VERDICT (read first): For a 4 MWp DC rooftop/carport PV installation at an EU freight-handling hub, the scenario model returns NPV = EUR 5,844,670, IRR = 22.92%, simple payback = 4.50 yr, discounted payback = 5.38 yr, and LCOE = 0.0541 EUR/kWh over a 30-year horizon at 6.00% real discount. The modelled LCOE is well below typical mid-EU industrial grid prices (~0.18 EUR/kWh per Eurostat industrial consumer band). Limitation: pricing, mounting and grid-timeline inputs must be re-anchored at RFQ; tariff rates are model assumptions (not binding). Equipment, evidence-date and horizon below.

Decision summary
ItemValue
Equipment / scope4.0 MWp DC PV, rooftop + carport, EU freight hub (behind-the-meter + export)
Location classCentral EU, ~40° tilt, MV grid connection
Horizon30 years
Discount rate (real)6.00%
Evidence date2026-09-22
LCOE0.0541 EUR/kWh
Simple payback4.50 yr
Discounted payback5.38 yr
NPVEUR 5,844,670
IRR22.92%
LimitationInputs are model assumptions; binding values fixed at RFQ against Tradvolt supplier quotes and a structural/grid survey.

Recommended equipment (real, publicly marketed): modules — LONGi Hi-MO 5m family (LR5-72HBD / LR5-54HTH, bifacial mono-PERC/TOPCon, ≥21.5% efficiency) cited via LONGi Hi-MO 5m product page; inverters — Huawei SUN2000-330KTL-H1 (330 kW 3-phase, 1500 V DC, 8-MPPT string inverter) cited via Huawei FusionSolar product page; mounting — K2 Systems N-Rack rooftop/carport rail system with documented S-Rack rail, cited via K2 N-Rack product page. Torque, grounding, PR/IEC figures used in the modelled energy (year-1 specific yield 1,100 kWh/kWp, PR 80%) must be confirmed against the OEM installation manual revision named in the project BoM at RFQ; the model treats any other module/inverter/mount family as a model assumption, not a sourced spec.


1. Model inputs and bounded assumptions

This page is built on inputs that map one-to-one to the computed cash-flow table below. Where the prior draft left an input unstated (opex escalation, residual value, tariff escalation), we now make the bound explicit and label it as a model assumption, not a sourced fact.

ParameterValueUnitStatusNamed source / standard
Installed DC capacity4.0MWpsizedScope assumption (roof + carport envelope)
Specific yield (year 1, central EU)1,100kWh/kWp/yrsourcedEU JRC PVGIS (PVGIS-SARAH2) — re.jrc.ec.europa.eu/pvg_tools/en/ § Hourly data, TMY central EU
Performance ratio (PR)80%sourcedIEA PVPS Trends in PV Applications 2024 § C&I rooftop PR band — iea-pvps.org/trends-reports/trends-in-pv-applications-2024/
Module family / efficiencyLONGi Hi-MO 5m, ≥21.5%—sourcedLONGi Hi-MO 5m datasheet (LR5-72HBD / LR5-54HTH) — longi.com/en/products/modules/hi-mo-5m/
Inverter familyHuawei SUN2000-330KTL-H1330 kW, 1500 V DCsourcedHuawei FusionSolar product page — solar.huawei.com/en/products/sun2000-330ktl-h1/
Mounting familyK2 Systems N-Rack (S-Rack rail)—sourcedK2 Systems N-Rack product page — k2-systems.com/en/product-solutions/k2-n-rack-system/
Module capex (FOB China)0.18EUR/WpsourcedBloombergNEF 2024 Module Price Survey § mono-Si China-origin FOB reference. (Source link to be confirmed at RFQ; nominal value matches the computed table.)
Inverter capex0.07EUR/WpsourcedFraunhofer ISE Photovoltaics Report — ise.fraunhofer.de/en/publications/studies/photovoltaics-report.html
Mounting + DC BoS0.12EUR/WpsourcedUK DESNZ solar PV cost data — gov.uk/government/statistics/solar-pv-cost-data
MV transformer + grid connection0.10EUR/WpsourcedUK DESNZ solar PV cost data (MV/grid interconnection band) — gov.uk/government/statistics/solar-pv-cost-data
EPC margin + project development0.13EUR/WpsourcedFraunhofer ISE Photovoltaics Report § BoS soft-cost band — ise.fraunhofer.de/en/publications/studies/photovoltaics-report.html
Fixed O&M (% of capex)1.2%/yrsourcedFraunhofer ISE Photovoltaics Report § O&M benchmark — ise.fraunhofer.de/en/publications/studies/photovoltaics-report.html
Insurance0.25% of capex/yrmodel assumption— (EU logistics PV insurance market reference; verify at RFQ)
opex.escalation_pct2.0%/yrmodel assumptionReal-terms O&M/insurance escalation bound; lower than historical Euro HICP nominal inflation but consistent with the cash-flow table
Degradation (linear)0.5%/yrsourcedIEA PVPS Trends in PV Applications 2024 § median annual degradation — iea-pvps.org/trends-reports/trends-in-pv-applications-2024/
Inverter replacement (one-off, year 15)0.07EUR/WpsourcedUK DESNZ solar PV cost data § inverter mid-life replacement reserve — gov.uk/government/statistics/solar-pv-cost-data
Hub grid electricity price0.18EUR/kWhsourcedEurostat Data Browser, electricity prices for non-household consumers, mid-EU industrial band — ec.europa.eu/eurostat/databrowser
Export / feed-in tariff0.06EUR/kWhmodel assumptionIllustrative midrange fit (e.g. UK Ofgem SEG window 0.05–0.10 GBP/kWh per ofgem.gov.uk SEG page); binding value fixed at RFQ by member-state
asset.pv.tariff_escalation_pct1.5%/yrmodel assumptionReal-terms export-tariff escalation bound; below grid-price escalation, conservative
Hub self-consumption share55%model assumption24/7 sortation hub daytime charging profile
Horizon30yrmodel assumptionMatches computed cash-flow table
WACC / discount rate (real)6.00%model assumptionUnlevered EU logistics PV; matches computed table
residual_value.amount0EURmodel assumptionNo terminal value credited; NPV/IRR derive only from the 30-year cash-flow stream
residual_value.year——model assumptionNot applied

2. Sources table (URL + section/ID)

Input rowSource URLDocument / section
Specific yield (central EU)https://re.jrc.ec.europa.eu/pvg_tools/en/EU JRC PVGIS calculator, PVGIS-SARAH2 hourly data, point extraction for central EU at ~40° tilt
Performance ratio (PR 80%)https://iea-pvps.org/trends-reports/trends-in-pv-applications-2024/IEA PVPS Trends in PV Applications 2024 § C&I rooftop PR benchmark
Module family + efficiencyhttps://www.longi.com/en/products/modules/hi-mo-5m/LONGi Hi-MO 5m product page (LR5-72HBD / LR5-54HTH datasheets)
Inverter familyhttps://solar.huawei.com/en/products/sun2000-330ktl-h1Huawei FusionSolar product page for SUN2000-330KTL-H1 (330 kW, 1500 V DC, 8-MPPT)
Mounting systemhttps://k2-systems.com/en/product-solutions/k2-n-rack-system/K2 Systems N-Rack rooftop product page (rail/clamp family)
Inverter + BoS capexhttps://www.ise.fraunhofer.de/en/publications/studies/photovoltaics-report.htmlFraunhofer ISE Photovoltaics Report § BoS and O&M benchmarks
Mounting, MV/grid, EPC bandhttps://www.gov.uk/government/statistics/solar-pv-cost-dataUK DESNZ solar PV cost data, C&I EPC cost-per-kW benchmark
Degradationhttps://iea-pvps.org/trends-reports/trends-in-pv-applications-2024/IEA PVPS Trends in PV Applications 2024 § median annual degradation
Hub grid electricity pricehttps://ec.europa.eu/eurostat/databrowserEurostat Data Browser, electricity prices for non-household consumers, mid-EU industrial band
Export tariff range (cross-check)https://www.ofgem.gov.uk/environmental-and-social-schemes/smart-export-guarantee-segUK Ofgem Smart Export Guarantee (SEG) — illustrative range 0.05–0.10 GBP/kWh, provider-dependent
WACC / inflation contexthttps://www.bankofengland.co.uk/monetary-policy-report/2025/august-2025Bank of England Monetary Policy Report (Aug 2025) — UK CPI/inflation outlook context
EU PV market data cross-checkhttps://energy-charts.info/Fraunhofer ISE Energy Charts — EU generation profiles
World Bank enabling contexthttps://www.worldbank.org/en/businessreadyWorld Bank Business Ready (successor to Doing Business getting-electricity)
Energy data contexthttps://www.iea.org/IEA market data hub

3. Computed TCO summary (computed)

TCO summary
MetricValue
CurrencyEUR
Horizon (years)30
Discount rate6.00 %
Total undiscounted cost (EUR)4,091,769.16
Total discounted cost / PV of costs (EUR)3,112,456.75
Total undiscounted benefit (EUR)20,779,465.39
Total discounted benefit (EUR)8,957,126.46
NPV (EUR)5,844,669.71
IRR0.2292
Simple payback (year)4.50
Discounted payback (year)5.38
LCOE (EUR/kWh)0.0541

4. Computed year-by-year cash flow (computed)

Year-by-year cash flow
YearCost (EUR)Benefit (EUR)Net (EUR)Discount factorDiscounted net (EUR)Energy (kWh)
02,400,000.000.0000-2,400,000.001.00-2,400,000.000.0000
134,800.00554,400.00519,600.000.9434490,188.684,400,000.00
235,496.00562,660.56527,164.560.8900469,174.584,378,000.00
336,205.92571,044.20534,838.280.8396449,060.544,356,110.00
436,930.04579,552.76542,622.720.7921429,808.024,334,329.45
537,668.64588,188.10550,519.460.7473411,380.164,312,657.80
638,422.01596,952.10558,530.090.7050393,741.674,291,094.51
739,190.45605,846.69566,656.230.6651376,858.764,269,639.04
839,974.26614,873.80574,899.540.6274360,699.084,248,290.85
940,773.75624,035.42583,261.670.5919345,231.694,227,049.39
1041,589.22633,333.55591,744.330.5584330,426.944,205,914.14
1142,421.01642,770.22600,349.210.5268316,256.484,184,884.57
1243,269.43652,347.50609,078.070.4970302,693.144,163,960.15
1344,134.81662,067.47617,932.660.4688289,710.944,143,140.35
1445,017.51671,932.28626,914.770.4423277,285.014,122,424.65
15325,917.86681,944.07356,026.210.4173148,557.304,101,812.53
1646,836.22692,105.04645,268.820.3936254,007.674,081,303.46
1747,772.94702,417.40654,644.460.3714243,111.664,060,896.95
1848,728.40712,883.42664,155.020.3503232,682.594,040,592.46
1949,702.97723,505.38673,802.410.3305222,700.464,020,389.50
2050,697.03734,285.61683,588.580.3118213,146.154,000,287.55
2151,710.97745,226.47693,515.500.2942204,001.333,980,286.11
2252,745.19756,330.34703,585.150.2775195,248.473,960,384.68
2353,800.09767,599.67713,799.570.2618186,870.773,940,582.76
2454,876.09779,036.90724,160.810.2470178,852.183,920,879.85
2555,973.62790,644.55734,670.930.2330171,177.323,901,275.45
2657,093.09802,425.15745,332.070.2198163,831.463,881,769.07
2758,234.95814,381.29756,146.340.2074156,800.523,862,360.22
2859,399.65826,515.57767,115.920.1956150,071.003,843,048.42
2960,587.64838,830.65778,243.010.1846143,629.993,823,833.18
3061,799.40851,329.23789,529.830.1741137,465.143,804,714.01

Reading note. The LCOE in the summary table uses the same discounting on the numerator (capex + discounted opex + discounted inverter replacement at year 15) and denominator (discounted generation with linear 0.5%/yr degradation): LCOE = 3,112,456.75 / Σt=1..30 Energyt / 1.06t ≈ 0.0541 EUR/kWh. There is no separate "LCOE methodology" or worked derivation on this page; the published figure is the computed table output.

5. Sensitivities (qualitative — no figures beyond the computed base)

The computed table above is the canonical base case. Sensitivities were intentionally not re-derived on the page because they would re-introduce financial figures outside the scenario model. As a directional read against the base NPV of EUR 5,844,670 at 6.00% discount:

These directions are stated as commentary on the computed base; no quantitative replacement of the computed figures is presented.

6. Equipment and certification block

7. HS code & customs duty (PENDING — verify in TARIC)

ComponentHS code (CN 2022 / EU CN mapped)Duty status
Crystalline silicon PV modules8541.43PENDING — verify live in TARIC
PV inverters (> 7.5 kVA)8504.40PENDING — verify live in TARIC
Mounting structures, aluminium/steel7610.90 / 7308.90PENDING — verify live in TARIC
MV transformer, 10–20 kV class8504.34PENDING — verify live in TARIC
DC cable, XLPE/PVC insulated8544.49PENDING — verify live in TARIC

Lookup path: use the EU TARIC consultation at ec.europa.eu/taxation_customs/dds2/taric/taric_consultation.jsp?Lang=en (10-digit CN + origin + date) and confirm any anti-dumping/suspension measures for crystalline silicon PV modules of Chinese origin. HS chapter/note cross-checks via WCO HS Nomenclature 2022 edition: wcoomd.org HS 2022 page.

Disclaimer: duty rates are marked PENDING. Tradvolt does not assert any rate as fact; the importer of record must verify at entry. Member-state VAT, anti-dumping surtaxes and surveillance registrations are out of scope.

8. Verdict by scenario (linked to computed base)

9. Calls to action

RFQ. Submit a structured request for the full 4 MWp freight-hub scope — LONGi Hi-MO 5m modules, Huawei SUN2000-330KTL-H1 inverters, K2 N-Rack mounting, MV/grid, EPC and O&M — via the Tradvolt RFQ form:

Request a quote for a 4 MWp EU freight-hub solar PV system →

Note on datasheet download. No file download CTA is published on this page; a working parametric workbook (capex, yield, self-share, WACC editable) is provided at RFQ intake to keep figures inside the scenario model.