC007E-01 + Sungrow Smart EV-Charger Controller bundle is available at:

Request RFQ — Ice-Rink 12-Port EVSE Hub (ZA, R9)

Download BOM/spec — R9 Ice-Rink 12-Port EVSE Hub (PDF)

HS block (for customs entry — PENDING rates):
• AC EVSE, 7 kW × 12 ports, OCPP 1.6J/2.0.1, Type-2 (Sungrow AC007E-01): 8504.40.90 — duty/VAT PENDING via SARS
• EV charging cables, Type-2-to-Type-2, 5 m, Mode 3: 8544.42.90 — PENDING
• OCPP load-management gateway (Sungrow Smart EV-Charger Controller, firmware ≥ v2.1.7): 8517.62.90 — PENDING
• Installation, switchgear, civils and commissioning: classified under the underlying equipment HS lines above; place of origin to be declared at RFQ.
• Cross-check: WCO HS 2022 edition · SARS customs · EU TARIC · USITC HTS

8 · Citations & sources

ClaimSource row
Eskom Ruraflex-style energy R 2.45/kWh and demand R 145/kVA (2024/25 schedule)Eskom tariffs and charges hub; NERSA pricing and tariffs
ZA discount-rate / inflation band contextSARB monetary policy; SARB statistics portal (for FX series)
IEC 62196-2 (Type-2 connector designation)IEC Webstore — cite full designation IEC 62196-2:2016 in text; certificate PENDING
IEC 61851-1 (safety standard)IEC 61851-1:2017 document page — cert. PENDING
IEC 61851-21-2 (EMC, charged DC separately for full-DC units; cited for completeness)IEC Webstore — cite IEC 61851-21-2:2018 in text; cert. PENDING
OCPP 1.6J / 2.0.1 protocolOpen Charge Alliance — cite protocol name + version in text; CSO test cert. PENDING
NRS 097-2-1 (ZA grid code for embedded generation / EV chargers)Cite NRS 097-2-1:2017 in text; certificate PENDING (SABS/ accredited test house)
ZA duty/VAT/HS duty ratesSARS customs tariff lookup — PENDING
HS nomenclature cross-check (8504 / 8517 / 8544)WCO HS Nomenclature 2022 edition
EU import (if re-export)EU TARIC consultation
US import (if re-export)USITC HTS search
UK Global Tariff (if re-export)UK Global Tariff lookup
EU Battery Regulation (relevant if battery-buffered variant)Regulation (EU) 2023/1542
Sungrow EVSE product family (AC007E-01)Sungrow — datasheet confirmed at RFQ
Equilibrium/EMA Eskom loadshedding context (capex risk)Eskom loadshedding hub
RFQ form (live)https://tradvolt.com/rfq/ — SCENARIO OUTPUTS for all RFQ CTAs
Downloadable BOM/spec sheethttps://tradvolt.com/assets/r9-ice-rink-12port-evse-hub-bom.pdf

Status flags carried forward: all IEC / NRS / OCPP / IP claims on this page are NOT YET CERTIFIED — PENDING until a certificate number + issuing body is produced. All ZA duty/VAT rate cells are PENDING until confirmed against the SARS customs tariff lookup.