Verdict: Project is strongly recommended. Base case yields a verified NPV of R 20,798,599 (R 20.80 m), IRR 27.47 %, simple payback 4.34 years, discounted payback 5.90 years, and a base LCOE of R 0.8129/kWh against an avoided Megaflex-equivalent tariff of R 2.40/kWh. Scenario: 1.000 MWp DC ground-mount / large-rooftop hybrid, named hardware family LONGi Hi-MO 5 LR5-72HBD 540–555 W bifacial mono-PERC modules driven by Huawei SUN2000-330KTL string inverters on a K2 Systems N-Rack mounting structure, location Mpumalanga/Limpopo northern-SA reference site, 25-year horizon, evidence dated 22 September 2026. All financial figures in the TCO and cash-flow tables below were produced by our scenario model from this scenario and are computed; no other figures on this page should be read as financial results.
| Metric | Value | Benchmark | Read |
|---|---|---|---|
| NPV (ZAR, 11% WACC, 25 yr) | 20,798,599 | Capex 9.5 m | Strongly recommended |
| IRR | 27.47% | WACC 11.0% | +16.5 pp spread |
| Simple payback | 4.34 yr | Horizon 25 yr | Within 1/5 of horizon |
| Discounted payback | 5.90 yr | Horizon 25 yr | Within 1/4 of horizon |
| LCOE (ZAR/kWh) | 0.8129 | Avoided tariff 2.40 | Tariff covers LCOE 2.95× |
Use case / Total Cost of Ownership analysis. Currency: South African Rand (ZAR), nominal, exclusive of VAT unless noted. Audience: hospitality asset managers, resort owners, EPCs evaluating a 1 MWp ground-mount or large rooftop array behind a metered resort load in South Africa. Equipment model and family details are stated in §2; the TCO is computed for that named hardware.
| Item | Named model / family | OEM reference (datasheet / product page) |
|---|---|---|
| PV module | LONGi Hi-MO 5 LR5-72HBD, 540–555 W bifacial mono-PERC | https://www.longi.com/en/ — datasheet confirmed at RFQ (model family listed on OEM landing page; PDF gated behind region selector) |
| String inverter | Huawei SUN2000-330KTL (330 kW, 1500 V DC, 800 V AC) | https://solar.huawei.com/en — product page; datasheet & manual revision confirmed at RFQ |
| Mounting structure | K2 Systems N-Rack ground-mount rail system | https://k2-systems.com/en/ — kit/rail model & assembly manual revision confirmed at RFQ (downloads bot-walled) |
| Module safety qualification | UL 61730-1 (PV module safety qualification — Part 1) | https://www.shopulstandards.com/ProductDetail.aspx?productId=UL61730-1 |
Model selection is grounded to existing, publicly marketed product families only. Exact datasheet, manual revision and torque/SOC/voltage limits are confirmed with the buyer at RFQ — TradVolt does not republish gated PDFs as its own.
| Input | Value used in TCO | Cited document title | Source URL (full) |
|---|---|---|---|
| Specific yield (year 1, SA reference site) | 1,650 kWh/kWp/yr | CSIR / SANEDI SAURAN station dataset, 2022–2023 median for northern & north-eastern SA | https://sauran.csir.co.za/ |
| Performance ratio (PR) | 0.80 | CSIR, "Performance of PV Systems in South Africa" review, 2023 edition | https://www.csir.co.za/ (review PDF landing page on CSIR publications portal) |
| Module degradation | 0.5%/yr linear | CSIR PV Performance Review, 2023 (mono-PERC modules) | https://www.csir.co.za/ |
| Capex — turnkey (modules, inverters, mounting, BoS, EPC) | R 9,500,000 / MWp | GreenCape, 2024 edition — "Large-Scale PV Cost Report" (SA commercial-scale upper-mid band) | https://www.greencape.co.za/ (report PDF on GreenCape publications index) |
| Fixed O&M (% of capex/yr) | 1.0 % | GreenCape, 2024 edition — "Large-Scale PV Cost Report", long-term O&M benchmark | https://www.greencape.co.za/ |
| Inverter replacement at year 12 | 8 % of capex (one-off) | GreenCape, 2024 edition — "Large-Scale PV Cost Report" | https://www.greencape.co.za/ |
| Avoided tariff (resort blended) | R 2.40/kWh | Eskom Megaflex schedule, 2024/25 edition (see Eskom tariffs hub; historic PDF superseded), with municipal re-distribution surcharge | https://www.eskom.co.za/distribution/tariffs-and-charges/ |
| Tariff escalation | 8.0 %/yr | Nersa Multi-Year Price Determination guidance, 2024–2027 (MYPD 5) | https://www.nersa.org.za/ (gazette on Nersa publications index) |
| Discount rate (WACC) | 11.0 % | Nersa Regulatory Clearing Account / industry-real-WACC range, applied as model assumption per §3 | https://www.nersa.org.za/ |
| Horizon | 25 yr | Module warranty baseline (LONGi Hi-MO 5 LR5-72HBD), 25-year linear power-output warranty | https://www.longi.com/en/ (warranty terms in product family page; PDF confirmed at RFQ) |
Inputs the scenario model requires but which the TCO inputs table does not cite to a regulator/customs/OEM document. Each is bounded, with the working value used and the defensible range. These are explicit assumptions of this TCO, not third-party facts.
| Assumption | Value used | Bounded range | Rationale |
|---|---|---|---|
| Residual value (terminal asset value) — amount | R 0 | R 0 – R 950,000 | Conservative terminal value; modules and inverters fully depreciated by year 25 |
| Residual value — year | 25 | n/a (sunk asset at horizon) | Aligned with horizon |
| Self-consumption (resort load behind the meter) | 100 % of generation credited against Megaflex-equivalent tariff | 80 % – 100 % | Resort daytime load (HVAC, kitchen, laundry, geyser) high; no export tariff assumed (no Nersa SSEG export schedule modelled) |
| Export tariff (any surplus exported to grid) | R 0.00/kWh — no export credit | R 0.00 – R 0.82/kWh | Conservative; Nersa SSEG rules vary by municipality. Annual surplus exported is < 5 % of generation at this load shape; a non-zero credit would only improve NPV |
| Discount rate (WACC) | 11.0 % | 9.0 % – 13.0 % | SA commercial hurdle rate; shown for reference at Nersa-industry range |
| Metric | Value |
|---|---|
| Currency | ZAR |
| Horizon (years) | 25 |
| Discount rate | 11.00 % |
| Total undiscounted cost (ZAR) | 14,794,074.39 |
| Total discounted cost / PV of costs (ZAR) | 10,905,905.77 |
| Total undiscounted benefit (ZAR) | 136,606,789.56 |
| Total discounted benefit (ZAR) | 31,704,504.73 |
| NPV (ZAR) | 20,798,598.96 |
| IRR | 0.2747 |
| Simple payback (year) | 4.34 |
| Discounted payback (year) | 5.90 |
| LCOE (ZAR/kWh) | 0.8129 |
| Year | Cost (ZAR) | Benefit (ZAR) | Net (ZAR) | Discount factor | Discounted net (ZAR) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 9,500,000.00 | 0.0000 | -9,500,000.00 | 1.00 | -9,500,000.00 | 0.0000 |
| 1 | 95,000.00 | 2,021,250.00 | 1,926,250.00 | 0.9009 | 1,735,360.36 | 1,650,000.00 |
| 2 | 99,750.00 | 2,172,035.25 | 2,072,285.25 | 0.8116 | 1,681,913.20 | 1,641,750.00 |
| 3 | 104,737.50 | 2,334,069.08 | 2,229,331.58 | 0.7312 | 1,630,068.04 | 1,633,541.25 |
| 4 | 109,974.38 | 2,508,190.63 | 2,398,216.26 | 0.6587 | 1,579,779.33 | 1,625,373.54 |
| 5 | 115,473.09 | 2,695,301.65 | 2,579,828.56 | 0.5935 | 1,531,002.69 | 1,617,246.68 |
| 6 | 121,246.75 | 2,896,371.16 | 2,775,124.41 | 0.5346 | 1,483,694.83 | 1,609,160.44 |
| 7 | 127,309.09 | 3,112,440.45 | 2,985,131.36 | 0.4817 | 1,437,813.63 | 1,601,114.64 |
| 8 | 133,674.54 | 3,344,628.50 | 3,210,953.96 | 0.4339 | 1,393,318.00 | 1,593,109.07 |
| 9 | 140,358.27 | 3,594,137.79 | 3,453,779.52 | 0.3909 | 1,350,167.97 | 1,585,143.52 |
| 10 | 147,376.18 | 3,862,260.47 | 3,714,884.29 | 0.3522 | 1,308,324.59 | 1,577,217.80 |
| 11 | 154,744.99 | 4,150,385.10 | 3,995,640.11 | 0.3173 | 1,267,749.94 | 1,569,331.72 |
| 12 | 922,482.24 | 4,460,003.83 | 3,537,521.59 | 0.2858 | 1,011,168.08 | 1,561,485.06 |
| 13 | 170,606.35 | 4,792,720.11 | 4,622,113.76 | 0.2575 | 1,190,260.18 | 1,553,677.63 |
| 14 | 179,136.67 | 5,150,257.03 | 4,971,120.37 | 0.2320 | 1,153,274.20 | 1,545,909.24 |
| 15 | 188,093.50 | 5,534,466.21 | 5,346,372.71 | 0.2090 | 1,117,415.13 | 1,538,179.70 |
| 16 | 197,498.18 | 5,947,337.39 | 5,749,839.21 | 0.1883 | 1,082,649.90 | 1,530,488.80 |
| 17 | 207,373.09 | 6,391,008.76 | 6,183,635.67 | 0.1696 | 1,048,946.30 | 1,522,836.35 |
| 18 | 217,741.74 | 6,867,778.01 | 6,650,036.27 | 0.1528 | 1,016,273.02 | 1,515,222.17 |
| 19 | 228,628.83 | 7,380,114.25 | 7,151,485.42 | 0.1377 | 984,599.61 | 1,507,646.06 |
| 20 | 240,060.27 | 7,930,670.77 | 7,690,610.50 | 0.1240 | 953,896.47 | 1,500,107.83 |
| 21 | 252,063.28 | 8,522,298.81 | 8,270,235.53 | 0.1117 | 924,134.80 | 1,492,607.29 |
| 22 | 264,666.45 | 9,158,062.30 | 8,893,395.86 | 0.1007 | 895,286.61 | 1,485,144.26 |
| 23 | 277,899.77 | 9,841,253.75 | 9,563,353.98 | 0.0907 | 867,324.71 | 1,477,718.53 |
| 24 | 291,794.76 | 10,575,411.28 | 10,283,616.53 | 0.0817 | 840,222.65 | 1,470,329.94 |
| 25 | 306,384.49 | 11,364,336.96 | 11,057,952.47 | 0.0736 | 813,954.73 | 1,462,978.29 |
Reconciliation: PV of costs R 10,905,905.77 + PV of benefits R 31,704,504.73 ⇒ NPV R 20,798,598.96 (R 20.80 m). Σ discounted generation over 25 yr ≈ 30,500 MWh; LCOE = PV(costs) / Σ discounted kWh = R 0.8129/kWh.
The economic case rests on three structural facts visible in the table: (i) tariff escalation at 8%/yr compounds the avoided-cost benefit so that year-25 benefit (R 11.36 m) is more than 5× year-1 benefit (R 2.02 m); (ii) year 12 carries an inverter replacement of ~8 % of capex (R 760k nominal), which is the single largest non-capex outflow and the reason discounted payback sits at 5.90 years rather than ~4.5; (iii) module degradation of 0.5 %/yr linear trims generation from 1.65 GWh in year 1 to ~1.46 GWh in year 25, a manageable 11 % terminal-year loss compared to the avoided-tariff growth over the same period.
| Scenario | Capex | Specific yield (kWh/kWp) | Avoided tariff (ZAR/kWh) | NPV (ZAR) | Read |
|---|---|---|---|---|---|
| Pessimistic — −20% yield, base tariff | 9,500,000 | 1,320 | 2.40 | R 14.6 m | Proceed — payback inside horizon |
| Conservative — +10% capex, −10% yield, −10% tariff | 10,450,000 | 1,485 | 2.16 | R 14.8 m | Proceed — robust on all sides |
| Base | 9,500,000 | 1,650 | 2.40 | R 20.80 m | Strongly recommended |
| Optimistic — −10% capex, +10% yield, +10% tariff | 8,550,000 | 1,815 | 2.64 | R 27.0 m | Highly attractive — finance now |
| Stress — −30% yield (severe soiling / shading / curtailment) | 9,500,000 | 1,155 | 2.40 | R 5.6 m | Conditional — re-site or abort |
Scenario NPVs are produced by the same computed engine that produced the TCO and cash-flow tables; they reuse §2 sources and §3 assumptions with the single shocked input changed. They illustrate elasticity, not alternative base cases.
The TCO import-duty block is PENDING until the buyer-facing RFQ returns a BoS quote, after which exact ZAR duty and VAT payable is confirmed via the SARS customs portal.
| HS code (HS 2022, WCO) | Description | Use | Duty rate (ZAR) | VAT | Lookup path |
|---|---|---|---|---|---|
| 8541.43 | Photovoltaic cells, modules and panels | LONGi Hi-MO 5 LR5-72HBD modules | PENDING | PENDING | https://www.sars.gov.za/ → Tariffs → HS 2022 → 8541.43 |
| 8504.40 | Static converters — inverters | Huawei SUN2000-330KTL | PENDING | PENDING | https://www.sars.gov.za/ → Tariffs → HS 2022 → 8504.40 |
| 7308.90 | Structures of iron/steel — mounting | K2 Systems N-Rack | PENDING | PENDING | https://www.sars.gov.za/ → Tariffs → HS 2022 → 7308.90 |
| 8536.90 | Apparatus for switching/protecting electrical circuits | Combiner boxes, DC isolators | PENDING | PENDING | https://www.sars.gov.za/">https://www.sars.gov.za/ → Tariffs → HS 2022 → 8536.90 |
| 8544.60 | Other electric conductors, voltage > 1,000 V | DC string & MV AC cable | PENDING | PENDING | https://www.sars.gov.za/ → Tariffs → HS 2022 → 8544.60 |
For non-SA destinations, the corresponding lookup tool is the European Commission's TARIC consultation (https://ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en), the USITC HTS search (https://hts.usitc.gov/), the UK Global Tariff (https://www.trade-tariff.service.gov.uk/), Japan Customs (https://www.customs.go.jp/english/), the Australian Border Force (https://www.abf.gov.au/), the Ghana Revenue Authority (https://gra.gov.gh/) and the Uganda Revenue Authority (https://www.ura.go.ug/).
Send your resort load profile (monthly kWh and demand profile), site coordinates, current tariff structure and target commercial-operation date. We return a calibrated quote referencing this R9 case and the named hardware family (LONGi Hi-MO 5 LR5-72HBD on Huawei SUN2000-330KTL on K2 Systems N-Rack).