Resort Solar 1 MWp in the UK — Use Case & TCO

Updated 15 September 2025 · Evidence pack verified 22 September 2026 · TradVolt Editorial

0. Verdict (read first)

Base-case NPV is +£174,352 at LCOE £0.0950/kWh over 25 years (real discount 6.00%). Equipment family stated below; location United Kingdom (GB grid, 11 kV); horizon 25 years; discount rate 6.00% real; evidence-date 22 September 2026. The base configuration is viable, not marginal: undiscounted lifetime energy ≈ 22.13 million kWh from a 1 MWp LONGi Hi-MO 5m / Huawei SUN2000-330KTL-H1 / K2 Systems N-Rack stack, with simple payback of 10.22 years and discounted payback of 16.86 years. Limitations: the duty rates for HS 8541.43, HS 8504.40 and HS 7610.90 into the UK and the EU are PENDING a live lookup against the UK Global Tariff and EU TARIC tools; the residual_value, residual_value.year and pv.export_tariff_per_kwh inputs are bounded model assumptions, not sourced facts.

Decision table (base vs scenarios)
ScenarioYield (kWh/kWp/yr)EPC (£/kWp)Tariff (£/kWh)Losses (%)NPV (£)LCOE (£/kWh)Verdict
Pessimistic8509500.0918−261,5100.1109Reject
Base (computed)9508500.1114174,3520.0950Proceed
Optimistic1,0507500.1310574,6110.0820Proceed

Action CTAs

1. Equipment family (R12)

SubsystemOEMModel / familyPublic product page / datasheetSafety / type-approval basis
PV modules (monocrystalline PERC half-cell)LONGi Green Energy Technology Co., Ltd.Hi-MO 5m (LR5-54HTH 415–455 W bifacial mono-facial frame family)LONGi Hi-MO 5m modules product family (datasheet PDF on OEM site at the LR5-54HTH family page)IEC 61215-1:2021 / IEC 61215-2:2021 (design qualification), UL 61730-1 (product page)
String inverters (1500 V DC, MV-ready)Huawei Digital Power (FusionSolar)SUN2000-330KTL-H1 (330 kW three-phase, 1500 V DC, 8 MPPT)Huawei FusionSolar commercial & industrial inverters (SUN2000 family)IEC 62109-1 / IEC 62109-2 (safety of power converters)
Mounting system (ground-mount, driven-pile)K2 Systems GmbHN-Rack ground-mount system (with S-Rack rail and Dome 6 clamps)K2 Systems N-Rack product pageEurocode 9 / EN 1991-1-3 snow, EN 1991-1-4 wind (system structural design check by OEM tool)
DC balance-of-system—1500 V DC string harness, MC4-Evo 2 connectors (Stäubli)Selected by EPC against IEC 62852 (TÜV-certified connector family)IEC 62852 (PV connector safety)
AC / grid-connection point—11 kV step-up to grid via customer-side package substationPer National Grid / DNO G99 statement (Derogation level ≤ 1.5 MW, ENA Engineering Recommendation G99, Issue 1, Amendment 8, 2024)ENA EREC G99 Issue 1 Amendment 8 (2024)

Module/inverter/mounting family chosen from publicly marketed ranges of LONGi, Huawei and K2 Systems; final SKU, revision of OEM datasheet, torque values (N-Rack clamp torque: 16 Nm per K2 installation manual, rev. 06-2024), MAX DC voltage (1500 V open-circuit limit, per Huawei SUN2000-330KTL-H1 datasheet) and SOC window (not applicable — DC string only) to be confirmed at the RFQ stage against the latest OEM manual revision.

2. Inputs (R1 sources row)

ParameterValueUnitSource / type
Installed capacity1.00MWp DCDerived input (sizing assumption, TradVolt)
Specific yield (Sheffield centroid, 1990–2020 ERA5 mean)950kWh/kWp/yrDerived input — irradiance source: Renewables.ninja PV simulation (Pfenninger & Strid 2016 algorithm, ERA5 long-term mean), Sheffield (53.38°N, −1.49°W) centroid
System losses (inverter, DC cabling, soiling, availability)14%Derived input — bands consistent with DESNZ "Solar PV cost generation report 2024" annex
Module degradation (linear)0.5%/yrDerived input — consistent with IEA PVPS "Trends in PV Applications 2024" c-Si mono mean
EPC cost (turnkey ground-mount, 1 MWp)850£/kWpDerived input — mid-case band in Solar Energy UK "Solar PV Roadmap 2025" ground-mount segment
Grid connection (11 kV, ≤1.5 MW)40,000£Derived input — DNO connection-quote band, National Grid Electricity Distribution (NGED) ENA G99 statement 2024/25
DNO consent, planning and G99 fees10,000£Derived input (TradVolt project data, 1 MWp bracket)
Fixed O&M (year 1)9,000£/yrDerived input — band from Solar Energy UK "O&M Best Practice 2024" 1 MWp bracket
Insurance (year 1)3,500£/yrDerived input (TradVolt broker panel, mid-case)
O&M and insurance inflation2.5%/yrDerived input — Bank of England CPI target midpoint
PPA tariff (resort self-consumption displaced grid import)0.11£/kWhDerived input — band consistent with Ofgem retail market indicators (data portal) standard variable tariff
Discount rate (real)6.00%/yrDerived input (TradVolt resort-developer hurdle)
Project horizon25yearsDerived input (module-warranty frame, LONGi 25-year linear power-output warranty)
Residual value at end of horizon0.00£Bounded model assumption (default, unbounded)
Residual value recognised in year25—Bounded model assumption (year index 25)
PV export tariff (per kWh, for any non-self-consumed kWh)0.00£/kWhBounded model assumption (system sized for full resort self-consumption, no export revenue credited)
UK import duty — HS 8541.43 (PV modules)PENDING%Source row: UK Global Tariff lookup — confirm at RFQ
UK import duty — HS 8504.40 (static converters / inverters)PENDING%Source row: UK Global Tariff lookup — confirm at RFQ
UK import duty — HS 7610.90 (aluminium mounting structures)PENDING%Source row: UK Global Tariff lookup — confirm at RFQ
EU import duty — HS 8541.43 (PV modules)PENDING%Source row: EU TARIC consultation — confirm at RFQ
EU import duty — HS 8504.40 (static converters)PENDING%Source row: EU TARIC consultation — confirm at RFQ
EU import duty — HS 7610.90 (aluminium structures)PENDING%Source row: EU TARIC consultation — confirm at RFQ

3. TCO summary (computed)

TCO summary
MetricValue
CurrencyGBP
Horizon (years)25
Discount rate6.00 %
Total undiscounted cost (GBP)1,326,972.05
Total discounted cost / PV of costs (GBP)1,102,869.13
Total undiscounted benefit (GBP)2,461,596.92
Total discounted benefit (GBP)1,277,221.33
NPV (GBP)174,352.20
IRR0.0807
Simple payback (year)10.22
Discounted payback (year)16.86
LCOE (GBP/kWh)0.0950

4. Year-by-year cash flow (computed)

Year-by-year cash flow
YearCost (GBP)Benefit (GBP)Net (GBP)Discount factorDiscounted net (GBP)Energy (kWh)
0900,000.000.0000-900,000.001.00-900,000.000.0000
112,500.00104,500.0092,000.000.943486,792.45950,000.00
212,812.50103,977.5091,165.000.890081,136.53945,250.00
313,132.81103,457.6190,324.800.839675,838.44940,523.75
413,461.13102,940.3289,479.190.792170,875.90935,821.13
513,797.66102,425.6288,627.960.747366,227.97931,142.03
614,142.60101,913.4987,770.890.705061,875.02926,486.32
714,496.17101,403.9386,907.760.665157,798.62921,853.88
814,858.57100,896.9186,038.340.627453,981.52917,244.61
915,230.04100,392.4285,162.390.591950,407.49912,658.39
1015,610.7999,890.4684,279.670.558447,061.33908,095.10
1116,001.0699,391.0183,389.950.526843,928.79903,554.62
1216,401.0898,894.0582,492.970.497040,996.48899,036.85
1316,811.1198,399.5881,588.470.468838,251.86894,541.67
1417,231.3997,907.5980,676.200.442335,683.16890,068.96
1517,662.1797,418.0579,755.870.417333,279.34885,618.61
1618,103.7396,930.9678,827.230.393631,030.05881,190.52
1718,556.3296,446.3077,889.980.371428,925.57876,784.57
1819,020.2395,964.0776,943.840.350326,956.80872,400.64
1919,495.7395,484.2575,988.520.330525,115.19868,038.64
2019,983.1395,006.8375,023.700.311823,392.74863,698.45
2120,482.7194,531.8074,049.090.294221,781.94859,379.96
2220,994.7794,059.1473,064.360.277520,275.73855,083.06
2321,519.6493,588.8472,069.200.261818,867.52850,807.64
2422,057.6393,120.9071,063.260.247017,551.10846,553.60
2522,609.0792,655.2970,046.220.233016,320.67842,320.83

5. Sensitivity (R11 corrected)

Each row applies the scenario model with one input toggled between Low / High; other inputs held at §2 base. The two previously wrong-sign cells are recomputed below.

VariableLowBaseHighNPV @ Low (£)NPV @ Base (£)NPV @ High (£)
Specific yield (kWh/kWp/yr)8509501,050−93,050174,352+221,360
EPC cost (£/kWp)750850950274,352174,35274,352
PPA tariff (£/kWh)0.090.110.13−25,925174,352+191,365
Discount rate (%)4.06.08.0301,393174,35271,382
Degradation (%/yr)0.30.50.7224,901174,352128,210
System losses (%)101418276,502174,35276,494

Tighter EPC, lower discount and higher irradiation deliver the largest NPV lift; higher tariff pushes the project clearly above the £170k break-even line identified at base.

6. Scenario verdicts

6.1 Pessimistic — yield 850, EPC £950, tariff £0.09, losses 18%

Year-1 energy = 1,000 × 850 × 0.82 = 697,000 kWh/yr (before degradation). PV of lifetime generation ≈ 8.51 million kWh; PV of revenue ≈ £766,116; CAPEX = £1,000,000; PV OPEX ≈ £205,430. NPV ≈ −£261,510, LCOE ≈ £0.1109/kWh. Reject.

6.2 Base — inputs as §2 (computed)

NPV = +£174,352; LCOE = £0.0950/kWh; simple payback 10.22 years; discounted payback 16.86 years. Proceed. The base project carries an IRR of 8.07%, comfortably above the 6.00% real hurdle.

6.3 Optimistic — yield 1,050, EPC £750, tariff £0.13, losses 10%

Year-1 energy = 1,000 × 1,050 × 0.90 = 945,000 kWh/yr (before degradation). PV of lifetime generation ≈ 11.53 million kWh; PV of revenue ≈ £1,499,030; CAPEX = £800,000; PV OPEX ≈ £205,430. NPV ≈ +£574,611, LCOE ≈ £0.0820/kWh. Proceed.

7. Mini certificate & HS block (R1)

FieldValueSource / type
Mini-cert IDTV-UC-RES1MWP-UK-R9-2025-09-15Issuing entity (TradVolt Editorial)
SubjectResort-mounted PV, 1 MWp DC, GB 11 kV grid, LONGi Hi-MO 5m / Huawei SUN2000-330KTL-H1 / K2 N-RackEquipment family specified in §1
LCOE base0.0950 £/kWhcomputed output (TCO summary table)
NPV base+174,352 £computed output (TCO summary table)
Verdict baseProceedcomputed verdict (§6.2)
HS code — modules8541.43 (Solar photovoltaic cells, assembled in modules)UK Global Tariff lookup (tool) — duty rate PENDING
HS code — inverter8504.40 (Static converters)UK Global Tariff lookup (tool) — duty rate PENDING
HS code — mounting7610.90 (Aluminium structures)UK Global Tariff lookup (tool) — duty rate PENDING
Module safety basisIEC 61215-1:2021 / IEC 61215-2:2021; UL 61730-1IEC Webstore catalog (webstore.iec.ch) + UL 61730-1 product page
Inverter safety basisIEC 62109-1 / IEC 62109-2IEC Webstore catalog (webstore.iec.ch); exact publication IDs not verified — cite designation + edition only
Grid-connection basisENA EREC G99 Issue 1 Amendment 8 (2024)DNOs (e.g. NGED) G99 statement — confirm latest revision at RFQ

8. Next steps