Tradvolt  |  Vertical: EVSE  |  Use-case: Coach Terminal, 600 kW DC  |  Lane: China → Egypt

Import a 600 kW DC EVSE from China to Egypt — Coach Terminal Use-Case (TCO & Landed Cost)

Verdict (first 100 words). Reference equipment: a 600 kW DC EVSE (e.g., Star Charge / TELD liquid-cooled dispenser family — exact SKU confirmed at RFQ; proof required: OEM datasheet). Location: Egypt (coach terminal, Alexandria-area lane). Horizon: 25 years (bounded assumption). Discount rate: 8.00 %/yr (bounded assumption). Evidence date: 2026-09-22. Limitation: HS/Egyptian duty rate is PENDING — must be looked up at the Egyptian Customs Authority (Misaq) Nafe' portal before RFQ. scenario TCO result: NPV ≈ 419,363 USD (USD); discounted payback ≈ 2.84 years; simple payback ≈ 2.45 years; TCO per km EV ≈ 0.083 USD/km vs ICE ≈ 0.256 USD/km; savings per km ≈ 0.173 USD/km. This page is a reference use-case and is not a quote.

Decision summary — at a glance
ItemValueSource / status
Equipment (family)600 kW DC EVSE, liquid-cooled (OEM family — exact SKU at RFQ)Bounded assumption (model input)
LocationEgypt, coach terminalBounded assumption (model input)
Horizon25 yearsBounded assumption (model input)
Discount rate8.00 %/yrBounded assumption (model input)
NPV (USD)419,362.71scenario TCO model (table below)
IRR0.4069 (40.69 %)scenario TCO model (table below)
Simple payback (year)2.4471scenario TCO model (table below)
Discounted payback (year)2.8371scenario TCO model (table below)
TCO per km — EV (USD/km)0.0828scenario TCO model (table below)
TCO per km — ICE (USD/km)0.2560scenario TCO model (table below)
Savings per km (USD/km)0.1732scenario TCO model (table below)
Savings over horizon (USD, undiscounted)1,732,000.00scenario TCO model (table below)
Egyptian HS / duty line8504.40 — PENDING — lookup at Egyptian Customs Authority (Misaq) Nafe' portalPENDING — buyer's HS lookup duty

Equipment family (exact model pending RFQ)

Reference family: a 600 kW DC EVSE, liquid-cooled dispenser with separate power cabinet (split architecture), charging protocol OCPP 2.0.1 over the Open Charge Alliance stack. Public examples of comparable Chinese OEM SKUs that exist in the 360–600 kW DC class include (exact model and SKU are buyer-specific and confirmed at RFQ; datasheets are JS-rendered on OEM product pages):

The exact equipment model and OEM manual revision (e.g., torque limits, SOC operating window, DC output voltage window 200–1000 V DC, storage SOC 20–80 %) are confirmed against the OEM's datasheet at /rfq/. Specific certificate numbers and issuing bodies are OEM-specific.

scenario TCO summary (USD, 25 years, 8 % discount)

TCO summary
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate8.00 %
Total undiscounted cost (USD)320,181.80
Total discounted cost / PV of costs (USD)204,044.21
Total undiscounted benefit (USD)1,460,000.00
Total discounted benefit (USD)623,406.93
NPV (USD)419,362.71
IRR0.4069
Simple payback (year)2.45
Discounted payback (year)2.84
TCO per km — EV (USD/km)0.0828
TCO per km — ICE (USD/km)0.2560
Savings per km (USD/km)0.1732
Savings over horizon (USD)1,732,000.00

Year-by-year cash flow (scenario TCO model, verbatim)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
0128,000.000.0000-128,000.001.00-128,000.000.0000
16,000.0058,400.0052,400.000.925948,518.520.0000
26,120.0058,400.0052,280.000.857344,821.670.0000
36,242.4058,400.0052,157.600.793841,404.380.0000
46,367.2558,400.0052,032.750.735038,245.630.0000
56,494.5958,400.0051,905.410.680635,325.950.0000
66,624.4858,400.0051,775.520.630232,627.360.0000
76,756.9758,400.0051,643.030.583530,133.210.0000
86,892.1158,400.0051,507.890.540327,828.110.0000
97,029.9658,400.0051,370.040.500225,697.810.0000
107,170.5658,400.0051,229.440.463223,729.150.0000
117,313.9758,400.0051,086.030.428921,909.920.0000
127,460.2558,400.0050,939.750.397120,228.880.0000
137,609.4558,400.0050,790.550.367718,675.580.0000
147,761.6458,400.0050,638.360.340517,240.390.0000
157,916.8758,400.0050,483.130.315215,914.390.0000
168,075.2158,400.0050,324.790.291914,689.330.0000
178,236.7158,400.0050,163.290.270313,557.580.0000
188,401.4558,400.0049,998.550.250212,512.090.0000
198,569.4858,400.0049,830.520.231711,546.330.0000
208,740.8758,400.0049,659.130.214510,654.280.0000
218,915.6858,400.0049,484.320.19879,830.340.0000
229,094.0058,400.0049,306.000.18399,069.370.0000
239,275.8858,400.0049,124.120.17038,366.590.0000
249,461.4058,400.0048,938.600.15777,717.590.0000
259,650.6258,400.0048,749.380.14607,118.280.0000

All figures above are taken directly from the scenario TCO model output. No methodology or derivations are included on this page. Inputs that the model requires but the underlying scenario did not supply are listed as bounded assumptions below.

CapEx — Indicative Build-Up (EXW China → Landed Egypt)

LineDescriptionUnitQtyUnit basisNotes
C-1EVSE unit, 600 kW DC, liquid-cooled (OEM SKU confirmed at RFQ)pcs1OEM EXW ChinaBuyer input — unit price per OEM datasheet
C-2Power cabinet / dispenser (split architecture)pcs1OEM EXW ChinaBuyer input — confirm with OEM datasheet
C-3DC cable set + liquid-cooling hosesset1OEM EXW ChinaBuyer input — length per terminal layout
C-4Spare parts kit (filters, fuses, contactor)set1OEM EXW ChinaBuyer input — per OEM datasheet
C-5Site preparation (foundation, ducting, MV connection)lot1Buyer-sited, EgyptBuyer input — civil scope, not OEM scope
C-6MV transformer + switchgear (if 11/22 kV step-down)lot1Buyer-sited, EgyptBuyer input — utility interface
C-7OCPP back-office / network commissioninglot1OEM or 3rd partyBuyer input — one-off activation
C-8Sea freight + insurance (Shanghai/Alexandria), Incoterms 2020 CIP/CIFshipment1Incoterm per RFQBuyer input — incoterm per ICC Incoterms 2020
C-9Egyptian customs duty, VAT & fees——PENDING — see Duty blockPENDING — lookup at Egyptian Customs Authority (Misaq) Nafe' portal
C-10Last-mile delivery + positioning + commissioninglot1OEM or local partnerBuyer input — site-dependent

CapEx line items are buyer inputs to the scenario TCO model. Unit costs and engineering scope must be confirmed against the OEM datasheet and the buyer's site survey before any commercial commitment.

Request a quote — replies in 48h

Request Quote — replies in 48h (use the form on the RFQ page; the form at /rfq/ is the canonical intake).

OpEx — Annual Recurring Cost Drivers (buyer inputs to the model)

LineDriverBasisFrequencyNotes
O-1Electricity consumption (load-dependent)kWh × USD/kWhMonthlyBuyer input — tariff to confirm with local DSO
O-2Demand charge / capacity feeUSD/kW/monthMonthlyBuyer input — tariff to confirm with local DSO
O-3Preventive maintenance kitOEM scheduleAnnualBuyer input — per OEM datasheet
O-4OCPP back-office subscriptionPer chargerAnnualBuyer input — if SaaS model used (Open Charge Alliance protocol stack)
O-5Connectivity (SIM / fibre)Monthly feeMonthlyBuyer input — operator-selected ISP
O-6Insurance & civil upkeepBuyer policyAnnualBuyer input — buyer-discretion
O-7Spare-parts reserveOEM scheduleAnnualBuyer input — per OEM datasheet

Sensitivity (scenario TCO model; uniform treatment, OM subtracted)

ScenarioAnnual throughput (kWh)Energy cost (USD/kWh)Revenue (USD/kWh)Annual O&M ex-energy (USD)Net cash (USD/yr)Comment
Base1,200,0000.080.306,000258,000scenario TCO model output
Low utilisation700,0000.080.306,000154,000scenario TCO model output
High energy cost1,200,0000.110.306,000228,000scenario TCO model output
Lower driver tariff1,200,0000.080.246,000192,000scenario TCO model output

Sensitivity rows are scenario model outputs. OM is subtracted consistently across all scenarios (uniform treatment). Figures are illustrative only and depend on the OEM final commercial proposal, the verified Egyptian duty/VAT stack, energy tariffs, dwell time and throughput at the coach terminal. Not a quote.

Bounded assumptions (model inputs the underlying scenario did not state)

AssumptionValueNote
residual_value.amount0.00 USDBounded assumption (zero residual at year 25)
residual_value.year25Bounded assumption (aligned with horizon)
asset.ev_fleet.vehicles1Bounded assumption (single dispenser)
asset.ev_fleet.km_per_year400,000Bounded assumption (bus-route proxy)
asset.ev_fleet.kwh_per_km1.20Bounded assumption (electric coach proxy)
asset.ev_fleet.diesel_l_per_km0.35Bounded assumption (intercity coach ICE proxy)
asset.ev_fleet.diesel_per_l0.90 USD/LBounded assumption
asset.ev_fleet.maint_ev_per_km0.04 USD/kmBounded assumption
asset.ev_fleet.maint_ice_per_km0.10 USD/kmBounded assumption
asset.ev_fleet.ice_capex_per_vehicle0.00 USDBounded assumption (no ICE CapEx counted in this scope)

Compliance & Certifications to Request from the OEM

Specific certificate numbers and issuing bodies are OEM-specific and must be verified per shipment. Tradvolt does not represent any third-party certification without documentary proof from the issuer.

Duty / HS National Line — Egypt (PENDING — lookup)

HS national lineProgramAs-ofSoT
8504.40 — Static converters (commonly used for DC EVSE) — PENDING — lookup at Egyptian Customs Authority (Misaq) Egyptian Customs Tariff (Misaq / Nafe' portal) 2026-09-22 PENDING — lookup

Every duty and VAT rate on this page is marked PENDING — lookup. The Egyptian Customs Authority (Misaq) tariff, applied VAT rate, any applicable free-zone or FTA preferential rate, and inspection fees must be confirmed at the official customs portal before any shipment. Verify directly:

HS classification is the importer's responsibility. Sub-classification, exemptions and FTA preferential treatment are shipment-specific and can only be confirmed at the moment of clearance with the original commercial invoice, packing list and BoL.

Request Quote — replies in 48h

Submit an RFQ — Tradvolt replies in 48h (English) with a line-item offer and the available certificates.

Frequently Asked Questions

1. Which HS code is typically used for 600 kW DC EVSE imports into Egypt?

DC EVSE is commonly classified under HS 8504.40 (static converters). The exact Egyptian national tariff line, rate and any exemptions MUST be verified against the Egyptian Customs Authority (Misaq) Nafe' portal at the time of shipment. See the Duty-Stack block above.

2. What certificates should a 600 kW DC EVSE carry for Egypt?

Typical requirements are an IEC-based type test (e.g., IEC 61851-1:2017 for EV conductive charging), a CB scheme certificate under the IECEE scheme, CE marking under EU conformity legislation (Reg. 765/2008 plus the relevant directives), and any local acceptance required by the buyer/utility. Always request the certificate number and issuing body from the OEM.

3. Is the payback figure on this page a quote?

No. The scenario TCO tables on this page are illustrative scenarios computed by Tradvolt's scenario TCO model. They depend on the OEM final commercial proposal, the verified Egyptian duty/VAT stack, energy tariffs, dwell time and throughput at the coach terminal. Not a quote.

4. What incoterm should I use when importing DC EVSE from China to Egypt?

Common incoterms for this lane are CIP Alexandria or FCA Chinese port under Incoterms 2020. CIF is widely used by first-time buyers but transfers less risk control. The choice changes who pays freight, insurance and Egyptian clearance — specify incoterm in your RFQ.

5. How fast does Tradvolt reply to an RFQ?

Replies are sent within 48 business hours, in English, with a line-item offer and the available certificates.

6. What site preparation is outside the OEM scope?

Civil works (foundation, ducting), the MV/LV transformer and switchgear, utility interconnection, and the back-office/OCPP integration are typically buyer or integrator scope. Confirm the split-of-scope in the OEM proposal.