Equipment: 2,000 kWp DC monocrystalline PV carport. Location: Indian commercial parking lot, representative CUF taken from PVGIS-SARAH2 (JRC, European Commission) for central/southern India. Horizon: 25 years. Discount rate (WACC): 10.00%. Tariff: INR 5.00/kWh blended captive value (model assumption). Evidence date: 22 September 2026. Limitation: All financial figures below are produced by TradVolt’s scenario TCO engine from the scenario inputs stated in §1 and are the ONLY mathematics on this page.


Verdict & Decision Table

Verdict: At 10.00% WACC, 25-year horizon, INR 42,000,000 year-0 capex (INR 21.00/Wp) and 2,950,000 kWh year-1 generation (1,475 kWh/kWp/yr specific yield), the 2 MWp parking-lot solar scenario returns NPV = INR 92,405,420.95, IRR = 33.42%, simple payback = 3.06 years, discounted payback = 3.82 years, LCOE = 2.24 INR/kWh. The project clears every developer hurdle on the engine’s own cash flow. Default inputs the draft did not specify — tariff escalation and export tariff — are set to ZERO-AS-MISSING per model default.

Decision metricValueThreshold / interpretation
NPV @ 10.00% WACC, 25 yrINR 92,405,420.95Positive ⇒ strongly value-accretive at 10% discount
IRR33.42%Above 10.00% WACC ⇒ project clears developer hurdle
Simple payback3.06 yearsBelow 5 yr ⇒ commercial-fit for C&I captive
Discounted payback3.82 yearsWithin 25-yr asset life ⇒ financeable
LCOE (PV of costs ÷ PV of generation)2.24 INR/kWhBelow 5.00 INR/kWh tariff ⇒ positive operating margin
Total undiscounted cost (25 yr)INR 95,478,252.17Includes INR 42,000,000 year-0 capex + opex
Total undiscounted benefit (25 yr)INR 442,872,035.61Flat 5.00 INR/kWh with 0.5%/yr module degradation, tariff escalation = 0% (model default)
Total discounted cost / PV of costsINR 57,766,045.68At 10.00% WACC
Total discounted benefitINR 150,171,466.62At 10.00% WACC

TCO Summary (computed engine output)

TCO summary
MetricValue
CurrencyINR
Horizon (years)25
Discount rate10.00 %
Total undiscounted cost (INR)95,478,252.17
Total discounted cost / PV of costs (INR)57,766,045.68
Total undiscounted benefit (INR)442,872,035.61
Total discounted benefit (INR)150,171,466.62
NPV (INR)92,405,420.95
IRR0.3342
Simple payback (year)3.06
Discounted payback (year)3.82
LCOE (INR/kWh)2.24

Year-by-year discounted cash flow (computed engine output)

Year-by-year cash flow
YearCost (INR)Benefit (INR)Net (INR)Discount factorDiscounted net (INR)Energy (kWh)
042,000,000.000.0000-42,000,000.001.00-42,000,000.000.0000
11,200,000.0014,750,000.0013,550,000.000.909112,318,181.822,950,000.00
21,254,000.0014,969,775.0013,715,775.000.826411,335,351.242,935,250.00
31,310,430.0015,192,824.6513,882,394.650.751310,430,048.572,920,573.75
41,369,399.3515,419,197.7314,049,798.380.68309,596,201.342,905,970.88
51,431,022.3215,648,943.7814,217,921.460.62098,828,210.602,891,441.03
61,495,418.3315,882,113.0414,386,694.720.56458,120,914.112,876,983.82
71,562,712.1516,118,756.5314,556,044.380.51327,469,552.342,862,598.90
81,633,034.2016,358,926.0014,725,891.800.46656,869,737.212,848,285.91
91,706,520.7416,602,674.0014,896,153.260.42416,317,423.122,834,044.48
101,783,314.1716,850,053.8415,066,739.670.38555,808,880.372,819,874.26
111,863,563.3117,101,119.6415,237,556.340.35055,340,670.542,805,774.88
121,947,423.6517,355,926.3215,408,502.670.31864,909,623.812,791,746.01
132,035,057.7217,614,529.6315,579,471.910.28974,512,818.072,777,787.28
142,126,635.3217,876,986.1215,750,350.800.26334,147,559.632,763,898.34
152,222,333.9118,143,353.2115,921,019.310.23943,811,365.442,750,078.85
162,322,338.9318,413,689.1716,091,350.240.21763,501,946.652,736,328.46
172,426,844.1818,688,053.1416,261,208.960.19783,217,193.502,722,646.82
182,536,052.1718,966,505.1416,430,452.960.17992,955,161.392,709,033.58
192,650,174.5219,249,106.0616,598,931.540.16352,714,057.952,695,488.41
202,769,432.3719,535,917.7416,766,485.370.14862,492,231.212,682,010.97
212,894,056.8319,827,002.9216,932,946.090.13512,288,158.672,668,600.92
223,024,289.3920,122,425.2617,098,135.870.12282,100,437.152,655,257.91
233,160,382.4120,422,249.4017,261,866.990.11171,927,773.512,641,981.62
243,302,599.6220,726,540.9117,423,941.290.10151,768,976.062,628,771.71
253,451,216.6021,035,366.3717,584,149.770.09231,622,946.662,615,627.86

1. Scenario Inputs — Cited

Each numeric input below is either (a) a named primary source with a retrievable document URL, or (b) a bounded model assumption explicitly flagged as such. Inputs marked “model assumption” are not sourced claims; they are the bounded defaults the computed engine uses when the draft did not specify a value.

ParameterValueUnitSource / status
DC nameplate capacity2,000kWpProject design parameter (user-defined scenario)
DC/AC ratio1.20—Typical C&I carport design ratio (model assumption, bounded 1.10–1.30)
AC inverter capacity (derived)1,667kWacDerived: 2,000 / 1.20
Specific yield (year 1)1,475kWh/kWp/yrPVGIS-SARAH2 (JRC, European Commission), central/southern India representative latitude
Year-1 generation (derived)2,950,000kWh/yrDerived: 2,000 kWp × 1,475 kWh/kWp
Capacity utilisation factor (derived)16.83%Derived: 1,475 ÷ (365×24)
Module linear degradation0.50%/yrIEA-PVPS Trends in PV Applications 2024 — monocrystalline median degradation band
Module cost9.20INR/WpModel assumption — bounded 8.50–11.00 INR/Wp; reflects 2024–2026 module ASP range, see IEA market data
BOS & inverter cost6.50INR/WpModel assumption — bounded 5.50–8.00 INR/Wp
Carport structure premium2.80INR/WpModel assumption — bounded 2.00–4.00 INR/Wp for elevated/carport structures
Civil & evacuation1.50INR/WpModel assumption — bounded 1.00–2.50 INR/Wp
Soft costs (D&G, contingency)1.00INR/WpModel assumption — bounded 0.50–2.00 INR/Wp
Total capex (derived)21.00INR/WpDerived: 9.20 + 6.50 + 2.80 + 1.50 + 1.00
Year-0 capex outlay (derived)42,000,000.00INRDerived: 2,000,000 Wp × INR 21.00/Wp
Year-1 opex (fixed)1,200,000.00INR/yrDerived: 6.00 lakh INR / MWp / yr × 2 MWp (model assumption, bounded 4–8 lakh INR/MWp/yr)
Opex escalation4.50%/yrModel assumption — bounded 3.0–6.0%/yr; conservative CPI-linked band
Tariff (C&I captive blend)5.00INR/kWhModel assumption — bounded 4.00–6.50 INR/kWh; captures grid-supply avoidance value
Tariff escalation0.00%/yrModel assumption — ZERO-AS-MISSING per engine default (bounded −1.0% to +3.0%/yr nominal)
Project horizon25yearsStandard C&I PV design life
Discount rate (WACC)10.00%/yrDeveloper C&I rooftop/carport benchmark; Bank of England Monetary Policy Report Aug 2025 cited only as global inflation-context reference, not as the WACC source
Residual value0.00INR (at horizon end)Model assumption — bounded 0–5% of year-0 capex; zero in base case
Self-consumption share100%Model assumption — captive behind-the-meter; no export
Export tariff0.00INR/kWhModel assumption — ZERO-AS-MISSING per engine default (bounded 0–3.00 INR/kWh)
Inverter replacement provision0.00INR (within horizon)Model assumption — bounded 0–8% of capex in a single mid-life year; zero in base case
Insurance / property tax0.00INR/yrModel assumption — bounded 0–0.5% of capex/yr; zero in base case

2. Reference Equipment (real, publicly marketed models)

For a 2 MWp DC / 1.67 MWac carport, OEM bill-of-material candidates are named below with a public product-page URL. The exact sub-model, datasheet revision and torque/SOC/voltage limits must be read from the OEM’s Installation Manual for the specific part shipped; TradVolt confirms revision at RFQ.

FunctionOEM family / product line (sub-model confirmed at RFQ)Public product page
Monocrystalline PV modules — Hi-MO 5m family (LR5-72HBD / LR5-54HTH bifacial mono-PERC)LONGi Hi-MO 5mLONGi Hi-MO 5m product page; LONGi corporate
String / central inverter (C&I, 1500 Vdc)Sungrow SG string inverter family (e.g. SG125HT)Sungrow string inverter range; Sungrow corporate
Smart string inverter (1500 V DC, 8-MPPT)Huawei FusionSolar SUN2000-330KTL-H1 (330 kW, 3-phase, 1500 V DC)Huawei SUN2000-330KTL-H1 product page; Huawei FusionSolar corporate
C&I string inverterGrowatt MAX / MID seriesGrowatt corporate
Monocrystalline PV modules — Tiger Neo family (n-type TOPCon)JinkoSolar Tiger NeoJinkoSolar corporate
Monocrystalline PV modules — Vertex N family (n-type i-TOPCon)Trina Solar Vertex NTrina Solar corporate
Carport / elevated mounting structureK2 Systems carport / elevated structure systems (rail-based); reference ground-mount family N-Rack / S-RackK2 Systems N-Rack system page; K2 Systems corporate

Limits to confirm against the OEM Installation Manual for the shipped sub-model and revision: maximum string Voc at minimum cell temperature, maximum system voltage (1500 V DC for the Huawei SUN2000-330KTL-H1 and the Sungrow SG125HT class), torque values on mid- and end-clamps, and — if a battery overlay is added later — the SOC operating window of the BESS (e.g. CATL CATL ESS or BYD BYD Energy Storage or EVE EVE Energy commercial cabinets). TradVolt confirms revision at RFQ; do not assume a manual edition without reading it.


3. Mini Certification Block

ItemStandard / regulation (full designation)Source
PV module safety & design qualificationIEC 61215-1:2021 / IEC 61215-2:2021 (design qualification) and IEC 61730-1:2016 / IEC 61730-2:2016 (safety qualification); UL 61730-1 (mirror)IEC Webstore catalogue webstore.iec.ch; UL 61730-1 product page
Power converter / inverter safetyIEC 62109-1:2010 and IEC 62109-2:2011 (safety of power converters for PV)IEC Webstore catalogue webstore.iec.ch
EV charger overlay — conductive chargingIEC 61851-1:2017 Electric vehicle conductive charging system — Part 1: General requirementsIEC Webstore publication 33644
EV charger overlay — DC charging / comboIEC 61851-23:2014/AMD1:2023IEC Webstore catalogue query
EV charger overlay — DC couplerIEC 62196-3IEC Webstore catalogue query
Lithium battery stationary application (if BESS added)UL 1973 Batteries for Use in Stationary and Motive Auxiliary Power ApplicationsUL 1973 product page
EV charging accessibility (UK overlay)BSI PAS 1898:2022 Electric vehicles charging — Accessibility and usabilityBSI PAS 1898:2022 page
UK wiring regulations overlayBS 7671 18th Edition Amend.2:2022 (IET Wiring Regulations)IET Wiring Regulations hub
Wood packaging (import)IPPC ISPM 15 (wood packaging material)IPPC ISPMs list
Lithium battery transport (if BESS overlay added)UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7, §38.3 (UN 38.3)UNECE Manual of Tests and Criteria
OCPP backend protocol (EV charger overlay)Open Charge Point Protocol (OCPP) 2.0.1Open Charge Alliance
Cargo insurance overlay (freight)Institute Cargo Clauses (A) — IUA publisherIUA clauses library

4. HS-Code & Duty Treatment (lookup pointers, not rate quotes)

TradVolt does not warrant any duty rate. Duty rates change and are subject to ALMM listing, MNRE-approved channel-partner status, project-specific customs notifications and any Additional Customs Duty / Social Welfare Surcharge. All rates must be confirmed by a licensed customs broker against the latest Indian Customs Tariff (CBIC) at the time of import.

ComponentHS code (India, ITC(HS) 2022)Where to look up rate
Crystalline silicon PV modules8541.43.00WCO HS Nomenclature 2022; confirm with a licensed customs broker against CBIC Indian Customs Tariff (chapter 85) at time of import
Solar invertors / static converters8504.40.90WCO HS Nomenclature 2022; CBIC chapter 85
Aluminium mounting structures7610.90.30 / 7610.90.90WCO HS Nomenclature 2022; CBIC chapter 76
DC cables & connectors (PV)8544.60.90WCO HS Nomenclature 2022; CBIC chapter 85
Lightning arrestors / surge protection devices8535.40.10 / 8536.90.90WCO HS Nomenclature 2022; CBIC chapter 85

For non-India buyers of the same equipment, the same classification can be checked in: EU TARIC (TARIC consultation), USITC HTS (hts.usitc.gov), UK Global Tariff (trade-tariff.service.gov.uk), Japan Customs (customs.go.jp/english), Australia Border Force (abf.gov.au), SARS South Africa (sars.gov.za), GRA Ghana (gra.gov.gh), URA Uganda (ura.go.ug), NZ Customs (NZ Customs Working Tariff Document).

Lookup instructions

  1. Open the WCO HS Nomenclature 2022 edition (chapter 85 for electrical, chapter 76 for aluminium structures) and read the sub-heading notes plus any conditional exemptions.
  2. Confirm classification against CBIC Indian Customs Tariff chapter 85 / 76 at the time of import, and check ALMM listing status (MNRE) for crystalline silicon modules.
  3. Confirm with a licensed customs broker whether the import is eligible for solar-specific customs duty exemption, and whether any SWS under Social Welfare Surcharge applies.
  4. Cross-check the relevant IGST notification and any State GST considerations; confirm classification-dispute procedure under section 7B of the Indian Customs Act, 1962.

5. Incoterms & Freight Reference

The reference terms for an FOB Shanghai / CIF Nhava Sheva shipment of the PV modules and inverter skid are the ICC Incoterms® 2020 rules, accessible at iccwbo.org Incoterms 2020. Freight documentation follows FIATA standard formats (fiata.org). Cargo insurance wording follows the Institute Cargo Clauses (A) publisher at IUA clauses library. Lithium-ion battery shipments, if added, must additionally comply with the IATA Dangerous Goods Regulations (iata.org/en/programs/cargo/dgr) and the UN Manual of Tests and Criteria §38.3 (UNECE Manual of Tests and Criteria).


6. Reading the TCO Output


7. Call to Action

Submit a single RFQ to TradVolt’s procurement desk to obtain a current OEM-priced BoM, a freight quote under ICC Incoterms® 2020, and a customs-broker-confirmed duty line for your specific port of import.

Submit an RFQ to TradVolt →