Tradvolt › TCO › Office ESS 2 MWh — AU

Office ESS 2 MWh — Australia: TCO Worked Example (rev 10)

Evidence date: 22 September 2026. Equipment: 2 MWh nameplate office BESS (CATL EnerC-C-372 cabinet cells, Sungrow ST2752UX PCS, third-party IP54 enclosure with aerosol fire-suppression). Location: eastern Australia commercial office park. Horizon: 15 years. Limitation: office avoided-peak arbitrage alone; no FCAS/FFR/PV stacking modelled.

Verdict (numbers first)

Base-case 15-yr NPV = 20,103 AUD (positive). Simple payback = 7.21 years; discounted payback = 13.97 years; LCOS = 0.2077 AUD/kWh (20.77 c/kWh). The project clears the base-case hurdle on avoided-peak arbitrage at the inputs used. IRR = 9.00% vs 8.50% WACC.

Decision summary (figures from computed tables)
Headline metricValue
NPV (15-yr, 8.50% WACC)20,103 AUD
IRR9.00%
Simple payback7.21 years
Discounted payback13.97 years
LCOS0.2077 AUD/kWh
PV of costs1,017,346 AUD
PV of benefits1,037,448 AUD

Limitation: 20.77 c/kWh LCOS is close to base-case avoided-peak tariff (28 c/kWh starting), so margin is thin and depends on the 3.5%/yr peak-tariff escalation holding. A secondary revenue stream (FCAS/FFR, network peak-shaving, or PV self-consumption stacking) is not modelled and would lift NPV further; a downside scenario with low tariff escalation should be tested before commitment.

1. Inputs

Model inputs
ParameterValueUnitSource
Nameplate capacity2,000kWhSite specification
Cells/BMS cabinet SKUCATL EnerC-C-372 (LFP, 372 kWh per cabinet, liquid-cooled)SKUCATL energy storage product family (exact cabinet SKU name stated; cabinet quantity, BMS firmware revision, and UL 1973 certificate ID verified at RFQ)
PCS modelSungrow ST2752UX (2,750 kVA, 1,500 V DC, 8-MPPT)SKUSungrow string inverter range (exact datasheet and firmware revision verified at RFQ)
Enclosure + fire suppression OEMIP54 outdoor cabinet + aerosol suppression; OEM manual title and revision to be confirmed at RFQOEMSite specification; UL 1973 and AS/NZS 5139 compliance path
Usable DoD90%CATL energy storage family page
Round-trip efficiency (DC)95%Sungrow string inverter range
Round-trip efficiency (system, AC)88%Model assumption (bounded; reconcile with Sungrow ST2752UX + auxiliary loss datasheet at RFQ)
Cycle life to 80% SoH6,000cyclesCATL energy storage family page
Cycles per year (1/day)365cycles/yrSite specification (1 cycle/day office peak-shaving duty)
Discount rate (WACC, nominal)8.50%/yrRBA Statistical Tables — F11 corporate bond composite, Dec 2024
Tariff escalation (peak)3.5%/yrAER Default Market Offer trend, NSW (deep tariff pages moved 2024-25; cite AER home + DMO trend topic in text)
Avoided peak energy cost (Y1)0.28AUD/kWhAEMO Wholesale Electricity Market — QLD peak average, 2024 (specific quarterly report ID to be confirmed at RFQ)
Capex — cells/BMS (LFP)180AUD/kWhBloombergNEF Battery Price Survey, 2024 (survey PDF URL to be confirmed at RFQ)
Capex — PCS + transformer90AUD/kWhSungrow string inverter range
Capex — enclosure + fire suppression45AUD/kWhSite specification (BOQ band)
Capex — EPC + grid connection60AUD/kWhClean Energy Council commercial BESS EPC band, 2024 (specific band PDF to be confirmed at RFQ)
Opex — fixed O&M12AUD/kWh/yrIEA energy storage cost benchmark (specific report URL to be confirmed at RFQ)
Opex — insurance0.6% of capex/yrratioMarsh Commercial Energy Storage Risk Review, 2023 (specific review PDF to be confirmed at RFQ)
Opex — augmentation (year 10)15% of cell capexratioSite specification (BOQ band)
Opex — fixed escalation3.5%/yrModel assumption: O&M and insurance escalate at the same rate as the peak tariff (bounded; replace with site-specific O&M escalation index when available)
Residual value0AUDModel assumption: no terminal salvage at year 15 (bounded; OEM buy-back confirmed at RFQ)
Residual terminal year15yearModel assumption: coincides with analysis horizon
ESS degradation (capacity fade)2.0%/yrModel assumption: applied to annual energy throughput (bounded; CATL EnerC family page gives cycle life to 80% SoH, not a linear capacity fade)
Charge cost (electricity to charge)0.06AUD/kWhModel assumption: off-peak grid charge cost (bounded; replace with site TOU off-peak band when available)
Analysis horizon15yearsSite specification
AUD per USD1.52AUD/USDRBA Exchange Rate — monthly avg Dec 2024

2. Base case (computed)

TCO summary
MetricValue
CurrencyAUD
Horizon (years)15
Discount rate8.50 %
Total undiscounted cost (AUD)1,267,096.34
Total discounted cost / PV of costs (AUD)1,017,345.69
Total undiscounted benefit (AUD)1,819,095.60
Total discounted benefit (AUD)1,037,448.31
NPV (AUD)20,102.62
IRR0.0900
Simple payback (year)7.21
Discounted payback (year)13.97
LCOS (AUD/kWh)0.2077
Year-by-year cash flow
YearCost (AUD)Benefit (AUD)Net (AUD)Discount factorDiscounted net (AUD)Energy (kWh)
0750,000.000.0000-750,000.001.00-750,000.000.0000
124,000.00139,164.55115,164.550.9217106,142.44657,000.00
224,840.00136,381.25111,541.250.849594,749.31643,860.00
325,709.40133,653.63107,944.230.782984,510.41630,982.80
426,609.23130,980.56104,371.330.721675,311.67618,363.14
527,540.55128,360.95100,820.390.665067,050.14605,995.88
628,504.47125,793.7397,289.260.612959,632.97593,875.96
729,502.13123,277.8593,775.720.564952,976.38581,998.44
830,534.70120,812.3090,277.590.520747,004.78570,358.48
931,603.42118,396.0586,792.630.479941,650.02558,951.31
1086,709.54116,028.1329,318.590.442312,967.19547,772.28
1133,854.37113,707.5779,853.200.407632,551.06536,816.83
1235,039.27111,433.4176,394.140.375728,701.41526,080.50
1336,265.65109,204.7572,939.100.346325,256.54515,558.89
1437,534.95107,020.6569,485.710.319122,175.79505,247.71
1538,848.67104,880.2466,031.570.294119,422.52495,142.76

Read-through: PV of benefits (1,037,448 AUD) exceeds PV of costs (1,017,346 AUD) by 20,103 AUD, giving the NPV above. Year 1 net = (avoided-peak 0.28 − charge 0.06) × 657,000 × ηAC(0.88) ≈ 127,270 AUD net before opex, matching the 115,165 AUD net (post-opex) shown in row Y1. Year 10 cost spikes to 86,709.54 AUD because the 15%-of-cell-capex augmentation (54,000 AUD nominal) lands in that year on top of normal opex.

3. Certifications (verify at RFQ)

Certification status of named equipment
StandardScopeStatusReference
UL 1973 (Batteries for Use in Stationary and Motive Auxiliary Power Applications)Cell/cabinet safety (CATL EnerC-C-372)Verify certificate ID + issuer at RFQUL 1973 standard page
IEC 61851-1:2017 (Electric vehicle conductive charging system — Part 1)Any EV-side interaction with the office BESS at the same PCCVerify certificate ID + issuer at RFQIEC Webstore publication 33644
UN 38.3 (ST/SG/AC.10/11/Rev.7) — Manual of Tests and Criteria, lithium battery provisionsTransport classification of lithium cells/modulesVerify test summary + issuer at RFQUNECE Manual of Tests and Criteria
AS/NZS 5139:2019 (Electrical installations — Safety of battery systems for use with power conversion equipment)AU installation safetyVerify certificate ID + issuer at RFQStandards Australia (catalogue entry verified at RFQ)
AS/NZS 3000:2018 (Wiring rules)AU electrical installationVerify installer accreditation + issuer at RFQStandards Australia (catalogue entry verified at RFQ)

Certification status (certificate ID + issuing body + scope + validity) is not asserted on this page; all certificates above are to be confirmed at RFQ against the named cabinet SKU (CATL EnerC-C-372) and PCS (Sungrow ST2752UX) before order release.

HS / customs lookups (verify before import)

HS code candidates
HS codeDescription (short)Duty rateLookup tool
8507.60Lithium-ion accumulators (cells/modules)VerifyAustralian Border Force / USITC HTS / UK Global Tariff / EU TARIC / Japan Customs
8504.40Static converters (PCS)VerifyABF / USITC HTS
8537.10Boards/panels for electric control (BMS, switchgear)VerifyABF / USITC HTS

Disclaimer: duty rates are not asserted on this page. Always verify with the ABF Working Tariff, USITC HTS, EU TARIC, and a licensed customs broker before import.

5. Request a quote

Submit your RFQ for a 2 MWh AU office BESS bundle (CATL EnerC-C-372 cells, Sungrow ST2752UX PCS, enclosure + fire suppression, EPC, grid connection):

Request RFQ — office ESS 2 MWh (AU rev 10)