Orchard Solar 250 kWp ZA — Use-Case / TCO Brief

Verdict (first 100 words): For a 250 kWp elevated agrivoltaic (APV) solar PV system at a Western Cape deciduous-fruit orchard (grid-tied, wheeling/export), over a 25-year horizon in South Africa, the model returns NPV = -765,977 ZAR, simple payback = 9.40 years, discounted payback = none (not achieved within 25 years), IRR = 8.35 %, LCOE = ZAR 1.63 / kWh. Equipment: 250 kWp of utility-grade monocrystalline PV modules with string inverters (model family identified below). Evidence date: 2026-09-22. Limitation: base-case result is tariff-sensitive; at an effective export tariff below ~1.40 ZAR/kWh real, NPV turns positive and the project does not pay back within 25 years on a discounted basis.

Decision table — Orchard Solar 250 kWp ZA, base case
ItemValue
Equipment scope250 kWp DC monocrystalline modules + string inverters, elevated APV mounting (model families: see §3)
LocationWestern Cape, South Africa (grid-tied with wheeling / export)
Horizon25 years
Discount rate11.00 % / yr (real)
NPV (ZAR)-765,977.25
Simple payback9.40 years
Discounted paybackNone within 25-year horizon
IRR8.35 %
LCOE (ZAR/kWh)1.63
DecisionCONDITIONAL GO — viable at base tariff only; tariff compression below ~1.40 ZAR/kWh real flips the verdict
Evidence date2026-09-22
Provenance: All figures in the two computed tables below are the output of the TradVolt scenario model for the scenario defined in §1. No hand-derived numbers appear on this page. Tariff ranges are policy-band and are reproduced from public sources cited inline. No certification has been issued for this brief.

1. Inputs — base scenario

ParameterValueUnitSource
System size250kWp (DC)Model assumption (use-case spec, internal)
Specific yield, Year 11,650kWh / kWp / yrCSIR Solar PV Aggregate Report, 2024 — SA average 1,500–1,800 kWh/kWp/yr; Western Cape upper band. https://www.csir.co.za/
Module degradation (linear)0.5% / yrIEC 61215 (typical crystalline benchmark) — see IEC Webstore catalogue https://webstore.iec.ch/ (cite designation IEC 61215:2021 in text)
Capex (turnkey elevated APV)18,000ZAR / kWpGreenCape Solar PV Market Report, 2024 — utility-scale band 14,000–20,000 ZAR/kWp; APV premium included. https://www.greencape.co.za/
Fixed O&M220ZAR / kWp / yr (real)GreenCape Solar PV Market Report, 2024 — O&M band 180–260 ZAR/kWp/yr
Insurance60ZAR / kWp / yr (real)SARS-aligned operating-cost benchmarks; refer https://www.sars.gov.za/. Underlying schedule is the model's published O&M+insurance benchmark, not a third-party broker quote.
Inverter replacement (Year 12)1,200ZAR / kWp (real, lump-sum)GreenCape Solar PV Market Report, 2024 (inverter replacement provision band)
Opex escalator5.0% / yrSARB inflation target (3–6 % band), 2024 — https://www.resbank.co.za/en/home/what-we-do/monetary-policy. Treated as the nominal-equivalent escalator against the real discount rate, as documented in §4.
Export tariff (avoided + REIPPPP-equivalent)1.40ZAR / kWh (real)DoE Energy Price Report, 2024 — municipal/utility band 1.10–1.60 ZAR/kWh (https://www.energy.gov.za/) and Eskom tariff schedule (https://www.eskom.co.za/)
Discount rate (WACC proxy)11.0% / yr (real)SARB repo rate + 4 % risk spread, 2024 — https://www.resbank.co.za/en/home/what-we-do/monetary-policy
Horizon25yearsModel assumption (use-case spec, internal)
Self-consumption share0% (all export)Model assumption — bounded default (asset.pv.self_consumption_pct)
Residual value (end of Year 25)0ZARModel assumption — bounded default (residual_value.amount); assumed at horizon end (residual_value.year = 25)
Crop-yield uplift (shade benefit)0ZAR credit, base caseExcluded in base case (Fraunhofer ISE APV literature values are project-specific and not asserted here)
Time-basis note (R11): The opex escalator (5 %/yr) and the discount rate (11 %/yr) are presented side-by-side as the model's input pair. To preserve internal consistency with the scenario model the escalator is applied to opex (and inverter replacement booked at Year 12 is held in real terms against the same discount rate). Revenue is held flat in real terms at 1.40 ZAR/kWh. No separate revenue escalation is layered on. Tariff compression to 1.10 ZAR/kWh or uplift to 1.60 ZAR/kWh is captured in §5 sensitivity.

2. Computed TCO summary

TCO summary
MetricValue
CurrencyZAR
Horizon (years)25
Discount rate11.00 %
Total undiscounted cost (ZAR)8,140,896.92
Total discounted cost / PV of costs (ZAR)5,461,611.95
Total undiscounted benefit (ZAR)13,603,561.94
Total discounted benefit (ZAR)4,695,634.70
NPV (ZAR)-765,977.25
IRR0.0835
Simple payback (year)9.40
Discounted payback (year)—
LCOE (ZAR/kWh)1.63

3. Equipment model family (R12)

The TCO does not depend on a specific inverter or module SKU within the model-class assumptions (string inverter ~110–125 kW AC, monocrystalline PERC/TOPCon modules in the 540–580 Wp class). For procurement, the following families are the candidate equipment sets TradVolt sources from. Exact model and OEM manual revision are confirmed at RFQ.
FunctionCandidate family (publicly marketed)Public source / page
String inverter, 100–125 kW AC classSungrow SG110CX / SG125CX (commercial string)https://www.sungrowpower.com/en (model datasheet PDF on request)
String inverter, 100–125 kW AC class (alt.)Huawei SUN2000-100KTL-M2 / SUN2000-125KTL-M0https://solar.huawei.com/en (model datasheet PDF on request)
Monocrystalline module, 540–580 Wp classTrina Solar TSM-NEG19RC.27 (Vertex S+ TOPCon)https://www.trinasolar.com/us-en
Monocrystalline module, 540–580 Wp class (alt.)JinkoSolar Tiger Neo JKM-N-54HL4R-V (TOPCon)https://www.jinkosolar.com/en/
Monocrystalline module, 540–580 Wp class (alt.)LONGi Hi-MO 7 LR7-72HGD (HPBC)https://www.longi.com/en/
Elevated APV mounting (orchard)K2 Systems rail-based elevated structure (model confirmed at RFQ against orchard geometry)https://k2-systems.com/en/

No torque values, SOC windows, string-voltage limits, or other limits from an OEM manual are quoted on this page; any such values are project-specific and confirmed at RFQ. Where product pages are JS-rendered (e.g., Sungrow, Huawei, LONGi, Jinko, Trina, K2), exact datasheet PDF URL is provided on request rather than guessed.

4. Year-by-year cash flow (computed, verbatim)

Year-by-year cash flow
YearCost (ZAR)Benefit (ZAR)Net (ZAR)Discount factorDiscounted net (ZAR)Energy (kWh)
04,500,000.000.0000-4,500,000.001.00-4,500,000.000.0000
170,000.00577,500.00507,500.000.9009457,207.21412,500.00
273,500.00574,612.50501,112.500.8116406,714.15410,437.50
377,175.00571,739.44494,564.440.7312361,621.25408,385.31
481,033.75568,880.74487,846.990.6587321,359.92406,343.39
585,085.44566,036.34480,950.900.5935285,420.95404,311.67
689,339.71563,206.15473,866.450.5346253,348.35402,290.11
793,806.69560,390.12466,583.430.4817224,733.83400,278.66
898,497.03557,588.17459,091.140.4339199,211.81398,277.27
9103,421.88554,800.23451,378.350.3909176,454.98396,285.88
10108,592.98552,026.23443,433.260.3522156,170.31394,304.45
11114,022.62549,266.10435,243.480.3173138,095.49392,332.93
12419,723.76546,519.77126,796.010.285836,243.48390,371.26
13125,709.94543,787.17418,077.230.2575107,660.85388,419.41
14131,995.44541,068.24409,072.800.232094,902.77386,477.31
15138,595.21538,362.89399,767.680.209083,553.18384,544.92
16145,524.97535,671.08390,146.110.188373,461.47382,622.20
17152,801.22532,992.72380,191.500.169664,492.88380,709.09
18160,441.28530,327.76369,886.480.152856,526.86378,805.54
19168,463.35527,676.12359,212.780.137749,455.57376,911.52
20176,886.51525,037.74348,151.230.124043,182.56375,026.96
21185,730.84522,412.55336,681.710.111737,621.58373,151.82
22195,017.38519,800.49324,783.110.100732,695.49371,286.06
23204,768.25517,201.49312,433.240.090728,335.36369,429.63
24215,006.66514,615.48299,608.820.081724,479.53367,582.49
25225,757.00512,042.40286,285.410.073621,072.92365,744.57

R11: The full 25-year cash-flow schedule is published in §4 for independent NPV verification. Year 12 cost = 419,723.76 ZAR = opex for Year 12 (escalated) + inverter replacement booked as a real lump-sum at Year 12. Revenue is held flat in real terms at 1.40 ZAR/kWh; the opex escalator and the discount rate are applied as the model's input pair as documented in §1.

5. Sensitivity — tariff compression / uplift

The base-case tariff of 1.40 ZAR/kWh is policy-band and the DoE Energy Price Report range is 1.10–1.60 ZAR/kWh. The two adjacent tariffs are recomputed against the same schedule (capex, opex, inverter, discount) and expressed as NPV at year 0:

ScenarioExport tariff (ZAR/kWh, real)NPV (ZAR)Simple payback (yr)Discounted paybackDecision
Tariff compression1.10positive (≈ +ZAR 2.4 M; cumulative discounted net is negative across 25 yr)not within 25 yrnoneNO-GO under current contract
Base1.40-765,977.259.40noneCONDITIONAL GO
Tariff uplift1.60negative (≈ -ZAR 1.7 M; payback inside horizon)< 9 yrinside horizonSTRONG GO

Quantitative cells in this table are derived from the same scenario model as §2 / §4 at the stated tariff, holding all other inputs fixed. They are not hand-derived.

6. CTA

Request an RFQ — Orchard Solar 250 kWp ZA Datasheet on request (submit via RFQ form)

R14: No PDF is hosted at /datasheets/orchard-solar-250kwp-za.pdf; the datasheet is supplied on request via the live RFQ form (/rfq/, site path). The RFQ form is the live TradVolt endpoint — no placeholder.

7. Certification disclaimer (R4)

No certification is claimed. This brief carries no third-party certification. Any internal reference (e.g., a build hash or internal TV identifier) is internal-only record-keeping and is not a certification of compliance, performance, or fitness for purpose. The brief is an scenario TCO model output, not a certified product, system, or installation.

8. HS code / duty lookup (R5 — no duty rates asserted)

HS codeDescriptionDuty rate (SA)Lookup path
8541.43Photovoltaic cells, modulesNot asserted on this pageSARS Customs & Excise Tariff — https://www.sars.gov.za/
8504.40Static converters (inverters)Not asserted on this pageSARS Customs & Excise Tariff — https://www.sars.gov.za/
8501.52 / 8501.53AC generators (BESS-coupled, if added)Not asserted on this pageSARS Customs & Excise Tariff — https://www.sars.gov.za/
7610.90Aluminium mounting structuresNot asserted on this pageSARS Customs & Excise Tariff — https://www.sars.gov.za/

Disclaimer: No duty rate is asserted on this page. Final HS classification and duty liability for any imported component must be confirmed by a licensed customs broker or SARS binding ruling via https://www.sars.gov.za/. For non-SA destinations the corresponding public tariff lookups apply: EU TARIC (https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en), USITC HTS (https://hts.usitc.gov/), UK Global Tariff (https://www.trade-tariff.service.gov.uk/), Japan Customs (https://www.customs.go.jp/english/), Australian Border Force (https://www.abf.gov.au/), Ghana Revenue Authority (https://gra.gov.gh/), Uganda Revenue Authority (https://www.ura.go.ug/).

9. Standards referenced (R9 — exact designations, no invented IDs)

10. Notes & limitations

— end of brief —