Resort Solar 1 MWp in the US — TCO & Landed-Cost Brief

Tradvolt green-tech trade desk · Article ID: resort-solar-1mwp-us-r9 · Evidence date: 2026-09-22 · Horizon: 25 years · Discount rate: 7.00% · Currency: USD

Verdict (read first): For a 1,000 kWp TOPCon rooftop + carport array at a US Sun Belt resort, the 25-year computed TCO is NPV = +USD 535,399, IRR = 10.45%, simple payback = 9.58 yr, discounted payback = 15.20 yr, LCOE = USD 0.0914/kWh. Equipment family: TOPCon bifacial modules in the LONGi Hi-MO 7 / Jinko Tiger Neo 3.0 / Trina Vertex N class; three-phase string inverters in the Sungrow SG125 / SG110CX class; rail mounting in the K2 Systems SingleRail / CrossRail class. All US Section 201 / AD-CVD / Section 232 import-duty rows are PENDING — confirm at the USITC HTSUS lookup before procurement. US has no federal import VAT; only the assessment of applicable duties and any state sales/use tax on installed equipment applies. Limitation: figures below are scenario outputs from an scenario model with bounded default inputs for self-consumption percentage and export-tariff price (see §1.2); the model assumes 100% on-site consumption of generated kWh at the resort's blended retail tariff.

TCO summary (scenario model output)
MetricValue
CurrencyUSD
Horizon (years)25
Discount rate7.00 %
Total undiscounted cost (USD)1,956,134.42
Total discounted cost / PV of costs (USD)1,654,781.11
Total undiscounted benefit (USD)5,110,500.33
Total discounted benefit (USD)2,190,180.26
NPV (USD)535,399.15
IRR0.1045
Simple payback (year)9.58
Discounted payback (year)15.20
LCOE (USD/kWh)0.0914
Decision matrix (model output)
IndicatorValueThreshold for "go"Pass?
NPV @ 7%, 25 yr+USD 535,399.15> 0Yes
IRR10.45 %> WACC (7.00 %)Yes
Simple payback9.58 yr< 12 yrYes
Discounted payback15.20 yr< 20 yrYes (marginal)
LCOEUSD 0.0914 /kWh< avoided tariff USD 0.135/kWhYes

1. Equipment family and inputs

1.1 Equipment family (exact marketed models)

1.2 Inputs (bounded defaults; not externally sourced)

ParameterValueUnitOrigin / treatment
DC nameplate1,000kWpProject specification
Capacity factor18.5%Model assumption (AZ/FL/NV mixed-tilt + carport envelope)
Year-1 generation1,620,600kWh/yrComputed from CF × 8,760
Module degradation0.50%/yrModel assumption (TOPCon warranted envelope)
Blended retail tariff0.135USD/kWhModel assumption (resort, AZ/FL/NV commercial)
Tariff escalation3.0%/yrModel assumption (long-run commercial)
Capex (turnkey, gross)1.415USD/WpModel assumption (Year-0 spend line)
O&M (Year 1)18USD/kW-yrModel assumption, 1.5%/yr escalation
Horizon25yearsModel assumption (module warranty envelope)
Discount rate7.00%Model assumption (hospitality WACC)
asset.pv.self_consumption_pct100%Bounded default — entire generation treated as on-site self-consumed; model collapses to avoided-retail-tariff benefit (no export credit).
asset.pv.export_tariff_per_kwh0.000USD/kWhBounded default — no export tariff credited; any net-metering/PURPA/feed-in premium must be re-run as a model assumption override.
Bounded default disclosure: the two model-assumption rows asset.pv.self_consumption_pct = 100% and asset.pv.export_tariff_per_kwh = USD 0.000/kWh are not externally sourced; they are explicit bounded defaults. Replacing either with project-specific values requires re-running the scenario model.

2. Capex breakdown — 1 MWp reference deck

LineUSD/WpUSD%
Modules (TOPCon, ~580 Wp)0.340340,00024.0
String inverters (~110–125 kW AC)0.110110,0007.8
Racking + carport structure (K2 Systems SingleRail / CrossRail)0.180180,00012.7
DC + AC BOS0.120120,0008.5
EPC labour + installation0.260260,00018.4
Soft costs (permitting, design, interconnection)0.175175,00012.4
Developer overhead + margin0.140140,0009.9
Contingency (5%)0.09090,0006.3
Total turnkey capex (gross)1.4151,415,000100.0

3. Year-by-year cash flow (scenario model output)

Year-by-year cash flow
YearCost (USD)Benefit (USD)Net (USD)Discount factorDiscounted net (USD)Energy (kWh)
01,415,000.000.0000-1,415,000.001.00-1,415,000.000.0000
118,000.00149,905.50131,905.500.9346123,276.171,620,600.00
218,270.00153,630.65135,360.650.8734118,229.241,612,497.00
318,544.05157,448.37138,904.320.8163113,387.301,604,434.52
418,822.21161,360.97142,538.750.7629108,742.131,596,412.34
519,104.54165,370.79146,266.240.7130104,285.811,588,430.28
619,391.11169,480.25150,089.140.6663100,010.731,580,488.13
719,681.98173,691.83154,009.850.622795,909.601,572,585.69
819,977.21178,008.08158,030.870.582091,975.401,564,722.76
920,276.87182,431.58162,154.710.543988,201.421,556,899.15
1020,581.02186,965.00166,383.980.508384,581.181,549,114.65
1120,889.73191,611.08170,721.350.475181,108.481,541,369.08
1221,203.08196,372.62175,169.540.444077,777.371,533,662.23
1321,521.13201,252.48179,731.350.415074,582.121,525,993.92
1421,843.94206,253.60184,409.660.387871,517.241,518,363.95
1522,171.60211,379.00189,207.400.362468,577.471,510,772.13
1622,504.18216,631.77194,127.590.338765,757.731,503,218.27
1722,841.74222,015.07199,173.330.316663,053.181,495,702.18
1823,184.37227,532.14204,347.780.295960,459.131,488,223.67
1923,532.13233,186.32209,654.190.276557,971.131,480,782.55
2023,885.11238,981.00215,095.880.258455,584.861,473,378.64
2124,243.39244,919.68220,676.290.241553,296.211,466,011.74
2224,607.04251,005.93226,398.890.225751,101.211,458,681.69
2324,976.15257,243.43232,267.280.210948,996.061,451,388.28
2425,350.79263,635.93238,285.140.197146,977.111,444,131.34
2525,731.05270,187.28244,456.230.184245,040.861,436,910.68

The IRR of 10.45% is the scenario model output for the table above. No closed-form derivation is reproduced here; the figure is taken verbatim from the model's iterative solve over the cash-flow series and reconciles to NPV ≈ 0 at r = 10.45% within solver tolerance.

4. US import duty / AD-CVD / Section 201 — PENDING

All rows relating to US Section 201 safeguards, anti-dumping/countervailing duty (AD/CVD) orders, or Section 232 measures on PV components are PENDING in this brief. The scenario model does not impute a duty rate; duty incidence must be confirmed at the official HTSUS lookup before procurement lands on a CIF-equivalent price.

How to confirm each row: Section 201 safeguard history on crystalline silicon PV cells/modules is administered by US Customs and Border Protection — see https://www.cbp.gov/ for the current operational guidance.

US import VAT: the United States does not levy a federal value-added tax or goods-and-services tax on imported goods at the federal border. There is no US import VAT row. State sales/use tax may apply to installed equipment once removed from bond and used in the resort state; that is a downstream state-level obligation and is not represented in this TCO.

5. Standards mini-reference (specific revision years)

6. Procurement anchor

For a matched bill-of-materials quotation for this 1 MWp TOPCon + string-inverter resort specification, use the Tradvolt RFQ form:

Request RFQ — Tradvolt green-tech trade desk

7. Audit trail

Tradvolt green-tech trade desk · Reviewed: 2026-09-22 · Article ID: resort-solar-1mwp-us-r9 · For B2B trade audiences.