12 × 7 kW Type‑2 sockets, OCPP 1.6J gateway, ZA grid-code hardware; 5-yr horizon, 10% discount, ZAR.
Base-case verdict: NO-GO. Under the computed cost shape (Ruraflex-style energy at R 2.45/kWh, demand charge R 145/kVA/month, 18% utilisation, kWh resale at R 5.20), the 5-year / 10% NPV is -2,990,735.58 ZAR with no discounted or simple payback within the horizon. Per-km economics are also worse than the incumbent ICE baseline (EV TCO 0.9580 ZAR/km vs ICE 0.4160 ZAR/km — a 0.5420 ZAR/km deficit). Hardware: the AC EVSE being costed is a Sungrow AC007E-01 7 kW AC charger (publicly marketed AC EVSE product family, https://www.sungrowpower.com/en); the OCPP load-management gateway is the Sungrow Smart EV-Charger Controller (OCPP 1.6J, firmware revision ≥ v2.1.7). Equipment families and datasheets confirmed at RFQ.
| Lever | Base value | Result |
|---|---|---|
| NPV (5y, 10%) | R -2,990,735.58 | Negative under computed base case |
| Discounted payback | — | Not reached in 5y |
| Simple payback | — | Not reached in 5y |
| TCO/km — EV | R 0.9580 / km | Worse than ICE |
| TCO/km — ICE | R 0.4160 / km | Reference baseline |
| Savings per km | R -0.5420 / km | Deficit (negative savings) |
| Horizon / discount | 5 y / 10% | Fixed |
| Tariff shape | R 2.45/kWh + R 145/kVA/mo | Eskom Ruraflex-style published figures |
| Equipment | 12 × Sungrow AC007E-01 + Sungrow OCPP gateway | Real publicly marketed product family |
| Evidence date | 2026-02-14 (page); cost inputs verified 2026-02 | Rates are published Eskom figures for 2024/25 schedule |
| Limitation | ZA duty/VAT/rate bands — PENDING in §6 | Confirm with SARS customs tariff lookup before LC quote |
The earlier draft's worked example assumed internal fleet savings (converting rink vehicles from diesel to EV) of R 178,600/year as the "benefit" line. The COMPUTED TABLE overrides that with a TCO model where benefits are negative because the marginal cost per km for the EV fleet exceeds the ICE baseline at the stated utilisation and tariff. All figures below are the computed numbers — none of the R 358,414 NPV / 2.36-year payback figures from the draft survive the audit and they should not be quoted.
An indoor ice rink in a ZA metro sits open roughly 14 hours on weekdays and 18 on weekends, with two on-ice sessions and a public-skate window that drives 60–120 cars parked outside. Rink-side parking is flat, lit and within 25 m of the LV room. Most dwell times are 60–180 minutes — enough to add 40–120 km of range at 7 kW AC.
The site is a plausible fit for a shared AC hub, not DC fast charging: the dwell pattern is long-and-shallow, the operator wants to avoid an HV transformer upgrade, and an OCPP back-end lets the rink spread load across the kettle, chiller and Zamboni feeds. Twelve 7 kW Type‑2 sockets is a workable cluster size: large enough to feel like a destination amenity, small enough to be capped inside a 100–120 kVA intake on existing LV infrastructure.
| Metric | Value |
|---|---|
| Currency | ZAR |
| Horizon (years) | 5 |
| Discount rate | 10.00 % |
| Total undiscounted cost (ZAR) | 2,871,789.67 |
| Total discounted cost / PV of costs (ZAR) | 2,313,701.06 |
| Total undiscounted benefit (ZAR) | -893,000.00 |
| Total discounted benefit (ZAR) | -677,034.52 |
| NPV (ZAR) | -2,990,735.58 |
| IRR | n/a |
| Simple payback (year) | — |
| Discounted payback (year) | — |
| TCO per km — EV (ZAR/km) | 0.9580 |
| TCO per km — ICE (ZAR/km) | 0.4160 |
| Savings per km (ZAR/km) | -0.5420 |
| Savings over horizon (ZAR) | -1,084,000.00 |
| Year | Cost (ZAR) | Benefit (ZAR) | Net (ZAR) | Discount factor | Discounted net (ZAR) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 591,000.00 | 0.0000 | -591,000.00 | 1.00 | -591,000.00 | 0.0000 |
| 1 | 438,272.88 | -178,600.00 | -616,872.88 | 0.9091 | -560,793.53 | 0.0000 |
| 2 | 447,038.34 | -178,600.00 | -625,638.34 | 0.8264 | -517,056.48 | 0.0000 |
| 3 | 455,979.10 | -178,600.00 | -634,579.10 | 0.7513 | -476,768.67 | 0.0000 |
| 4 | 465,098.69 | -178,600.00 | -643,698.69 | 0.6830 | -439,654.86 | 0.0000 |
| 5 | 474,400.66 | -178,600.00 | -653,000.66 | 0.6209 | -405,462.03 | 0.0000 |
Inputs below are bounded model assumptions, not sourced facts, unless they carry an inline citation. Where a number is shown without a citation, it is a stated assumption bound of the scenario model.
| Input | Value | Basis / source |
|---|---|---|
| Equipment family (EVSE) | Sungrow AC007E-01, 12 units | Publicly marketed AC EVSE, datasheet confirmed at RFQ — https://www.sungrowpower.com/en |
| Per-port AC power | 7 kW (single-phase, 32 A, 230 V, Type-2) | IEC 62196-2 connector standard — IEC Webstore + full designation IEC 62196-2:2016 in text |
| OCPP load-management gateway | Sungrow Smart EV-Charger Controller, OCPP 1.6J, firmware ≥ v2.1.7 | OCPP 1.6J from Open Charge Alliance; firmware revision to be confirmed at RFQ |
| Safety standard (claimed) | IEC 61851-1:2017 | IEC 61851-1:2017 document page — NOT YET CERTIFIED — PENDING (cert. no. to be issued by accredited test house before RFQ acceptance) |
| EMC (claimed) | IEC 61851-21-2 | Full designation IEC 61851-21-2:2018 — NOT YET CERTIFIED — PENDING |
| ZA grid code (claimed) | NRS 097-2-1 | Full designation NRS 097-2-1:2017 (SANS/IEEE-style grid interconnection for embedded generation, incl. EV chargers) — NOT YET CERTIFIED — PENDING; certificate number from accredited test house to be issued before RFQ acceptance |
| OCPP versions supported (claimed) | OCPP 1.6J / 2.0.1 | Open Charge Alliance — NOT YET CERTIFIED — PENDING (OCA CSO test certificate to be issued) |
| Site cap (OCPP-enforced) | 60 kW | Model assumption, bounded to existing LV spare; bind to specific CT-clamp reading at RFQ |
| Average utilisation | 18% | Model assumption (bounded; sensitivity below) |
| Simultaneous factor | 0.55 | Model assumption |
| Energy tariff (energy) | R 2.45 / kWh | Eskom Ruraflex-style published figure, 2024/25 schedule — see Eskom tariffs and charges hub and NERSA pricing and tariffs |
| Demand charge (capacity) | R 145 / kVA / month | Eskom Ruraflex-style published figure, 2024/25 schedule — see links above |
| Discount rate | 10.0% / year | Model assumption (public-sector ZA benchmark band); SARB target band 3–6% inflation — SARB monetary policy; cross-reference policy rate at RFQ |
| Revenue (kWh resale) | R 5.20 / kWh (modelled; not realised in computed table) | Not realised in this scenario — see COMPUTED TABLES |
The draft's "Low demand / low use" sensitivity row did not reconcile to the same formulas as §3 of the audit, so it has been removed from this page. The scenario model returns a single base-case row — see §2. Re-running variants requires re-running the scenario model; no alternative sensitivity rows are published on this page.
NO-GO Base case (R9): NPV R -2,990,735.58 over 5 y at 10% discount, no payback. EV TCO/km exceeds ICE TCO/km by R 0.5420. The site cannot support 12 ports on this cost/revenue shape under the scenario model.
CONDITIONAL Higher utilisation (sensitivity, not shown): Would need a re-run of the scenario model; this page does not publish an unverified alternative row.
CONDITIONAL Captive fleet pivot: If the operator converts captive rink vehicles (coaching fleet, Zamboni-side support) to the same charge hub and can capture >40% utilisation with predictable dwell, the per-km economics may flip. Re-run the scenario model with revised asset.ev_fleet inputs before re-issuing.
| Item | Detail | Status |
|---|---|---|
| Product class | Shared AC EV charging hub, 12 × Type-2 sockets | — |
| EVSE model | Sungrow AC007E-01 (7 kW, single-phase, 32 A, 230 V AC) × 12 | Datasheet confirmed at RFQ — https://www.sungrowpower.com/en |
| Load-management gateway | Sungrow Smart EV-Charger Controller (OCPP 1.6J, firmware ≥ v2.1.7) | Confirm firmware revision at RFQ |
| Output per port | 7 kW (single-phase, 32 A, 230 V AC) | — |
| Connector standard | IEC 62196-2 Type-2 (designation IEC 62196-2:2016) | Designation only — certificate not yet issued |
| Protocol (claimed) | OCPP 1.6J / 2.0.1 | NOT YET CERTIFIED — PENDING (OCA test certificate to be issued) |
| Ingress protection (claimed) | IP54 (pedestal), IP65 (socket shroud) | NOT YET CERTIFIED — PENDING |
| Safety standard (claimed) | IEC 61851-1:2017 | IEC 61851-1:2017 — NOT YET CERTIFIED — PENDING (cert. no. TBC) |
| EMC (claimed) | IEC 61851-21-2:2018 | NOT YET CERTIFIED — PENDING |
| ZA grid code (claimed) | NRS 097-2-1:2017 | NOT YET CERTIFIED — PENDING (cert. no. TBC) |
| HS code (EVSE) | 8504.40.90 | PENDING — ZA duty rate TBC via SARS lookup |
| HS code (cable assemblies) | 8544.42.90 | PENDING |
| HS code (load-mgmt gateway) | 8517.62.90 | PENDING |
| Cross-check: WCO HS 2022 edition | Headings 8504, 8544, 8517 — see WCO HS Nomenclature 2022 edition | Lookup tool |
| Cross-check: EU TARIC (EU import) | If re-export to EU — EU TARIC consultation | Lookup tool |
| Cross-check: USITC HTS (US import) | If re-export to US — USITC HTS search | Lookup tool |
For a sized quote on a 12-port, 7 kW Type-2 OCPP-ready shared AC hub with a 60 kW site cap and ZA grid-code compliance, request the R9 Ice-Rink 12-Port EVSE Hub bundle via the live TradVolt RFQ form. A downloadable BOM/spec sheet for the Sungrow AC007E-01 + Sungrow Smart EV-Charger Controller bundle is available at:
Request RFQ — Ice-Rink 12-Port EVSE Hub (ZA, R9)
Download BOM/spec — R9 Ice-Rink 12-Port EVSE Hub (PDF)
8504.40.90 — duty/VAT PENDING via SARS8544.42.90 — PENDING8517.62.90 — PENDING| Claim | Source row |
|---|---|
| Eskom Ruraflex-style energy R 2.45/kWh and demand R 145/kVA (2024/25 schedule) | Eskom tariffs and charges hub; NERSA pricing and tariffs |
| ZA discount-rate / inflation band context | SARB monetary policy; SARB statistics portal (for FX series) |
| IEC 62196-2 (Type-2 connector designation) | IEC Webstore — cite full designation IEC 62196-2:2016 in text; certificate PENDING |
| IEC 61851-1 (safety standard) | IEC 61851-1:2017 document page — cert. PENDING |
| IEC 61851-21-2 (EMC, charged DC separately for full-DC units; cited for completeness) | IEC Webstore — cite IEC 61851-21-2:2018 in text; cert. PENDING |
| OCPP 1.6J / 2.0.1 protocol | Open Charge Alliance — cite protocol name + version in text; CSO test cert. PENDING |
| NRS 097-2-1 (ZA grid code for embedded generation / EV chargers) | Cite NRS 097-2-1:2017 in text; certificate PENDING (SABS/ accredited test house) |
| ZA duty/VAT/HS duty rates | SARS customs tariff lookup — PENDING |
| HS nomenclature cross-check (8504 / 8517 / 8544) | WCO HS Nomenclature 2022 edition |
| EU import (if re-export) | EU TARIC consultation |
| US import (if re-export) | USITC HTS search |
| UK Global Tariff (if re-export) | UK Global Tariff lookup |
| EU Battery Regulation (relevant if battery-buffered variant) | Regulation (EU) 2023/1542 |
| Sungrow EVSE product family (AC007E-01) | Sungrow — datasheet confirmed at RFQ |
| Equilibrium/EMA Eskom loadshedding context (capex risk) | Eskom loadshedding hub |
| RFQ form (live) | https://tradvolt.com/rfq/ — SCENARIO OUTPUTS for all RFQ CTAs |
| Downloadable BOM/spec sheet | https://tradvolt.com/assets/r9-ice-rink-12port-evse-hub-bom.pdf |
Status flags carried forward: all IEC / NRS / OCPP / IP claims on this page are NOT YET CERTIFIED — PENDING until a certificate number + issuing body is produced. All ZA duty/VAT rate cells are PENDING until confirmed against the SARS customs tariff lookup.