Base-case verdict. For a 1 MWp grid-tied PV plant serving an EU Southern resort (coastal/lakeside, mixed rooftop + ground carport), 25-year horizon, 6.00% discount rate, EUR-denominated, with the LONGi Hi-MO 5m LR5-54HTH module family and Huawei SUN2000-330KTL-H1 string inverter family, the scenario model returns NPV EUR 984,097, IRR 26.03%, simple payback 3.89 yr, discounted payback 4.56 yr, LCOE EUR 0.0281/kWh (2.81 ct/kWh). Evidence date: 2026-09-22. Limitation: figures are the model's base case; HS-code duties and grid-connection fees require a binding customs ruling and DSO quote per project.
| Item | Value |
|---|---|
| Equipment family | LONGi Hi-MO 5m LR5-54HTH module + Huawei SUN2000-330KTL-H1 string inverter |
| Location class | EU Southern (coastal/lakeside resort) |
| Horizon | 25 years |
| Discount rate (WACC) | 6.00% |
| Currency | EUR |
| NPV | EUR 984,096.77 |
| IRR | 26.03% |
| Simple payback | 3.89 yr |
| Discounted payback | 4.56 yr |
| LCOE | EUR 0.0281/kWh (2.81 ct/kWh) |
| Metric | Value |
|---|---|
| Currency | EUR |
| Horizon (years) | 25 |
| Discount rate | 6.00 % |
| Total undiscounted cost (EUR) | 591,837.46 |
| Total discounted cost / PV of costs (EUR) | 490,577.79 |
| Total undiscounted benefit (EUR) | 2,973,675.85 |
| Total discounted benefit (EUR) | 1,474,674.56 |
| NPV (EUR) | 984,096.77 |
| IRR | 0.2603 |
| Simple payback (year) | 3.89 |
| Discounted payback (year) | 4.56 |
| LCOE (EUR/kWh) | 0.0281 |
All equipment references are to publicly marketed product families. Specific certificate numbers and datasheet/manual revision for any individual shipment must be verified against the shipper's test report at RFQ stage (see /rfq/). The certification list in §6 is illustrative for the named model family; per-shipment revisions confirmed at RFQ (R12).
| Parameter | Value | Unit | Source |
|---|---|---|---|
| Installed capacity | 1,000 | kWp (DC) | Model assumption — bounded to project specification |
| Module family | LONGi Hi-MO 5m LR5-54HTH (monocrystalline bifacial, ~21.5% module efficiency class) | — | LONGi Hi-MO 5m family page (per-shipment datasheet edition confirmed at RFQ) |
| Inverter family | Huawei SUN2000-330KTL-H1 (330 kW, 1,500 V DC max, 8-MPPT, three-phase string) | — | Huawei SUN2000-330KTL-H1 product page (torque, DC voltage, MPPT/SOC thresholds per OEM manual revision confirmed at RFQ) |
| Mounting family | K2 Systems N-Rack / S-Rack rail-based ground-mount + pitched-roof kit family | — | K2 Systems N-Rack ground-mount system (exact rail kit and wind/snow load manual revision confirmed at RFQ) |
| Monitoring | Huawei FusionSolar Smart PV Management System / Sungrow iSolarCloud class SCADA gateway | — | Huawei FusionSolar; Sungrow string inverter range |
| Specific yield (Southern EU, ~35° tilt) | 1,420 | kWh/kWp/yr | EU PVGIS SARAH2 database query for the resort location class (year-1 input) |
| Linear annual module degradation | 0.45 | %/yr | LONGi Hi-MO 5m LR5-54HTH family datasheet (manufacturer warranted linear degradation); cross-check vs. IEA PVPS Trends in PV Applications 2024 |
| Discount rate (WACC) | 6.00 | %/yr | Model assumption — bounded to typical EU corporate WACC for green-tech PPVs |
| Project lifetime | 25 | years | Model assumption — bounded to typical PV plant economic life |
| Inverter replacement (year 12) | EUR 45,000 nominal | EUR | Model assumption — bounded to Huawei SUN2000-330KTL-H1 family installed cost |
| O&M (year 1) | 1.2% of CAPEX (4,740.12 EUR) | EUR | Model assumption — bounded to typical EU C&I PV O&M contract band |
| Blended self-consumption tariff | 0.085 | EUR/kWh | Model assumption — bounded to EU Southern resort retail band (vs. Eurostat non-household electricity prices) |
| Export tariff | 0.06 | EUR/kWh | Model assumption — bounded to typical EU Southern feed-in band |
| Self-consumption share | 55 | % | Model assumption — resort load shape |
| Tariff escalation | 1.5 | %/yr | Model assumption — bounded to long-run EU electricity CPI |
| O&M escalation | 2.0 | %/yr | Model assumption — bounded to typical EU O&M contract escalator |
| Year | Cost (EUR) | Benefit (EUR) | Net (EUR) | Discount factor | Discounted net (EUR) | Energy (kWh) |
|---|---|---|---|---|---|---|
| 0 | 395,010.00 | 0.0000 | -395,010.00 | 1.00 | -395,010.00 | 0.0000 |
| 1 | 4,740.12 | 104,725.00 | 99,984.88 | 0.9434 | 94,325.36 | 1,420,000.00 |
| 2 | 4,834.92 | 105,817.54 | 100,982.62 | 0.8900 | 89,874.17 | 1,413,610.00 |
| 3 | 4,931.62 | 106,921.49 | 101,989.86 | 0.8396 | 85,632.66 | 1,407,248.76 |
| 4 | 5,030.25 | 108,036.94 | 103,006.69 | 0.7921 | 81,590.95 | 1,400,916.14 |
| 5 | 5,130.86 | 109,164.04 | 104,033.18 | 0.7473 | 77,739.64 | 1,394,612.01 |
| 6 | 5,233.48 | 110,302.89 | 105,069.42 | 0.7050 | 74,069.79 | 1,388,336.26 |
| 7 | 5,338.15 | 111,453.63 | 106,115.48 | 0.6651 | 70,572.86 | 1,382,088.75 |
| 8 | 5,444.91 | 112,616.37 | 107,171.46 | 0.6274 | 67,240.70 | 1,375,869.35 |
| 9 | 5,553.81 | 113,791.24 | 108,237.43 | 0.5919 | 64,065.57 | 1,369,677.93 |
| 10 | 5,664.88 | 114,978.36 | 109,313.48 | 0.5584 | 61,040.08 | 1,363,514.38 |
| 11 | 5,778.18 | 116,177.88 | 110,399.70 | 0.5268 | 58,157.18 | 1,357,378.57 |
| 12 | 50,893.74 | 117,389.90 | 66,496.16 | 0.4970 | 33,046.55 | 1,351,270.37 |
| 13 | 6,011.62 | 118,614.57 | 112,602.95 | 0.4688 | 52,792.66 | 1,345,189.65 |
| 14 | 6,131.85 | 119,852.02 | 113,720.17 | 0.4423 | 50,298.54 | 1,339,136.30 |
| 15 | 6,254.49 | 121,102.38 | 114,847.89 | 0.4173 | 47,922.01 | 1,333,110.18 |
| 16 | 6,379.58 | 122,365.78 | 115,986.20 | 0.3936 | 45,657.54 | 1,327,111.19 |
| 17 | 6,507.17 | 123,642.36 | 117,135.19 | 0.3714 | 43,499.84 | 1,321,139.19 |
| 18 | 6,637.31 | 124,932.26 | 118,294.94 | 0.3503 | 41,443.90 | 1,315,194.06 |
| 19 | 6,770.06 | 126,235.61 | 119,465.55 | 0.3305 | 39,484.92 | 1,309,275.69 |
| 20 | 6,905.46 | 127,552.56 | 120,647.10 | 0.3118 | 37,618.34 | 1,303,383.95 |
| 21 | 7,043.57 | 128,883.26 | 121,839.69 | 0.2942 | 35,839.80 | 1,297,518.72 |
| 22 | 7,184.44 | 130,227.83 | 123,043.39 | 0.2775 | 34,145.17 | 1,291,679.88 |
| 23 | 7,328.13 | 131,586.43 | 124,258.30 | 0.2618 | 32,530.48 | 1,285,867.32 |
| 24 | 7,474.69 | 132,959.21 | 125,484.52 | 0.2470 | 30,991.98 | 1,280,080.92 |
| 25 | 7,624.19 | 134,346.31 | 126,722.12 | 0.2330 | 29,526.08 | 1,274,320.56 |
Energy column declines monotonically per the 0.45%/yr linear module degradation assumption. Discounted net column reconciles to the TCO summary totals and to NPV = EUR 984,096.77.
| Line | Value (EUR) | Note |
|---|---|---|
| Modules (LONGi Hi-MO 5m LR5-54HTH family) | 115,000 | 1,000 kWp × ~0.115 EUR/Wp; FOB indicative |
| Inverters (Huawei SUN2000-330KTL-H1 family) | 45,000 | String-inverter class |
| Mounting (K2 Systems N-Rack / S-Rack family) | 60,000 | Rooftop + ground carport mix |
| DC + AC BOS (cables, combiners, protection) | 55,000 | — |
| Grid connection + ring-main switchgear (Schneider RM6 class) | 55,000 | Fixed allowance; DSO quote required |
| SCADA / monitoring gateway (Huawei FusionSolar / Sungrow iSolarCloud class) | 12,000 | Fixed |
| Hardware subtotal | 342,000 | — |
| EPC margin + soft costs | 34,200 | 10% of hardware |
| Subtotal with soft costs | 376,200 | — |
| Contingency | 18,810 | 5% of subtotal |
| Total CAPEX (year 0) | 395,010 | Matches Year-0 cost in cash-flow table |
Year-1 OPEX = 1.2% × 395,010 = 4,740.12 EUR, escalating at 2.0%/yr (model assumption). Year-12 includes a Huawei SUN2000-330KTL-H1 family string-inverter replacement of EUR 45,000 nominal, reflecting mid-life refurbishment typical for the cited inverter class.
Customs classification below is a lookup path, not a binding ruling. Duty rates and any anti-dumping/countervailing measures must be confirmed per shipment via the EU TARIC consultation tool and a binding customs ruling (Article 33 of Regulation (EU) No 952/2013 — Union Customs Code).
For non-EU destinations, consult USITC HTS search, UK Global Tariff, Japan Customs, Australian Border Force, SARS, Ghana Revenue Authority, or Uganda Revenue Authority as applicable. Shipment terms per ICC Incoterms® 2020; dangerous-goods classification per IATA DGR (lithium battery components: see UN Manual of Tests and Criteria, ST/SG/AC.10/11/Rev.7, UN 38.3).
The list below is illustrative for the cited model families. Per-shipment certificate numbers, revision dates, and issuing laboratory must be verified against the shipper's test report and module/inverter nameplate. No certificate numbers are asserted on this page.
For the inputs in §1, the base case clears typical EU commercial hurdle rates: NPV EUR 984,097, IRR 26.03%, discounted payback 4.56 yr, LCOE EUR 0.0281/kWh. The economic case is robust to a Southern-EU resort load profile, a 25-year asset life, and standard warranty replacement of the string inverter at year 12. Procurement risk concentrates in customs classification, DSO connection cost, and resort self-consumption share — confirm each per project.
Request a structured quotation for the 1 MWp EU resort package at the TradVolt RFQ form.
Request RFQ — Resort Solar 1 MWp EU
All financial figures above are produced by Tradvolt's scenario TCO model from this page's scenario. Inputs not source-cited are bounded model assumptions listed in §1. The CAPEX breakdown in §3 is illustrative and reconciles to the model's year-0 cost of EUR 395,010.