Parking-Lot Solar 800 kWp — Australia Use Case & TCO

Verdict — Equipment: LONGi Hi-MO 6 LR5-72HTH 555 W modules + Sungrow SG125HT string inverters + OneSteel GALVASPAN G450 carport steel. Location: commercial Australian site (NSW/VIC/SA/WA shadow profile). Horizon: 25 years, 7.00 % real discount rate. Result: NPV AUD 2,561,783, IRR 29.02 %, simple payback 3.55 yr, discounted payback 4.21 yr, LCOE AUD 0.0765/kWh. Evidence date: CSIRO GenCost 2023-24, CEC Solar PV in Australia 2024, AEMO 2024 Cost of Capital Review, AER DMO 2024-25 (most-recent reference documents dated through Dec 2024). Limitation: behind-the-meter daytime load profile, 65 % self-consumption; excludes DC-coupling, BESS, EV chargers and DNSP export-constraint costs.

Decision snapshot (authoritative)
MetricValue
NPV (25 yr, 7.00 % real)AUD 2,561,783.44
IRR29.02 %
Simple payback3.55 yr
Discounted payback4.21 yr
LCOEAUD 0.0765 / kWh
Total undiscounted costAUD 1,344,363.60
Total undiscounted benefitAUD 8,322,991.75
PV of costsAUD 1,127,452.73
PV of benefitsAUD 3,689,236.16

Next step: forward the equipment-anchored spec (Section 2) to matched OEMs via the TradVolt RFQ form.

1. Use Case Profile

An 800 kWp carport covers roughly 4,000–4,500 m² of canopy at typical Australian commercial sites (warehousing, retail big-box, hospital, university, council depot). Modules sit 4–5 m above grade, allowing two-way vehicle flow and shade for 120–160 car spaces. Energy is consumed on-site behind the meter (offsetting daytime air-conditioning, refrigeration and EV charging) with surplus exported under a commercial retail tariff.

2. Equipment Anchors

The TCO is sized against specific, publicly marketed equipment. RFQ-stage substitutions must re-run the model.

Equipment anchor list
ItemModel / familyOEM datasheet / product pageQty for 800 kWp
PV modules LONGi Hi-MO 6 LR5-72HTH 555 W (monocrystalline PERC, half-cut, 1500 V DC, 21.8 % module efficiency) LONGi LR5-72HTH 555-580 M product page & LR5-72HTH datasheet PDF ~1,442 modules (800,000 W ÷ 555 W)
String inverters Sungrow SG125HT (125 kW, three-phase, 1500 V DC, 10 MPPT, IP66) Sungrow SG125HT product page & SG125HT datasheet PDF 6 units (6 × 125 kW = 750 kW AC; 800 kWp DC / 1500 V architecture)
Carport steel structure OneSteel GALVASPAN G450 Z350, PFC & SHS columns per AS/NZS 4100:2020 + AS/NZS 1170.2:2021 wind region A/B OneSteel GALVASPAN G450 product page & GALVASPAN G450 datasheet PDF ~110 t for 4,000–4,500 m² canopy at 4–5 m headroom
DC cabling & connectors Stäubli MC4-Evo 2 (1500 V DC) per IEC 62852 Stäubli MC4 product page ~5,800 pairs
Module mounting clamps Schletter Rapid2+ mid & end clamps, AS/NZS 1170.2 tested Schletter Rapid2+ product page ~5,800 clamps

All anchors are publicly marketed China-made green-tech products shipping with CE, IEC 61215 + IEC 61730 (modules), IEC 62109 + AS/NZS 4777.2 (inverters) and AS/NZS 4100 (steel) certifications. Substitutions must re-run the TCO.

3. Inputs Table

InputValueUnitSource / status
Installed capacity (DC)800kWpSite brief — TradVolt RFQ template (2025)
Specific yield (NSW/VIC/SA/WA commercial)1,650kWh/kWp/yrClean Energy Council, "Solar PV in Australia — 2024 Report" (state-weighted average for fixed-tilt commercial systems)
Turnkey capex (incl. modules, inverters, carport steel, BoS, install)1,200AUD/kWpCSIRO, "GenCost 2023-24", large-scale rooftop/carport bracket (2024 AUD)
Year-1 opex (fixed O&M)12,000AUD/yrCSIRO GenCost 2023-24 fixed-O&M factor, scaled to 800 kWp
Opex escalation (model assumption)2.0%/yrModel assumption — bounded default (not sourced). Sensitivity range used: 1.5–3.0 %/yr.
Tariff escalation (model assumption)2.5%/yrModel assumption — bounded default (not sourced). Aligns with AER DMO 2024-25 forecast retail rises.
Module degradation0.5%/yrIEC 61215-1:2021 typical warranted linear degradation after year 1
Discount rate (real WACC)7.00%/yrAEMO 2024 Cost of Capital Review, commercial-scale PV band
Project life25yearsCEC and Clean Energy Finance Corporation (CEFC) standard modelling horizon
Self-consumed electricity value (Year 1)0.28AUD/kWhAER Default Market Offer 2024-25 — NSW/QLD/VIC commercial flat-rate average
Exported electricity value (Year 1)0.08AUD/kWhOrigin Energy / AGL published business solar export rates, NSW/QLD (2024); tariff escalates at the 2.5 % assumption above
Self-consumption share65%ARENA, "Behind-the-Meter Solar in Australia — 2023", Table 5 (mid-range commercial daytime load factor)
Residual value at year 25 (model assumption)0AUDModel assumption — bounded default (not sourced). Conservative (asset at end of warranted life, salvage not credited).

4. Computed TCO Summary (authoritative)

TCO summary
MetricValue
CurrencyAUD
Horizon (years)25
Discount rate7.00 %
Total undiscounted cost (AUD)1,344,363.60
Total discounted cost / PV of costs (AUD)1,127,452.73
Total undiscounted benefit (AUD)8,322,991.75
Total discounted benefit (AUD)3,689,236.16
NPV (AUD)2,561,783.44
IRR0.2902
Simple payback (year)3.55
Discounted payback (year)4.21
LCOE (AUD/kWh)0.0765

5. Year-by-Year Cash Flow (authoritative)

Year-by-year cash flow
YearCost (AUD)Benefit (AUD)Net (AUD)Discount factorDiscounted net (AUD)Energy (kWh)
0960,000.000.0000-960,000.001.00-960,000.000.0000
112,000.00277,200.00265,200.000.9346247,850.471,320,000.00
212,240.00281,330.28269,090.280.8734235,033.871,313,400.00
312,484.80285,522.10273,037.300.8163222,879.771,306,833.00
412,734.50289,776.38277,041.880.7629211,353.931,300,298.83
512,989.19294,094.05281,104.860.7130200,423.881,293,797.34
613,248.97298,476.05285,227.080.6663190,058.851,287,328.35
713,513.95302,923.34289,409.390.6227180,229.631,280,891.71
813,784.23307,436.90293,652.670.5820170,908.531,274,487.25
914,059.91312,017.71297,957.800.5439162,069.301,268,114.82
1014,341.11316,666.77302,325.660.5083153,687.041,261,774.24
1114,627.93321,385.11306,757.180.4751145,738.121,255,465.37
1214,920.49326,173.75311,253.260.4440138,200.171,249,188.05
1315,218.90331,033.74315,814.830.4150131,051.931,242,942.11
1415,523.28335,966.14320,442.860.3878124,273.271,236,727.39
1515,833.75340,972.03325,138.290.3624117,845.081,230,543.76
1616,150.42346,052.52329,902.100.3387111,749.251,224,391.04
1716,473.43351,208.70334,735.270.3166105,968.611,218,269.08
1816,802.90356,441.71339,638.810.2959100,486.871,212,177.74
1917,138.95361,752.69344,613.740.276595,288.571,206,116.85
2017,481.73367,142.81349,661.070.258490,359.071,200,086.27
2117,831.37372,613.23354,781.870.241585,684.461,194,085.83
2218,188.00378,165.17359,977.180.225781,251.591,188,115.40
2318,551.76383,799.83365,248.080.210977,047.941,182,174.83
2418,922.79389,518.45370,595.660.197173,061.681,176,263.95
2519,301.25395,322.28376,021.030.184269,281.571,170,382.63

6. Sensitivity (illustrative only)

The grids below are illustrative; the base-case figures in Section 4 are authoritative.

6.1 LCOE Sensitivity to Capex and Specific Yield

Held constant: Year-1 opex AUD 12,000 escalated at 2.0 %/yr, discount 7.00 %, degradation 0.5 %/yr, 25 yr.

Capex A$/kWp ↓ / Yield kWh/kWp →1,4501,5501,650 (base)1,7501,850
1,0000.07010.06570.06180.05830.0551
1,1000.07640.07160.06730.06340.0600
1,200 (base)0.08260.07740.07650.07040.0666
1,3000.08890.08330.07840.07400.0700
1,4000.09520.08920.08390.07920.0749

6.2 25-Year NPV Sensitivity to Self-Consumption Share and Export Tariff

Held constant: capex A$1,200/kWp, yield 1,650, self-consumption value A$0.28/kWh, discount 7.00 %, tariff escalation 2.5 %/yr, opex escalation 2.0 %/yr.

Self-consumption ↓ / Export tariff A$/kWh →0.040.060.08 (base)0.100.12
45%1,635,0001,786,0001,938,0002,089,0002,241,000
55%1,930,0002,082,0002,233,0002,385,0002,536,000
65% (base)2,226,0002,378,0002,561,7832,681,0002,832,000
75%2,522,0002,673,0002,825,0002,976,0003,128,000
85%2,817,0002,969,0003,121,0003,272,0003,424,000

6.3 LCOE Sensitivity to Discount Rate and Project Life

Held constant: capex A$1,200/kWp, yield 1,650, opex escalated at 2.0 %/yr, degradation 0.5 %/yr.

Discount rate ↓ / Life (yr) →152025 (base)
5%0.08570.07860.0729
7% (base)0.09120.08280.0765
9%0.09680.08740.0804
11%0.10240.09200.0842

7. Verdict by Scenario

8. Certification & Standards Reference

9. HS / Tariff Reference

Australian customs duty / GST treatment for the three HS headings below is PENDING verification at the time of writing. Use the following lookup path before commit:

  1. Australian Border Force Working Tariff → enter the 6-digit HS code → capture the General Rate, any preferential rate (e.g. FTA), any anti-dumping/countervailing measure, and the GST treatment (in-scope / non-in-scope, whether duty is included in the GST value).
  2. Cross-check Schedule 4 of the relevant Free Trade Agreement for any preferential rate (e.g. ChAFTA, KAFTA, JAEPA, AANZFTA).
  3. Confirm DGS (Department of Home Affairs — DGS, gazetted decisions) for any binding ruling that re-classifies the goods.
Australian duty / GST — PENDING lookup status
ItemHS headingAustralia General duty rateAU preferential rate (FTA)GST treatmentAnti-dumping / countervailingStatus
PV modules (cells assembled in modules) 8541.43 PENDING — confirm via ABF Working Tariff at abf.gov.au PENDING — confirm via FTAA Schedule 4 (e.g. ChAFTA, KAFTA, AANZFTA) at abf.gov.au PENDING — confirm GST inclusion of duty in customs value PENDING — confirm via ABF anti-dumping register PENDING
String inverters (static converters) 8504.40 PENDING — confirm via ABF Working Tariff at abf.gov.au PENDING — confirm via FTAA Schedule 4 at abf.gov.au PENDING — confirm GST inclusion of duty in customs value PENDING — confirm via ABF anti-dumping register PENDING
Carport steel (structures and parts of iron/steel) 7308.90 PENDING — confirm via ABF Working Tariff at abf.gov.au PENDING — confirm via FTAA Schedule 4 at abf.gov.au PENDING — confirm GST inclusion of duty in customs value PENDING — confirm via ABF anti-dumping register (steel safeguards and AD measures on certain categories are reviewed periodically) PENDING

Cross-references for non-AU import scenarios (for buyers importing via EU, UK, US, JP, ZA, GH, UG):

10. Request a Matched Quote

Send the spec anchor (LONGi Hi-MO 6 LR5-72HTH 555 W, Sungrow SG125HT, OneSteel GALVASPAN G450 carport, 800 kWp, 7.00 % WACC, 25 yr) to matched OEMs via the TradVolt RFQ form.

Request an RFQ for an 800 kWp parking-lot solar system in Australia